Title: Lessons being Learned from the Anacostia Active Capping Demonstration
1Lessons being Learned from the Anacostia Active
Capping Demonstration
- Danny Reible, W. David Constant
2EPA Hazardous Substance Research Center
South and Southwest
Louisiana State University Georgia Institute of
Technology Rice University Texas AM
University University of Texas www.hsrc-ssw.org
- Research and Technology Transfer
- Contaminated sediments and dredged material
- Primarily focused on in-situ processes and risk
management - Unique regional (46) hazardous substance
problems - Outreach
- Primarily regional in scope
- Driven by community interests and problems
- Sediment Resource Center Member
http//www.epa.gov/superfund/resources/sediment
3Project Schedule
- 2002/2003 Laboratory evaluation of proposed
caps - 2003 Site characterization
- March-April 2004 Placement of active caps
- May 2004 One month sampling event
- September/October 2004 6 month sampling
- September/October 2005 18 month sampling
- September/October 2006 30 month sampling
4Selected Active Caps and Goals of Field Program
- AquaBlokTM w/EPA SITE program
- Evaluate tidal seepage control
- Evaluate potential for uplift during tidal range
- Coke
- Evaluate PAH sequestration/retardation
- Evaluate placement in laminated mat designed and
built by CETCO - Apatite
- Evaluate metal sequestration/retardation
- Evaluate effectiveness of direct placement
- Sand (for comparison)
5Site Field Assessment
- Relatively homogeneous sediment properties and
contaminant distribution - Steady depositional environment
- Shallow zone of bioturbation reworking
- Tidally influenced seepage near shore
- Significant gas generation and release
6Anacostia Geochronology from Radionuclide Profiles
Pb-210, Cs-137 profiles suggest deposition 0.44
0.84 cm/yr Be-7 profiles suggest 4 cm
accessible layer and bioturbation mass transfer
coefficient of 6-9 cm/yr
7Cap Placement
- Can conventional equipment (clamshell) be used to
place a relatively thin, uniform layer using the
innovative capping materials? - Targets
- 6 inches of apatite with 6 inches of sand
- 4 inches of Aquablok with 6 inches of sand
- 1 inch of Coke (laminated mat) with 6 inches of
sand - 12 inches of sand in two lifts
8(No Transcript)
9Sand/Apatite
AquaBlok
Coke Breeze
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14Mat Placement
15Cap Thicknesses
(Measured by core samples)
16Cap Thickness by Survey
Variability likely due to lateral position
inaccuracy
17Observations after Placement
- Chemical measurements showed good cap/sediment
separation - Seepage diverted by low permeability cap
(Aquablok) - Significant gas release during and subsequent to
placement no evidence of contaminant release - Gas accumulation with low permeability cap
18Chemical Data May 04 Sampling
- Data undergoing review
- No samples showed any detectable migration into
active or sand cap layers beyond intermixing
layer - Occasional cores showed thin layer of fine
grained sediment at surface of cap unconnected to
underlying sediment - Possible resuspension during capping (but no
corresponding water column detection during
capping) - Possible new sediment deposition
- One sample showed 3 ppm total PAHs on surface of
sand (coke breeze cap- near storm drain with
occasional active oil seeps)
19Seepage rates in Anacostia
Nearshore
East
Offshore
West
20Seepage Rates Post Placement
Uncapped
Sand
Aquablok
Smith, 2004
21Sediment Camera Image Anacostia River
Bubble
Gas Voids
22Effects of Gas on Impermeable Cap Inclinometer
Placement
23FIGURE 2
Cap Deformation During the Period 4/16/4004
through 5/25/04 1500 hrs
Anacostia River Sediment Capping Research
Project Washington, D.C.
HydroQual, Inc.
24Selected Active Caps Total Material Costs
- AquaBlok (4-6)
- 3.00/ft2
- 27/yd2
- Coke (mat)
- 1.11-1.14/ft2 (1/ft2 mat)
- 10/yd2
- Apatite (6)
- 3.10 /ft2
- 28/yd2
- Sand (6 layer) (added to each of the above)
- 0.45/ ft2
- 4/yd2
All costs exclude shipping
25Cap Placement Rates
- Coke Breeze mat
- 0.4-0.9 yd2/hr
- Aquablok (3 inch dry target)
- 2.4 6.3 yd2/hr
- Sand/Apatite
- 1.4 33 yd2/hr
- All rates limited by startup issues on small
areas - Placement over large areas expected to be
significantly greater
26Cap Placement Costs
- Demonstration construction costs not
representative due to small size - Although construction completed 2 weeks ahead of
schedule and 20 under budget - Large scale site (1000 acre)
- 25/yd2 materials
- Mobilization/demobilization 1 /yd2
- Cap placement 10/yd2
- Project Management 2/yd2
- Monitoring 10/yd2
- Miscellaneous 2/yd2
- Site Preparation
- Construction Management
- Design and Permits
- Sand capping cost Navigational dredging
27Lessons being Learned
- Innovative cap materials possible to place using
conventional equipment with experienced
contractor - Possible to apply thin (6) layer of cap material
using clamshell techniques - Thickness criteria should be probabilistic
- Occasional deviations, typically near edges
- Intermixing in soft sediments small and
manageable after near surface discharge of
granular cap material. - A laminated mat provides opportunities for
controlled placement of light and/or high value
materials (e.g. ? scale zero valent iron or
activated carbon) - Gas will find a path of release
- Plan for it and monitor for potential
consequences - Seemingly few consequences, at least in the
absence of NAPL