Title: Superintendents Proposed Capital Improvement Plan 20082018
1Superintendents Proposed Capital Improvement
Plan 2008-2018
2Sorting Out the Pieces
3What is the Capital Improvement Plan (CIP)?
- Superintendents recommended CIP budget to the
School Board - Intended to convey the school systems needs
- Spans a ten-year period
- First five years cost information included
- Fluid document that is updated annually
4What Types of Projects Are in the CIP?
- Permanent new or expanded facilities
- Remodeling or renovation of facilities
- Site acquisition
- Mechanical/maintenance projects
- Architectural/engineering design work
5Evaluating Capital Projects(Facility Condition
Inspections)
6Why Does the CIP Change Annually?
Major repairs, maintenance, and renovations
Housing info
Student population
7New Homes Built 2002-2006
Does not include age-restricted units
8Home Sites Available(by Middle School Planning
Area)
Total 7,625
Source CPS Planning Development Department,
7/07
9Student Enrollment Change 2001-2006(by Middle
School Planning Area)
Total 1,487
IRM 38
OSM 446
JMS/WBM 563
CWM/GRM (-52)
DCM/HOM 96
GBM 62
HMS 334
10Percent of Enrollment Change1997-2007
2 years of enrollment decline
23 consecutive years of enrollment growth
11Changing Enrollment PatternsKindergarten vs.
12th Grade Enrollment
2,989
2,564
2,399
2,244
12Enrollment Influences Outlook
- Recent Influences
- Number of 12th graders exiting has grown faster
than the number of Kindergartners entering - Although CPS declined in overall enrollment, 14
schools showed an increase in enrollment from
last year - Recent enrollment decline is not unique to CPS
- Norfolk declined 5 of 5 years
- Portsmouth declined 4 of 5 years
- Virginia Beach declined 4 of 5 years
- Local/regional/national housing market has cooled
13Enrollment Influences Outlook (Continued)
- Future Outlook
- Chesapeake population is expected to grow by 30
by 2030 - Chesapeake is expected to gain nearly 60,000 jobs
by 2034 - Residential development has been shifting from
large tract single family to multi-family
housing, infill development, mixed-use projects,
and age-restricted housing.
Source The Hampton Roads Planning District
Commission, 6/07
14Examining the Pieces Are Our Schools Overcrowded?
15Elementary School Zones Over 90 of Capacity
16Middle School Zones Over 90 of Capacity
Once the replacement school for OSM is
completed, OSM will be less than 100 of capacity.
17High School Zones Over 90 of Capacity
18Portables by Elementary School Zones
8 WBP/WBI
5 TME
- 15/28 elementary schools have portables
- 69 portables total
2 GTP
13 CHT
6 SWE
18 BMW/CWI
4 DCE
1 GRP
2 BRP
2 GBP
2 DCCE
1 GFE
5 SEE
Note Includes Instructional and
Non-Instructional Portables
19Portables by Middle School Zones
- 4/10 middle schools have portables
- 90 portables total
15 IRM
31 OSM
15 CWM
29 HMS
Note Includes Instructional and
Non-Instructional Portables
20Portables by High School Zones
- 6/7 high schools have portables
- 3/7 high schools have 20 portables
- 123 portables total
36 WBH
28 IRH
7 DCH
19 OSH
13 GBH
20 HHS
Note Includes Instructional and
Non-Instructional Portables
21Totals by Grade Level
Includes instructional and non-instructional
portables
22Puzzle Basics Infrastructure Projects
23Why Are Major Mechanical/Maintenance Repairs
Needed?
- Systems and parts have a finite life
- Scarcity or unavailability of older parts
- Increased operational costs
- Increased operational failures (example no heat
more frequently and for longer periods) - No temporary fix for failed roofs or HVAC systems
24Age of Roofs(15-20 Year Life Span)
CIP includes 19 roof replacements
25Age of HVAC Systems(15-Year Life Span)
CIP includes 26 HVAC replacements
26Major Mechanical/Maintenance Projects55,144,400
or 15 of Total CIP
27Other Major Mechanical/Maintenance Projects
- Mixing box replacements at IRH, IRM and WBM
- Repaving at PORT, DCE, DCH, and WBP
Approximately 13 million is currently available
for major mechanical and maintenance projects.
28Filling in the Puzzle Construction Land
Projects
29School Projects 306,527,500 or 82 of Total
CIP Budget
- Design and construct an additional high school in
the Elbow Road/Centerville Turnpike North area - Design and construct a middle school to relieve
HMS - Design and construct an additional elementary
school in the BMW/CWI/GRP/GRI area - Design and construct an elementary school in the
DCE/DCCE area - Design and construct an addition/renovation to CWM
30School Projects (Continued)306,527,500 or 82
of Total CIP Budget
- Design and construct an addition/renovation to
IRH - Construct an addition to and renovation of WBH
- Design and construct addition/renovation to CHT
- Design an addition/renovation to GBP
- Design an addition/renovation to CWI
- Design an addition/renovation to IRM
31Land Acquisition and Other Projects10,707,500
or 3 of Total CIP Budget
- Land for elementary school in the DCCE/DCE area
- Renovate DCM and GBM stadiums
- Parking/storage facility for buses
- Renovate the former RE-ED Center
- Drainage improvements at CWM
- Replace tennis courts at GBH
32Nearly Complete the Last Two Pieces
332008-2013 Five-Year Grand Total(Current Dollars)
342008-2013 Five-Year Grand Total(Inflated Dollars)
35Additional Puzzle Pieces
Thurs., Nov. 1, 2007 700 pm _at_ DCHS
Public Hearing Work Session
Mon., Nov. 26, 2007 700 pm _at_ SAB
Public Hearing, Work Session
Final Action
Mon., Nov. 5, 2007 700 pm _at_
SAB Public Hearing Work Session
36(No Transcript)
37(No Transcript)
38(No Transcript)
39(No Transcript)
40Portable Use
- Instructional Non-Instructional
- CPS Total 279 20
- Two Examples
- Instructional Non-Instructional
- GRP 0 1 (P.E. storage)
- OSM 29 2 (cafeteria, storage)