Environmental Groups - PowerPoint PPT Presentation

1 / 72
About This Presentation
Title:

Environmental Groups

Description:

Statewide Small Business Liaison for Caltrans, Office of Civil Rights ... steel structure, trucked and assembled on site with the use of a crawler crane ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 73
Provided by: pb275
Category:

less

Transcript and Presenter's Notes

Title: Environmental Groups


1
San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project Contractor
Information Meeting Construction Contract
04-0120F4 November 30, 2005
2
  • Jon Tapping
  • Interim SFOBB East Span
  • Project Manager, Caltrans

3
  • Dan McElhinney,
  • District 4 Director, Caltrans

4
DVBE - Civil Rights
  • Robert Padilla
  • Statewide Small Business Liaison for Caltrans,
    Office of Civil Rights
  • Disabled Veteran Business Enterprise (DVBE) goal
  • Prime Contractors commitment

5
Technical Issues
  • Brian Maroney
  • SFOBB East Span Technical Manager, Caltrans

6
Guidelines for QA
  • Please submit questions in writing on cards
    provided
  • Any answers provided today are preliminary and
    not considered final until posted on the bidder
    inquiry web site
  • Bidder Inquiry website http//www.dot.ca.gov/d
    ist4/construction/Inquiries/04-0120F4_inquiry.html
  • Future inquiries may be addressed to the Duty
    Senior
  • email Duty_Senior_District04_at_dot.ca.gov
  • Mailing address P.O. Box 23660, Oakland, CA
    94623-0660
  • Fax number (510) 622-1805
  • All inquiries must include the contract number
    (04-0120f4)

7
  • Mike Whiteside
  • Upcoming Addenda

8
Upcoming Addendum Items
  • Addendum 4, early December
  • CJP to PJP
  • Remove Unsatisfactory Progress Specification
  • Add Temp. Tower AE AW final Designs
  • Use of Electorslag Welding
  • Pre-Assembly Requirements Reduced
  • Constructability Refinements/Improvements
    Conflict Resolution

9
Upcoming Addendum Items
  • Addendum 5, late December
  • Performance specifications for castings
  • E2 Shear Key/Bearing Alternative
  • Hinge K Pipe Beam Fabrication
  • Hinge K Closure
  • Availability of North Side of Oakland Approach

10
Upcoming Addendum Items
  • Addendum 6, early January
  • Miscellaneous clean-up issues
  • Constructability Refinements/Improvements
    Conflict Resolution

11
  • Michael Stone
  • Schedule

12
SAS Schedule
13
SAS Schedule Working Drawings
14
SAS Schedule
  • Changes since last advertisement
  • Increased bidder compensation
  • Revised CRIP specifications to provide
    non-compensable time for CRIP submittal
  • Reduction in time required for Caltrans to review
    and approve weld repairs
  • Allowing repairs to be made after erection
  • E2/T1 availability earlier in the contract, more
    time between E2/T1 availability and Milestones 2,
    3 and 4

15
  • Marwan Nader
  • Temporary Tower Design Example

16
TEMPORARY TOWER DESIGN EXAMPLE
  • November 18, 2005

17
(No Transcript)
18
Tower Configurations
  • Tower C
  • Tower G

19
(No Transcript)
20
(No Transcript)
21
DESIGN CRITERIACodes, Standards, Specifications
  • Applicable Codes/Specifications
  • CalTrans Standard Specifications, 1999
  • CalTrans Special Provisions, Contract 040120F4
  • CalTrans Falsework Manual, Rev. 32, November 2001
  • AISC-LRFD, 1999 for rolled sections
  • API RP2A-LRFD, July 1993 for tubular sections and
    connections (and pipe piles)
  • AASHTO-LRFD Bridge Construction Specification,
    2nd Ed. (Concrete only)
  • ANSI/ASCE 795 (Wind loads only)

22
Independent Loads Cases
  • Dead Load
  • Live Load
  • Vessel Impact
  • Earthquake
  • 1.0X-direction 0.3 Y direction
  • 0.3 X-direction 1.0 Y direction
  • -1.0 X-direction 0.3 Y direction
  • 0.3 X-direction - 1.0 Y direction
  • Wind Load
  • Wind, Wave and Current

23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
Wind, Wave and Current
  • Wind
  • ASCE 7-95 specifies an 85MPH Wind Gust _at_ 10m
  • Section 10-1.59 of the Special Provisions
    specifies a 100 MPH 3-sec gust _at_ El. 50m.
  • The 100MPH Wind Gust velocity stated in the
    Special Provisions govern.
  • The importance factor is 1.15 per revised Special
    Provisions
  • The exposure coefficients are for exposure D
    (open water)
  • The gust factor is 0.85 in accordance with ASCE
    Section 6.6
  • The shape factor on projected flat surface of the
    box girder was 1.5 (ASCE Table 6-8), and 0.8 for
    the tubular tower structures (ASCE Table 6-9).
  • Wave
  • 2m high, 6sec wave per revised Special Provisions
  • Drag and inertia coefficients are 0.65 and 1.6
    (ref API RP2A), respectively
  • Current
  • 3-knot surface current was conservatively
    assumed(Note Vessel Collision Report indicates
    a uniform 2 knot design current for Impact
    design).
  • The surface current velocity profile with depth
    was developed utilizing a 1/7th power
    distribution.

27
(No Transcript)
28
Construction Loads/Stages
  • 1. Individual deck lifts 1 thru 9 on the
    appropriate towers
  • 2. In- fill / heavy lifts 1, 2, 3 4 on the
    appropriate towers
  • 3. Connecting the deck sections together in the
    longitudinal direction
  • 4. Connecting the cross beams in the transverse
    direction
  • 5. Connecting the deck sections to W2 and E2 cap
    beams
  • Tower C
  • Temporary Tower (TT)
  • TT plus Deck Lift 1 (830 Tonnes) on 4 bearing
    pads
  • TT plus Deck Lift 4 (459 Tonnes) on 4 bearing
    pads
  • TT plus Deck Lift 4 plus half of Heavy Lift 1
    (830/2 415 Tonnes) total 875 T
  • Envelope of Vertical Forces (see Table 1 on Sheet
    Construction Load No. 1)
  • Tower G
  • Temporary Tower (TT)
  • TT plus Deck Lift 9 (892 Tonnes) on 6 bearing
    pads
  • TT plus Deck Lift 9 plus half of Heavy Lift 3
    (1285/2 643 Tonnes) tot al 1535 T
  • TT plus Deck Lift 9 plus half of Heavy Lifts 3
    4 2177 T
  • Envelope of Vertical Forces (see Table 1 on Sheet
    Construction Load No. 1)

29
Load Combinations
  • 1.4 DL
  • 1.1 DL 1.3 LL
  • 1.0 DL 1.0 LL 0.5 Wind 1.0 Current 1.0
    Impact (Vessel)
  • 1.0 DL 1.0 LL 1.0 EQ
  • 1.0 DL 1.0 LL 1.3Wind 1.3Wave 1.3Current

30
Tower C
  • Tubular steel structure, trucked and assembled on
    site with the use of a crawler crane
  • All tower and truss joints are to be bolted
  • Leg segments bolted together with splice flanges
    located near inflection points
  • Pre-installed gusset plates welded to legs for
    bracing members to be bolted onto
  • Gusset plates actually penetrate through the legs
    to provide load continuity through the joints

31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
Tower G
  • 6- leg tubular steel jacket structure, 65m (213
    ft) high
  • 14m x 30m (46 ft x 98 ft) footprint at the top,
    to match bearing locations
  • Pin piles driven through the jacket legs
  • The jacket base plan dimensions provide the same
    overturning resistance in both orthogonal
    directions
  • Bay height chosen to provide efficient diagonal
    bracing
  • Cross braced to provide ductility

35
(No Transcript)
36
(No Transcript)
37
(No Transcript)
38
(No Transcript)
39
3D View of Towers ABC Model
40
Mode 1 (T0.78 sec)
41
Y Spectral Displacement (5.62 cm at top of Tower
C) (Transverse)

42
Wind Displacement (0.8 cm at top of Tower C)
43
Transverse Pushover at 115mm
44
Transverse Pushover to 115mm
Shear reductions are due to compression member
buckling (tension members take over)
45
3D View of Tower C Model as a separate structure
46
Mode 2 (T1.43 sec)
47
Y Spectral Displacement (7.63cm at top of Tower)
(Transverse)


48
Wind Displacement (1.06cm at top of Tower)
49
Transverse Pushover at 300mm
50
Transverse Pushover to 300mm, Force-Displacement
Curve (76mm Seismic Demand)


Shear reductions are due to compression member
buckling (tension members take over)
51
Tower C Conclusions
  • Combined structure is stiffer lower period
  • Produces larger forces
  • Separate structure is more flexible higher
    period
  • Produces lower forces
  • Consider Base Isolation System
  • (Slip plane at bearing level with retainers)

52
3D View of Tower G Model

53
3D View of Tower G alone
54
(No Transcript)
55
Mode 2 (T1.36 sec)


56
IMPACTY Displacement (Y4.5 cm at top of tower,
Y11.5 cm at point of impact)


57
Y Spectral Displacement (9.7 cm at top of Tower)


58
Wind Displacement (4.4 cm at top of Tower)


59
Transverse Pushover Displaced Shape at X0.45 m


60
Transverse Pushover Curve to 0.45 m
No member buckling present at this load level
piles govern capacity
61
3D View of Tower G Model Pinned at the Base


62
Transverse Pushover Displaced Shape at X1.0 m


63
Transverse Pushover Curve to 1.0 m


Shear reductions are due to compression member
buckling (tension members take over)
64
(No Transcript)
65
(No Transcript)
66
Tower G Conclusions
  • Provide Vessel Impact energy absorption
    system(reduces overall demand on tower)
  • Increase pile diameter and/or reduce bracing size
    (to provide more tower ductility)

67
It should be noted that this Design Example is a
first iteration in the design process and
requires further refining in order to meet the
full intent of the specified design requirements.
  • As noted, there are several approaches to meet
    the requirements of the Drawings and Special
    Provisions.

68
  • Chris Traina
  • Cash Flow Analysis

69
Early Pay Items Analysis
70
Steel Payments
71
Cash Flow Analysis
72
  • Rick Morrow
  • Outstanding Bidder Inquiries
  • Tower Mock-Up
Write a Comment
User Comments (0)
About PowerShow.com