Title: Environmental Groups
1San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project Contractor
Information Meeting Construction Contract
04-0120F4 November 30, 2005
2- Jon Tapping
- Interim SFOBB East Span
- Project Manager, Caltrans
-
3- Dan McElhinney,
- District 4 Director, Caltrans
4DVBE - Civil Rights
- Robert Padilla
- Statewide Small Business Liaison for Caltrans,
Office of Civil Rights - Disabled Veteran Business Enterprise (DVBE) goal
- Prime Contractors commitment
5Technical Issues
- Brian Maroney
- SFOBB East Span Technical Manager, Caltrans
6Guidelines for QA
- Please submit questions in writing on cards
provided - Any answers provided today are preliminary and
not considered final until posted on the bidder
inquiry web site - Bidder Inquiry website http//www.dot.ca.gov/d
ist4/construction/Inquiries/04-0120F4_inquiry.html
- Future inquiries may be addressed to the Duty
Senior - email Duty_Senior_District04_at_dot.ca.gov
- Mailing address P.O. Box 23660, Oakland, CA
94623-0660 - Fax number (510) 622-1805
- All inquiries must include the contract number
(04-0120f4)
7- Mike Whiteside
- Upcoming Addenda
8Upcoming Addendum Items
- Addendum 4, early December
- CJP to PJP
- Remove Unsatisfactory Progress Specification
- Add Temp. Tower AE AW final Designs
- Use of Electorslag Welding
- Pre-Assembly Requirements Reduced
- Constructability Refinements/Improvements
Conflict Resolution
9Upcoming Addendum Items
- Addendum 5, late December
- Performance specifications for castings
- E2 Shear Key/Bearing Alternative
- Hinge K Pipe Beam Fabrication
- Hinge K Closure
- Availability of North Side of Oakland Approach
10Upcoming Addendum Items
- Addendum 6, early January
- Miscellaneous clean-up issues
- Constructability Refinements/Improvements
Conflict Resolution
11 12SAS Schedule
13SAS Schedule Working Drawings
14SAS Schedule
- Changes since last advertisement
- Increased bidder compensation
- Revised CRIP specifications to provide
non-compensable time for CRIP submittal - Reduction in time required for Caltrans to review
and approve weld repairs - Allowing repairs to be made after erection
- E2/T1 availability earlier in the contract, more
time between E2/T1 availability and Milestones 2,
3 and 4
15- Marwan Nader
- Temporary Tower Design Example
-
16TEMPORARY TOWER DESIGN EXAMPLE
17(No Transcript)
18Tower Configurations
19(No Transcript)
20(No Transcript)
21DESIGN CRITERIACodes, Standards, Specifications
- Applicable Codes/Specifications
- CalTrans Standard Specifications, 1999
- CalTrans Special Provisions, Contract 040120F4
- CalTrans Falsework Manual, Rev. 32, November 2001
- AISC-LRFD, 1999 for rolled sections
- API RP2A-LRFD, July 1993 for tubular sections and
connections (and pipe piles) - AASHTO-LRFD Bridge Construction Specification,
2nd Ed. (Concrete only) - ANSI/ASCE 795 (Wind loads only)
22Independent Loads Cases
- Dead Load
- Live Load
- Vessel Impact
- Earthquake
- 1.0X-direction 0.3 Y direction
- 0.3 X-direction 1.0 Y direction
- -1.0 X-direction 0.3 Y direction
- 0.3 X-direction - 1.0 Y direction
- Wind Load
- Wind, Wave and Current
23(No Transcript)
24(No Transcript)
25(No Transcript)
26Wind, Wave and Current
- Wind
- ASCE 7-95 specifies an 85MPH Wind Gust _at_ 10m
- Section 10-1.59 of the Special Provisions
specifies a 100 MPH 3-sec gust _at_ El. 50m. - The 100MPH Wind Gust velocity stated in the
Special Provisions govern. - The importance factor is 1.15 per revised Special
Provisions - The exposure coefficients are for exposure D
(open water) - The gust factor is 0.85 in accordance with ASCE
Section 6.6 - The shape factor on projected flat surface of the
box girder was 1.5 (ASCE Table 6-8), and 0.8 for
the tubular tower structures (ASCE Table 6-9). - Wave
- 2m high, 6sec wave per revised Special Provisions
- Drag and inertia coefficients are 0.65 and 1.6
(ref API RP2A), respectively - Current
- 3-knot surface current was conservatively
assumed(Note Vessel Collision Report indicates
a uniform 2 knot design current for Impact
design). - The surface current velocity profile with depth
was developed utilizing a 1/7th power
distribution.
27(No Transcript)
28Construction Loads/Stages
- 1. Individual deck lifts 1 thru 9 on the
appropriate towers - 2. In- fill / heavy lifts 1, 2, 3 4 on the
appropriate towers - 3. Connecting the deck sections together in the
longitudinal direction - 4. Connecting the cross beams in the transverse
direction - 5. Connecting the deck sections to W2 and E2 cap
beams - Tower C
- Temporary Tower (TT)
- TT plus Deck Lift 1 (830 Tonnes) on 4 bearing
pads - TT plus Deck Lift 4 (459 Tonnes) on 4 bearing
pads - TT plus Deck Lift 4 plus half of Heavy Lift 1
(830/2 415 Tonnes) total 875 T - Envelope of Vertical Forces (see Table 1 on Sheet
Construction Load No. 1) - Tower G
- Temporary Tower (TT)
- TT plus Deck Lift 9 (892 Tonnes) on 6 bearing
pads - TT plus Deck Lift 9 plus half of Heavy Lift 3
(1285/2 643 Tonnes) tot al 1535 T - TT plus Deck Lift 9 plus half of Heavy Lifts 3
4 2177 T - Envelope of Vertical Forces (see Table 1 on Sheet
Construction Load No. 1)
29Load Combinations
- 1.4 DL
- 1.1 DL 1.3 LL
- 1.0 DL 1.0 LL 0.5 Wind 1.0 Current 1.0
Impact (Vessel) - 1.0 DL 1.0 LL 1.0 EQ
- 1.0 DL 1.0 LL 1.3Wind 1.3Wave 1.3Current
30Tower C
- Tubular steel structure, trucked and assembled on
site with the use of a crawler crane - All tower and truss joints are to be bolted
- Leg segments bolted together with splice flanges
located near inflection points - Pre-installed gusset plates welded to legs for
bracing members to be bolted onto - Gusset plates actually penetrate through the legs
to provide load continuity through the joints
31(No Transcript)
32(No Transcript)
33(No Transcript)
34Tower G
- 6- leg tubular steel jacket structure, 65m (213
ft) high - 14m x 30m (46 ft x 98 ft) footprint at the top,
to match bearing locations - Pin piles driven through the jacket legs
- The jacket base plan dimensions provide the same
overturning resistance in both orthogonal
directions - Bay height chosen to provide efficient diagonal
bracing - Cross braced to provide ductility
35(No Transcript)
36(No Transcript)
37(No Transcript)
38(No Transcript)
393D View of Towers ABC Model
40Mode 1 (T0.78 sec)
41Y Spectral Displacement (5.62 cm at top of Tower
C) (Transverse)
42Wind Displacement (0.8 cm at top of Tower C)
43Transverse Pushover at 115mm
44Transverse Pushover to 115mm
Shear reductions are due to compression member
buckling (tension members take over)
453D View of Tower C Model as a separate structure
46Mode 2 (T1.43 sec)
47Y Spectral Displacement (7.63cm at top of Tower)
(Transverse)
48Wind Displacement (1.06cm at top of Tower)
49Transverse Pushover at 300mm
50Transverse Pushover to 300mm, Force-Displacement
Curve (76mm Seismic Demand)
Shear reductions are due to compression member
buckling (tension members take over)
51Tower C Conclusions
- Combined structure is stiffer lower period
- Produces larger forces
- Separate structure is more flexible higher
period - Produces lower forces
- Consider Base Isolation System
- (Slip plane at bearing level with retainers)
523D View of Tower G Model
533D View of Tower G alone
54(No Transcript)
55Mode 2 (T1.36 sec)
56IMPACTY Displacement (Y4.5 cm at top of tower,
Y11.5 cm at point of impact)
57Y Spectral Displacement (9.7 cm at top of Tower)
58Wind Displacement (4.4 cm at top of Tower)
59Transverse Pushover Displaced Shape at X0.45 m
60Transverse Pushover Curve to 0.45 m
No member buckling present at this load level
piles govern capacity
613D View of Tower G Model Pinned at the Base
62Transverse Pushover Displaced Shape at X1.0 m
63Transverse Pushover Curve to 1.0 m
Shear reductions are due to compression member
buckling (tension members take over)
64(No Transcript)
65(No Transcript)
66Tower G Conclusions
- Provide Vessel Impact energy absorption
system(reduces overall demand on tower) - Increase pile diameter and/or reduce bracing size
(to provide more tower ductility)
67It should be noted that this Design Example is a
first iteration in the design process and
requires further refining in order to meet the
full intent of the specified design requirements.
- As noted, there are several approaches to meet
the requirements of the Drawings and Special
Provisions.
68- Chris Traina
- Cash Flow Analysis
-
69Early Pay Items Analysis
70Steel Payments
71Cash Flow Analysis
72- Rick Morrow
- Outstanding Bidder Inquiries
- Tower Mock-Up
-