Title: Utilize CPI
1CPI Customer Task Order Award Process Flow Hill
AFB Only
XP Determination
Prepares One Page Summary
Customer Receives Wing Approval
Organic Resource?
Customer Prepares Draft CET to begin ROM
discussions
Utilize CPI Contractor Support
YES
NO
XP Reviews Package Submits Final Package to PK
Buyer Processes Package Releases RFP (2
Working Days)
Customer Submits Finalized Documents Final PR
Packageto XP
Customer Prepares Draft PR (Form 36) PR
Attachments (See Attach 1)
Review Board XP/Buyer/Customer
Technical Evaluation XP Customer (5 Working
Days)
Contractor Prepares Proposal
PCO Awards Task Order
Customer
XP
Buyer Completes Task Order (5 Working Days)
Team
Buyer/PCO
Contractor
2CPI Customer Task Order Award Process
Flow Non-Hill AFB Sites
Customer Prepares Direct Site (a) MIPR or AF
Form 616 and (b) PR Attachments
Review Board XP/Buyer/Customer
Customer Submits Finalized Documents Final PR
Package to XP
XP Reviews Package Submits Final Package to PK
Customer Prepares Draft CET to begin ROM
discussions
Technical Evaluation XP Customer (5 Working
Days)
Buyer Processes Package Releases RFP (2
Working Days)
Contractor Prepares Proposal (5 Working Days)
PCO Awards Task Order
Buyer Completes Task Order (5 Working Days)
Customer
OO-ALC/XP
OO-ALC CPI Team
OO-ALC Buyer/PCO
Contractor