Title: PROJECTS


1
S O N A
PROJECTS
2
N L A Q
NORTHERN LUZON AGRI-BUSINESS QUADRANGLE
PORT PROJECTS
PORT IRENE PORT PROJECT
SALOMAGUE PORT PROJECT
DINGALAN PORT PROJECT
3
PORT IRENE DEVELOPMENT PROJECT
CEZA CAGAYAN Freeport, Sta. Ana, Cagayan
As of 15 August 2008
IMPLEMENTING AGENCY CEZA
a. CONSTRUCTION OF BREAKWATER
TIMETABLE May 2006 - October 2007
COST P397.261 M - CEZA Funds
  • 96.00 completed when damaged by typhoon.
  • Damaged portion of the breakwater is currently
    being rehabilitated.

a1. REHABILITATION OF THE DAMAGED BREAKWATER
TIMETABLE October 2007 - 2010
COST P78.034 M
  • Rehabilitation works is on-going with 18
    accomplishment and completion is scheduled in
    November 2008.

Aerial View of Port Irene
4
PORT IRENE DEVELOPMENT PROJECT
CEZA CAGAYAN Freeport, Sta. Ana, Cagayan
As of 15 August 2008
IMPLEMENTING AGENCY CEZA
b. PORT REHABILITATION AND PORT DEVELOPMENT
TIMETABLE October 2007 - 2010
COST P3,300 M
  • EPC Contractor of Concessionaire (APIT) is
    awaiting Philexim guarantee to commence with the
    civil works and order of handling equipment.
  • Fabrication of cranes will take about 18 months.
  • By that time, the berth area shall be completed
    and ready for the delivery of the cranes. A
    conveyor loading system is already operational to
    handle bulk cargoes.

Proposed Development
5
SALOMAGUE PORT DEVELOPMENT PROJECT
ILOCOS SUR
As of 15 August 2008
IMPLEMENTING AGENCY LGU-Ilocos Sur
a UPGRADING OF THE EXISTING PORT FACILITIES AND
CONSTRUCTION OF NEW FACILITIES FOR THE SPECIAL
ECONOMIC ZONE AND FREEPORT
COST P5.50 B, ODA/LGU
TIMETABLE To start by 2010
  • The Provincial Government of Ilocos Sur will take
    responsibility over ROW and access road
    construction.
  • Alternative no. 2 was prepared as site for the
    proposed Salomague Port, which is located at
    Municipality of San Juan, Ilocos Sur.
  • As per DBM letter dated 11 August 2008, DOTC's
    request for funding support in the amount of Php
    495 Million for the development of port
    facilities in the Salomague Port was denied
    considering that there is no specific
    appropriation for that purpose in the DOTC FY
    2008 budget.

Location of the Proposed Development
6
South Aurora
South Nueva Ecija
South Tarlac
South Zambales
Pampanga
Polillo Is.
Bulacan
NCR
Rizal
SUBIC BAY port project
Bataan
LUCENA port project
Cavite
Laguna
Quezon
BATANGAS port project
Batangas
Marinduque
CAWIT port project
Or. Mindoro
Occ. Mindoro
LUZON URBAN BELTWAY
O
P
R
T
PROJECTS
7
SUBIC BAY PORT DEVELOPMENT PROJECT
SUBIC, ZAMBALES
As of 15 August 2008
IMPLEMENTING AGENCY SBMA
a. PORT DEVELOPMENT
COST P6.911 B
TIMETABLE 03 May 2004 - 30 June 2007

Duration 1,155 c.d.
  • Substantially completed in March 2008.
  • Currently undergoing rectification and repair of
    punchlisted items of works.
  • Additional Works required by SBMA for inclusion
    in the SBPDP
  • 1. Procurement of Equipment for ISPS requirement.
  • 2. Additional Oil Skimmer and Inflatable Boom
  • 3. Const. of Range Light at Boton Wharf
  • 4. Additional buildings and warehouses for the
    Bureau of Customs
  • 5. PABX
  • 6. Additional Works at the Access Road
  • - SBMA is in discussion with JBIC to secure
    concurrence/no-objection
  • - SBMA to seek approval from NEDA ICC Board

8
SUBIC BAY PORT DEVELOPMENT PROJECT
SUBIC BAY FREEPORT, ZAMBALES
As of 15 August 2008
IMPLEMENTING AGENCY SBMA
9
CENTRAL PHILIPPINES
Camarines Norte
Catanduanes
PORT PROJECTS
Camarines Sur
Albay
PANTAO port project
SAN PASCUAL port project
Sorsogon
CLAVERIA port project
AROROY port project
Northern Samar
Masbate
CAWAYAN port project
Samar
ESPERANZA port project
MARIPIPI port project
Biliran
Eastern Samar
Aklan
Capiz
NAVAL port project
Leyte
DAANBANTAYAN port project
Iloilo
Antique
BOGO port project
Guimaras
Cebu
SIBUNAG port project
Southern Leyte
Bohol
Limasawa Is.
Palawan
Negros Occ.
UBAY port project
LIMASAWA port project
SANTANDER port project
Siargao
Negros Or.
Camiguin
GUINSILIBAN port project
Siquijor
BALBAGON port project
SIQUIJOR port project
Dapitan
10
CAWAYAN PORT IMPROVEMENT PROJECT
BRGY. MAHAYAHAY, CAWAYAN, MASBATE
As of 15 August 2008
IMPLEMENTING AGENCY PPA
ROCK CAUSEWAY BACK-UP AREA, RC PLATFORM, RORO
RAMP BREASTING DOLPHIN, MOORING, FENDERING
PORT LIGHTING SYSTEM
COST P42.95 M
TIMETABLE May 2006 - May 2007
Rev. TCD 27 May 2006 - 31 May 2008
Project Duration 360 c.d.
Rev 432 c.d.
  • The project is substantially completed with an
    accomplishment of 99.964 as of 25 July 2008.
    However, some completed items of work had been
    damaged by the recent typhoon "Frank" last 20
    June 2008. Extent of damages is still being
    assessed.

11
ESPERANZA PORT DEVELOPMENT PROJECT
ESPERANZA, MASBATE
As of 15 August 2008
IMPLEMENTING AGENCY PPA
CONSTRUCTION OF RORO RAMP ( 9M x11M ) PLATFORM -
( 43.3M x 6M ) ROCK CAUSEWAY - ( 280M x 60M )
BACK-UP AREA - (4,750 SQ.M.) PTB - ( 464 SQ.M. )
COST P133.69 M
TIMETABLE Feb 2007 - Sept 2008
Rev. TCD 19 July 2008
Project Duration 360 c.d.
Rev 437 c.d.
  • The project is 24.849 completed, behind by
    35.896 or a delay of 157 days based on the
    approved contract schedule.
  • However, should the unworkable sea condition be
    considered the negative slippage will be reduced
    to 7.977.
  • Failure to mobilized the fully-loaded barge with
    materials from Ormoc due to rough sea condition
    caused the delay in the project.
  • The contractor had been advised to undertake
    appropriate measures to catch up with the
    schedule.

12
AROROY PORT DEVELOPMENT PROJECT
AROROY, MASBATE
As of 15 August 2008
IMPLEMENTING AGENCY PPA
CONSTRUCTION OF RORO RAMP ( 9M x11M ) BACK-UP
AREA - ( 4,449 SQ.M.)
COST P96.47 M
TIMETABLE Nov 2006 - Apr 2008
Rev 24 Jan 2007 - 17 May 2008
Project Duration 360 c.d.
  • The project is 96.893 completed as of 25 July
    2008.
  • Punchlisting inspection of the project has
    already been conducted on 23-25 July 2008.

ON-GOING RECLAMATION OF BACK-UP AREA
13
CLAVERIA PORT DEVELOPMENT PROJECT
CLAVERIA, BURIAS ISLAND, MASBATE
As of 15 August 2008
IMPLEMENTING AGENCY PPA
CONSTRUCTION OF RORO RAMP ( 9M x11M ) ROCK
CAUSEWAY - ( 114M x 9M ) BACK-UP AREA - (2,000
SQ.M. PTB - ( 464 SQ.M. )
COST P125.15 M
TIMETABLE Apr 2007 - Sept 2008
Rev 07 May 2007 - 08 July 2008
Project Duration 360 c.d.
rev 431 c.d.
  • The project is 71.50 completed as of 25 July
    2008, behind by 4.592 due to the revision of
    plans to suit the actual field condition due to
    the existence of rock fill materials within and
    beyond the limit of the project.
  • Partial suspension of the project was issued on
    the affected activities. The existence rock fill
    will be incorporated in the project thru
    Variation Order.and the tentative completion date
    will be on 01 November 2008 once approved.

14
SAN PASCUAL PORT DEVELOPMENT PROJECT
SAN PASCUAL, BURIAS ISLAND, MASBATE
As of 15 August 2008
IMPLEMENTING AGENCY PPA
CONSTRUCTION OF RORO RAMP ( 9M x11M ) BACK-UP
AREA - ( 2,000 SQ.M.) and PTB
TIMETABLE Apr 2007 - Sept 2008
Rev 26 July 2007 - 31 July 2008
COST P42.84 M
Project Duration 300 c.d.
  • The project is 73.790 completed as of 25 July
    2008, behind by 8.417 based on the proposed
    revised construction schedule
  • The delay is due to unfavorable result of the
    test pile driven.
  • The required bearing power was not attained, thus
    an additional length of test is necessary.
    Likewise, the pile length of regular piles will
    be increased to conform to the actual pile
    driving result.
  • The increase in pile length will be covered by a
    Variation Order with a corresponding time
    extension.
  • Should the proposed variation be approved, the
    tentative completion date will be on 20 November
    2008.

15
MARIPIPI PORT PROJECT
MARIPIPI ISLAND, BILIRAN
As of 15 August 2008
IMPLEMENTING AGENCY PPA
CONSTRUCTION OF RORO RAMP ( 9M x11M ) BACK-UP
AREA - (1,700 SQ.M.), PTB - ( 447 SQ.M. )
COST P49.10 M
TIMETABLE Apr 2007 - Sept 2008
Rev 15 Mar 2007 - 07 July 2008
Project Duration 300 c.d.
  • The project is substantially completed with an
    accomplishment of 98.50. However, portion of the
    completed structure has been damaged by Typhoon
    "FRANK" on 20 June 2008.
  • The damaged portion is now under restoration.
    Suspended activities will resume upon completion
    of the restoration works.
  • Expected completion date is on 31 October 2008.

16
GUINSILIBAN PORT PROJECT
GUINSILIBAN, CAMIGUIN
As of 15 August 2008
IMPLEMENTING AGENCY PPA
a. PORT DEVELOPMENT PROJECT
COST P63.23 M
  • Updating of Program of Work on-going.
  • Implementation schedule of the project is in
    December 2008.

b. CONSTRUCTION OF PTB
COST P20.0 M
  • On-going. POW under evaluation.
  • Programmed for implementation in CY 2010,
    however, early implementation may be considered
    once fund is available.

17
SANTANDER PORT DEVELOPMENT PROJECT
SANTANDER, CEBU
As of 15 August 2008
IMPLEMENTING AGENCY CPA
  • he Provincial Government of Cebu will implement
    the project instead of the Cebu Ports Authority
    (CPA) as per 4th National Infra Forum.
  • CPA has the intension to implement the project
    but the Governor of Cebu has the plan to do the
    same.

Santander Port Proposed Site
18
DAANBANTAYAN PORT DEVELOPMENT PROJECT
MAYA, DAANBANTAYAN, CEBU
As of 15 August 2008
IMPLEMENTING AGENCY CPA
a. CONSTRUCTION OF RORO RAMP
COST P15.0 M
TIMETABLE 25 March 2007 - 21August 2007
Project Duration 150 c.d.
  • The project is 66.80 complete as of 31 May 2008.
    All field operations were stopped for the
    meantime, waiting for the result of road
    right-of-way negotiations for the proposed access
    road. (NO UPDATED REPORT)

b. Access Road and Reclamation
  • This project is a counterpart of the Municipality
    of Daanbantayan and not yet started.

19
Dinagat Island
MINDANAO AGRI-BUSINESS
Surigao del Norte
PORT PROJECTS
Agusan Del Norte
Surigao del Sur
Misamis Or.
CAGAYAN DE ORO Port project
Agusan Del Sur
Misamis Occ.
Bukidnon
Lanao Del Norte
Zamboanga del Norte
Lanao Del Sur
Zamboanga del Sur
Davao
Zamboanga Sibugay
Cotabato
Davao City
Maguindanao
Davao Or.
Davao del Sur
Sultan Kudarat
Basilan
South Cotabato
Sarangani
Sulu
DAVAO Port project
Tawi-Tawi
20