Title: PowerPoint Presentation Proposed Active Caps
1Implementation of Anacostia RiverComparative
Validation of Innovative Capping Technologies
Status Report to AWTA
- Danny D. Reible
- W. David Constant
- Hazardous Substance Research Center/South
- Southwest, Louisiana State University
- Yuewei Zhu
- Horne Engineering Services, Inc.
- September 30, 2003
2Location Map
3Summary of Field Investigations
- Geophysical investigation -bathymetry, sonar,
magnetometry - Sediment profile imaging (SPI) survey
- Sampling of the sediment - contaminant concent.
and profiles - River current velocity via Acoustic Doppler
Current Profiler - Multicoring for sediment radionuclide
characterization. - Geotechnical to evaluate sediment stability and
consolidation behavior loads imposed by the
active cap materials - Benthic investigation
- Draft Report 9/26/03 w/o seepage or dating work
- Seepage Tests (September 2003)
- Objective Establish baselines for placement and
assessment
4Bathymetry Map
5Geophysical Survey Findings
- Gently undulating surface with few surface
irregularities. River depths from 5 near shore
to 20 at southern bound. - Fine grained sediments likely ranging from soft
aqueous silts muds to aqueous fine grained sand
silt. Sonar mosaics were superimposed on the
depth contours. - Sonar mosaics are representative of features
extending above the river bed (dark), while light
areas represent shadows behind features or
surface depressions. - Subbottom penetration of the profiler system was
restricted due to the presence of gaseous-type
sediments in the near-subsurface. - Organically derived gases in sediments is not
uncommon and often characterizes sediments in
upland rivers, bays and estuaries.
6SPI Image
- The sediment was primarily fine silt and
clay sediment - Biogenic activity of epifauna and infauna was
not a predominant factor in structuring surface
sediment - There was no evidence at Areas 1 that SAV were
present
Bubble
7Sediment Contamination Delineation
- 13 EPA priority metals
- PAHs
- PCBs (both aroclors and congeners)
- Pesticides
- Total phosphorus
- TKN
- TOC
- Acid volatile sulfide/simultaneously extracted
metals
8PAHs Contour Map
9Geotechnical Investigation
- Five deep borings ranging from 21 feet to 27 feet
- Samples collected for engineering properties
testing - Vane shear tests performed at adjacent offset
location - Inferred subsurface profile defining 5 sediment
strata
10Inferred Subsurface Profile
11Field River Flow Velocity Measurement
- Workhorse Sentinel ADCP used
- 4 tide stages (maximum flood, maximum ebb, high
slack, and low slack). - Variability of magnitude between the four tide
stages was not significant. - Median magnitudes for the averaged ensemble data
from 0.13 ft/s for high slack to 0.21 ft/s for
maximum flood. - Maximum magnitudes ranged from 0.64 ft/s at high
slack to 1.29 ft/s at maximum ebb
12Averaged Velocities During Maximum Flood
13Radionuclide Testing Preliminary Results
14Benthic Survey Preliminary Results -1
15Benthic Survey Preliminary Results -2
16Seepage Test Field Photos
17Active Caps for Demo
- AquaBlokTM with EPA SITE
- Coke breeze CMU/CETCO
- Apatite - UNH
- Sand (for evaluation purpose)
- Sevenson Environmental
18Pilot Study Cell Considerations
- Within 200x300, each cap is 100x100
- Three active caps plus a traditional sand cap
- A control (blank) cap.
19Pilot Study Cell Area Selection Considerations
- Known elevated contamination
- Identified for potential remedial action by the
AWTA - Outside of the navigation channel
- A relative slow flow segment of the Anacostia
-confirmed with the field measurements - Pilot study cells footprint has minimal slope (lt
4)
20Pilot Study Cell Layout
21Measured Heavy Metals in Coke Leachate and
corresponding Criterion Maximum Concentrations
(CMC)1
Other Elements Detected in Coke Leachate (DI, PW)
and Anacostia Porewater
a. Porewater generated by equilibrating DI water
with Anacostia Sediment
a. Metals with detection limits exceeding CMC
values. b. Criterion Maximum Concentrations (CMC)
were obtained at on the EPA website (1) and
defined as an estimate of the highest
concentration of a pollutant in freshwater, to
which an aquatic community can be exposed briefly
(acute limit) without resulting in an
unacceptable effect.
22Cap Thickness Considerations
- A thin composite cap consists of a component of
materials in which the reactive cap materials
will be placed first. Once placed, these
reactive cap materials will be overlain by a
clean sand layer. - A nominal 6-inch thick sand layer atop the active
cap materials. - An estimated 6-inch thick reactive cap layer
(varying thickness based on the feasibility
studies). - A total of 12- to 14-inch thick cap thickness
expected.
23Permit Activity
- U.S. Corps of Engineers
- National Park Service EA in Public period
October 24..\NPS EA\Capping Project EA.pdf - DC EHA
- GSA Sevenson Environmental
24Construction Planning
- Negotiated with the vendors to purchase cap
materials - Working with Sevenson Environmental Services on
placement/handling/staging with GSA - Cap placement now planned to start in
October/November 2003
25Cap Placement Considerations
- The cap material will be placed with a clamshell
bucket in a manner that provides the necessary
layer thickness while minimizing resuspension of
the contaminated sediment - The actual method of placement could be modified
if necessary during the cap placement depending
on actual conditions encountered in the field.
Mat for Coke Breeze - Silt Curtain will be used during the cap
placement. - Cap thickness will be monitored using instrument
and manual methods. - Required water quality monitoring will be
performed accordingly.
26Plans and Scheduling -1
- September - baseline sampling of seepage rates in
vicinity of test area completed. - Oct/Nov. placement of 4 technologies with a 6
layer of sand on each - Aquablok with SITE
- Apatite for metals sequestration
- Coke Breeze organic sequestration
- Placement with laminated mat sized/washed
27Plans and Scheduling - 2
- Issues at hand
- Program in review by Corps, DC and NPS EA
- Some delay with materials/permitting so now
planning on mid-October mobilization - Addressing GSA Concerns
- Placement Windows
- Done before Thanksgiving
- Do right after Thanksgiving finish by mid-Dec.
- Or we are in January?
- Questions?