Title: Agenda 1


1
Agenda (1)
  • Clemens - chambers
  • David - pad planes
  • Damian - radiators
  • Rainer - chamber testing
  • Mihai - status Bucharest lab.
  • Yuri - status Dubna lab.
  • Harry - overview of production

2
Agenda (2)
  • Ken - chamber/electronics integration
  • Bernd - supermodule, lifting device
  • Marc - mounting of services
  • Vojtek - cooling
  • Chilo - gas system
  • Georgios - Xe-activation
  • Angelos - HV distribution

3
Agenda (3)
  • Hans-Kristian - PASA
  • Venelin - TRAP
  • Ivan - Readout Board
  • Marc/Dirk - DCS
  • Tobias - DCS communications
  • Worms - DIM
  • T. Blank - MCM production
  • Volker - electronics schedule

4
Agenda (4)
  • David - status construction DB
  • Bogdan - GTU simulations
  • Ken - dE/dx
  • Marian - central barrel tracking
  • Tariq - quarkonia physics performance
  • Christoph - planning simulations

5
Agenda (5)
  • Anton - beam tests GSI/CERN
  • David - preparation for beamtime
  • Anton - commissioning/installation
  • Hannes - milestones/preparation for CR4

6
TRD Planning Milestones
  • planning of sub-projects milestones
  • radiator
  • readout chamber
  • electronics
  • gas system
  • cooling system
  • detector control system

7
Overall Timeline
  • driven by overall ALICE installation schedule
  • need to finish at least 2-3 supermodules for
    installation below beampipe by August 2005
  • rest of installation starts April 2006
  • 50-100 issue still open ? repercussions on
    installation scenario

8
Radiator Production
  • at current rate of production probably done by
    October

9
Chamber Production
  • delay since start of production lt 1 yr
  • some slack to catch up
  • stacking of supermodules moved from Mar-04-gt
    Jan-05

10
PASA Production
  • Delay compared to official schedule 1yr
  • still compatible with overall schedule of
    electronics

11
Digital Chip ProductionTest
  • pilot run delayed by 1yr
  • moving into start of production

12
Gas System Production
  • PRR was in December
  • production of components started
  • timing not critical

13
Cooling Schedule
  • work on cooling unit started
  • panels need to be started soon

14
DCS Schedule
15
Various
  • beamtime request 2005
  • alignment requirements
  • t0-TTC integration
  • test of TTC close to magnetic field
  • connector specification
  • completion of cable DB
  • verification of rack layout (B-field)

16
B-field in UX worst case (D.Swoboda TB 27.1.04)
L.Jirden
17
B-field in UX worst case (D.Swoboda TB 27.1.04)
L.Jirden
Rack group C 50 Gauss
18
B-field tests PL500
L.Jirden
  • Power module fan
  • PAPST 614MN

19
B-field tests PL500
L.Jirden
  • Power module fan
  • NMB 1606 KL
  • This fan is used to cool the double power modules
    type MDL.

20
B-field tests
L.Jirden
  • VME fan tray
  • Behaves similar to PAPST 614MN max 80 Gauss
    tolerated
  • Ethernet transceiver
  • Vacor PT4153S transformer chip tested
  • Operation depends on orientation in worst
    direction all traffic stops at 200-220
  • Plan rack layouts in view of water cooling only
    (racks without ventilator units) ??