Title: Buy America
1 Buy America
- Montana Department of Transportation
Pat Ernst Anson Moffett Construction
Engineering Services Materials
2- Originated in the Surface Trans Asst Act of 1982
passed by Congress. - Applies only to Federal-aid highway construction
program - Originally applied to steel and cement and
manufactured products - Congress clarified to include iron and coating as
a manufacturing process in 1991
3- All manufacturing processes, including coating,
must occur in the US - State must have standard contract provision
requiring domestic steel and iron
4What is manufacturing?
- Any process that modifies the chemical content
physical shape or size or final finish. - Includes initial melting and mixing (smelting)
through the bending and coating stages. Also
includes rolling, extruding, machining, grinding,
and drilling. - Foreign source steel billets are not allowed
5 Waiver ?
- Must be requested by state to FHWA
- Must be in public interest (PIF)
- Show domestic materials are not produced in the
US in sufficient and reasonably available
quantities. - Current nationwide waivers for pig iron raw
alloys, and processed, pelletized, and reduced
iron ore granted in 1995.
6 NAFTA
- Does not apply to Buy America
- Specific exemption in NAFTA for grant programs
such as Federal-aid - GATT and EEC agreements do not apply either
7Domestic Materials (Steel)
- Code of Federal Regulations Highways 23
- MDT Requirements.
- Special Provision
- Standard Specifications for Road Bridge
Construction 1995 2006 Edition. 106.09. - Section 106.03 Certificate of Compliance.
8Domestic Materials (Steel)
- Manufactured in the U.S.A
- Foreign Materials are allowed if the price
- is 1/10th of 1 or 2500.00 which ever is
- greater including freight.
- Letter of permission is required from the
Materials Engineer or the Bridge Engineer
depending on usage. - Aluminum is not covered under Buy America.
9Domestic Materials Section 106.09
Mill test reports (MTR's) are required to ensure
- Material Grade
- Country of Origin
- Chemical and Physical Analysis
- Tracking of (Heat Numbers)
- Confirmation from the mill smelting the ore is
the only way to ensure documentation properly
corresponds with the material provided.
10Domestic Materials Section 106.09
- The smelter reduces iron ore/pig iron,slab or
recycled steel then processes the material into
useable form. - The smelter or manufacture provides the
appropriate mill test report. - Mill test reports may not be reproduced by a
supplier for incorporation into a MDT project. - This document would be a certificate of
compliance. - Mill test report must be legible.
11Special Provisions
- Special Provisions requires a Form 406 or 407 be
submitted 5 days prior to incorporation into the
project. - Form 406 or 407 must be signed by the Prime
Contactor. - Forms are available on the Construction Bureau
web site under the link for Contractors forms.
12Submit all required documentation with this form.
See the back of this form for general guidance
on Buy America documentation. Refer to MT 601
for sampling testing requirements. Contractors
Statement of Certification Domestic Material. I
hereby certify that all manufacturing processes,
including application of coating, occurred in the
United States for the above listed materials and
that those materials do meet all other
requirements as set forth in the plans and
specifications. Non-Domestic Material. I
hereby certify that the above listed materials do
meet the requirements as set forth in the plans
and specifications with the exception that all or
part of the manufacturing process may have
occurred outside the United States. The material
is considered non-domestic. The cost of this
material, including delivery to the project, is
__________. By Title
(Prime Contractors Name, Typed or Printed)
Date
Prime Contractors Signature
13Section 106.03Certificate of Compliance
14Certificate of Compliance Section 106.03
- Certificates of compliance sometimes referred
to as (C of C) may be as simple as a letter from
the supplier stating that the Materials provided
comply with the contract documents for a specific
MDT project and signed. The price of the supplied
items must be within the Buy America requirements.
15Certificate of Compliance Section 106.03
- The Certificate of Compliance (C of C) may be as
complicated as a listing of all metallurgical
aspects that are being provided for the material. - The letter is provided on company letterhead with
phone numbers and addresses to check the source.
16Certificate of Compliance Section 106.03
- A bill of lading is not a (C of C) neither is a
packing slip with a bar code on it. - In the event confirmation of material provided on
the certificate of compliance cannot be
established the material will be rejected.
17Certificate of Compliance Section 106.03
- Printed or stamped on the (C of C) must be the
domestic material phrase (we certify the material
provided was melted/smelted and manufactured in
the U.S.A) or a similar statement. - C of C must be legible.
18Complete Conformance Cert
- Signature
- Statement of Certification
- Company Address
- Attributes of the test are detailed in the
standards - Steel items will have a domestic material
statement
19Certification Statement
Certification Statement I certify...
20Incomplete Compliance
Heat Numbers
Incomplete Conformance Data
21Complete Documentation
- Brokers Test Data
- Heat Numbers Supplied
- Paperwork Matches Mill Data
22Complete Documentation
Brokers Test Data With Mill Certification
23Complete Documentation
- Brokers Test Data
- Heat Numbers Supplied
- Paperwork Matches Mill Data
24Manufactured in the U.S.A
- Manufactured Has Been Used by Suppliers (Brokers)
to Infer the Item Is of Domestic Origin. - This Is Not the Case.
- The Only Source That Is Acceptable to Claim
Domestic Material Compliance Is From the
Smelter/Steel Mill.
25Certification - No Signature
Test is Not Accepted No statement of made in
the USA. Certificate is Not Signed
26Foreign Certificate Example
Test Sheet not in English
27Double Switch
28Double Switch
29Double Switch
30Double Switch
- Data Not Consistent
- Non-Domestic?
- USA?
31Read the Paperwork
Paperwork from a US Smelter.
32Read the Paperwork
Not all Heat Numbers are Domestic Steel
33Foreign Materials
34Foreign Materials
We must have the following to consider the
request
- FAP project number and name.
- Item or piece number.
- Drawing reference.
- Quantity.
- Cost including delivery to the project.
35Foreign Materials
- Written Authorization Bridge Engineer, Materials
Engineer or their Agent for the Use of Foreign
Material is Required.
36Follow the Paperwork
MDTs Acceptance Letter
37Follow the Paper Work
MDT Issue Acceptance on
- Heat Number
- Mill
- Supplier
- Project Use
- Cost
38Follow the Paperwork
MDTs Acceptance Letter
Broker Certification Letter
39Follow the Paper Work
- Steel Broker Sends
- Test Report
- Requests Acceptance
- Report Includes Heat Numbers and Steel Testing
Data
40Follow the Paperwork
MDTs Acceptance Letter
Broker Certification Letter
Mill Certification Test Report
Chinese
41Follow the Paper Work
- Request is not Complete
- Brokers Test Report Dose Not Have Mill Test
- (Required from the Mill Only)
- Must Include Heat or Lot Numbers
42Foreign Certificate Example
Missing Heat Numbers
43Components Inspection
44Components Inspection
Bridge Components (T101, Girders Etc) and
Overhead Sign Structures. Bridge Bureau Will Make
Inspection Arrangements and Notify
- FPM
- Contractors
- Inspectors
- Fabricators
45Components Inspection
- Field Inspections, FPM May Request Field
Inspection of Materials Received That Were Not
Shop Inspected.. - The FPM Will Be Notified of the Inspection
Requirements.
46Components Inspection Other
Materials Bureau Will Make Inspection
Arrangements for Other Components Cattle Guards,
Sign Posts, Culvert, Etc. Materials will verify
Buy America requirements for CSP and RCP at the
point of manufacture.
47Source and Supply Letters
48Source and Supply Letters
- Source and Supply Letters Will Continue to Be
Sent to the Materials Bureau. - Notification of Bridge Bureau to Initiate
Inspection Arrangements Cannot Be Made Without
the Source Supply Letter. - Materials That Are Delivered to the Project
Without These Checks and Balances Should Not Be
Incorporated Until the Source Can Be Determined.
49Source and Supply Letters
- It Is in the Contractors Best Interest to Get the
Source and Supply Letter to Materials as Soon as
Possible.
50Call for assistance
- Bridge Bureau
- Phone (406) 444-6162
- Materials Bureau
- Phone (406) 444-6268
- Local Materials Office
51Guardrail
52(No Transcript)
53Inspection
- Prior to installation match the paper work to the
rail. - Check the heat number stamped on the rail.
- If the heat numbers dont match-dont install it.
- Box Beam doesnt have heat numbers stamped on
them. - Where is the heat number?
54Suppose To be here
55(No Transcript)
56(No Transcript)
57(No Transcript)
58(No Transcript)
59(No Transcript)
60(No Transcript)
61(No Transcript)
62Questions