Earned Value Management - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Earned Value Management

Description:

Accurate measurement of physical performance against a detailed ... Because we are be hind schedule the take will now take 2 weeks instead of one. Works Cited ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 20
Provided by: Informatio297
Category:

less

Transcript and Presenter's Notes

Title: Earned Value Management


1
Earned Value Management
  • Zach Reeser
  • Patrick Smith

2
About EVM
  • Focus
  • Accurate measurement of physical performance
    against a detailed plan to allow for the accurate
    prediction of the final scope, costs, and
    schedule results
  • Requirements
  • Fully defined scope
  • Baseline plan

3
Origin of EVM
  • Released by the Department of Defense (DOD) in
    December 1967
  • Engrained in the Cost/Schedule Control System
    Criteria (C/SCSC)

4
Evolution of EVM Concept
  • Phase 0
  • Late 1800s
  • Industrial engineers three dimensional approach
    to asses cost performance efficiency
  • Cost Variance definition
  • EVM at most basic form

5
Evolution of EVM Concept
  • Phase 1 (PERT/COST)
  • First introduced by the Navy in 1958
  • Used from 1962 1965
  • Strong emphasis on statistical probability
  • Computer hardware nor software was adequate to
    implement the concept
  • Introduced Earned Value concept in 1962
  • Cost of Work Report

6
Evolution of EVM Concept
  • Phase 2 (C/SCSC)
  • Used from 1967 1996
  • Incorporated EV concept in the form of 35
    criteria rather than a control system (PERT)
  • Imposed on contractors management control system
    when cost or incentive type contract was used
  • Interpretations over the decades lead to
    modifications and additions

7
Evolution of EVM Concept
  • Phase 3 (EVM ANSI/EIA 748)
  • Used 1996 Present
  • Government realizes Earned Value concept needs to
    be made more user friendly
  • Changes officially released in the American
    National Standard Institute/Electronic Industry
    Association 748 guide in 1998

8
EVM Criteria
  • Organization
  • Planning, Scheduling, and Budgeting
  • Accounting Considerations
  • Analysis MGMT. Reports
  • Revisions Data Maintenance

9
Methods to Plan and Measure EV
  • Weighted Milestones
  • Individual work packages that exceed a short span
  • Each milestone is assigned a specific budget
    value earned after completion of the event.
  • Total work package budget is divided based on
    weighted value assigned to each milestone.

10
Methods to Plan and Measure EV
  • Fixed formula by task
  • Partial percentage is earned when the activity is
    started, rest is obtained when activity is
    completed
  • Percent complete estimates
  • Allows for periodic estimates
  • Estimates are subjective
  • Companies often set maximum ceiling (80-90)

11
Methods to Plan and Measure EV
  • Equivalent completed units
  • Allows planned value to be earned for each full
    unit of work completed
  • Break individual cost elements into a percentage
    of the total value per unit

12
EVM Maturity Model
  • Level I
  • An organization with no or limited EVM
    implementation in place. This level provides a
    defined starting point for an initial
    implementation of EVM and does not require a
    large commitment of resources.
  • Level II
  • An EVM implementation which is less than fully
    compliant with ANSI 748, but may be sufficient
    for smaller projects or for a simplified EVM
    implementation.
  • Level III
  • ANSI/EIA 748 compliant implementation.
  • Level IV
  • Adds guidelines for measuring the quality of EVM
    data and introduces metrics for measuring the
    health of an Earned Value Management System.
  • Level V
  • Requires monitoring the efforts to improve an
    Earned Value Management system. Organizations
    with an ANSI or DOD compliant EVM implementation
    can use Levels IV and V as goals for improving
    the utility, timeliness, accuracy, and cost
    effectiveness of their EVM systems.

13
Planned Value
  • The portion of the approved total cost planned to
    be spent on an activity during a given period
  • If the Activity is to make a slide show in a week
    for 5000 then the Planned Value for making the
    slide show that week

14
Actual Cost
  • The total direct and indirect costs incurred in
    accomplishing work on an activity in a given time
    period
  • If it actually cost 6000 dollars to make the
    slide show in the week you planned to do it, then
    the Actual Cost is 6000

15
Earned Value
  • Estimate for value of physical work actually
    completed. It is based on the original planned
    costs of the activity and the rate at which the
    team is completing the work. (Rate of
    Performance) (RP)
  • Rate of Performance
  • Is the ratio of actual work completed as compared
    to the work that was planned to be completed. If
    you plan to finish the whole slide show in a week
    and only half is done then your Rate of
    Performance.5
  • Example
  • EVPVRP
  • EV5000.5
  • EV2500
  • Earned Value you tells you the value of you work
    to date

16
Cost and Schedule Variance
  • How far are you compared to your cost or schedule
    estimates
  • Cost Variance (CV)
  • CV EV-AC
  • CV2500-6000
  • CV-3500
  • This tells you, you are over budget by 3500
  • Schedule Variance
  • SVEV-PV
  • SV2500-5000
  • SV-2500
  • This tells you, you are behind schedule
  • If either of these numbers is negative you are
    going to go over either time or budget. If they
    are zero you are right on and if you are positive
    you are going to finish early or under budget

17
Cost and Schedule Performance IndexesCPI SPI
  • Measures compared to schedule or budget plans
    shown as ratios or percentages.
  • CPI EV/AC
  • CPI 2500/6000
  • CPI .416
  • SPI EV/PV
  • SPI2500/5000
  • SPI.5
  • These ratios show you weather you are over your
    budgeted amount of time or money. Anything less
    than one means you are over cost or behind
    schedule, 1 means you are right on budget or
    schedule and an numbers greater than one mean you
    are doing better than planned.

18
Budget at CompletionEstimate at Completion
Estimated Time to Complete
  • Budget at Completion can be divided by Estimate
    at Completion will tell you how much a project
    will cost upon completion.
  • EACBAC/CPI
  • EAC5000/.416
  • EAC12019.23
  • Because we are over budget upon completion the
    task will cost 12,019.23
  • Estimated time to complete takes the given
    information and tells you the adjusted schedule
  • Estimated time to completeOriginal time
    estimate/SPI
  • Estimated time to complete 1week/ .5
  • Estimated time to complete 2 weeks
  • Because we are be hind schedule the take will now
    take 2 weeks instead of one

19
Works Cited
  • Fleming, Quentin W., and Joel M. Koppelman.
    Earned Value Project Management. Newton Square
    Project Management Institute, 2000.
  • Stratton, Ray W. Earned Value Management Maturity
    Model. Vienna Management Concepts, 2006.
  • "Earned Value Management." Earned Value
    Management. 23 Nov. 2007 lthttp//earnedvaluemanage
    ment.com/gt.
Write a Comment
User Comments (0)
About PowerShow.com