Title: PUBLIC HEARING ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE
1PUBLIC HEARING ON CONDITIONAL GRANTS AND CAPITAL
EXPENDITURE 2nd QUARTER 2006/2007
- Presented By Ms MB MONAMA
- 24 NOVEMBER 2006
2CONTENT
- Departmental priorities till 2008/9
- Data trends, allocations and expenditure
- Budget Allocations
- Second Quarter Expenditure Profile
- MTEF Budget Allocation
- Overview of the organisational environment
- Constraints hampering delivery
- Interventions to deal with challenges
- Monitoring and Evaluation
- Conclusion
3DEPARTMENTAL PRIORITIES TILL 2008/9
- The Department of Housing has refocused its plan
and the following has been prioritised - Formalisation and Eradication of Informal
Settlement - Development of Social and Mixed Income
Settlements - Regeneration of Twenty Old established Townships
- Affordable Rental Accommodation
- Urban Regeneration
4DEPARTMENTAL PRIORITIES TILL 2008/9 (Cont)
- This will be achieved through
- Fast tracking of top structure delivery
- Provision of Housing in targeted areas in line
with Growth and Development Strategy and Global
City Region approach. - Renewal of 20 prioritised townships
- Social Housing program to be refocused to include
affordable rental low and middle income earners - Job Creation through housing development
- SMME/ BBBEE - Empowerment and Participation
5Trend in Allocations, Transfers and Actual
Expenditure i.r.o. Conditional Grant
Name of Conditional Grant Amount Transferred 2005/06 R000 Planned Transfers 2006/07 R000 Planned Transfers 2nd Quarter R000 Actual Transfers 2nd Quarter R000 Actual Expenditure 2nd Quarter R'000 Deviation from target
Name of Conditional Grant Amount Transferred 2005/06 R000 Planned Transfers 2006/07 R000 Planned Transfers 2nd Quarter R000 Actual Transfers 2nd Quarter R000 Actual Expenditure 2nd Quarter R'000 Deviation from target
Housing Fund 1,117,463 1,757,666 510,822 510,822 468,644 -8
Human Settlement 30,353 0 0 0 0 0
Land Distribution Alexandra 6,335 8,000 0 0 0 0
TOTAL 1,154,151 1,765,666 510,822 510,822 468,644 -8
6Trend in Allocations, Transfers and Actual
Expenditure i.r.o. Conditional Grant
Name of Conditional Grant Planned Transfers 2006/07 R000 Planned Transfers 2nd Quarter R000 Actual Transfers 2nd Quarter R000 Actual Expenditure 2nd Quarter R'000 Deviation from target
Name of Conditional Grant Planned Transfers 2006/07 R000 Planned Transfers 2nd Quarter R000 Actual Transfers 2nd Quarter R000 Actual Expenditure 2nd Quarter R'000 Deviation from target
Housing Fund 1,757,666 510,822 510,822 468,644 -8
Land Distribution Alexandra 8,000 0 0 0 0
TOTAL 1,765,666 510,822 510,822 468,644 -8
7YEAR TO DATE EXPENDITURE
Programmes Payments Audited 2005/06 R000 Projected Payments 2006/07 (R000) Projected Payments 2nd quarter (R000) Actual Payments 2nd quarter (R000) Deviation from target
Administration 78.017 74,918 20 727 28 727 138
Housing Planning and Research 7,513 10,284 2 486 2 004 81
Housing Performance/ Subsidy Programme 1,195,267 1,550,152 399 816 399 417 99,9
Urban Renewal and Housing Settlement Redevelopment 326,992 380,630 92 625 44 543 48
Housing Asset management 65,513 65,478 16 206 61 029 499,9
Total 1,673,302 2.081,462 531 860 535 720 100,7
8Conditional Grant/s and Capital Expenditure
- Data on trends in allocations, transfers and
actual expenditure of conditional grants and
capital expenditure of the Department as well as
a brief assessment on this departments monitoring
capacity for the financial year 2006/07 is
captured in the next few slides i.t.o. a tabular
format.
9BUDGET ALLOCATION (2006/2007)
- Particulars of the financial resources available
funding of the activities of the Department are
summarized in the Table hereunder
Particulars Amount R000 Total R000
Integrated Housing and Human Settlement Conditional Grant Note 1 Provincial Allocation for Urban Renewal Note 2 Administration Note 3 Goods, Services Machinery Note 4 1 765 666 191 500 87 150 37 146 1 765 666 191 500 124 296
Total IHHSCG, Dedicated Operational Budget Total IHHSCG, Dedicated Operational Budget 2 081 462
10BUDGET ALLOCATION (2006/2007) cont.
- Note 1 This represents the capital allocation to
the Gauteng Housing Department in terms of the
Division of Revenue Act DORA for the funding
of the implementation of National Housing
Programmes and Provincial Housing consistent
therewith - Note 2 This is an allocation from the Provincial
Revenue Funds towards the funding of the Urban
Renewal Programme in Gauteng Province. - Note 3 An allocation with the Operational
Budget of the Department for the funding of
compensation of employees during the 2006/07
financial year. - Note 4 The available funding for expenditure in
terms of Goods Services with the Operational
Budget of the Department.
11Second Quarter Expenditure Profile 2006/2007
Conditional Grant
GRANT BUDGET Projected Expenditure Actual Expenditure Variance
Integrated Housing and Human Settlement Development 1,757,666 510,822 468,644 42,178
12Second Quarter Expenditure Profile 2006/2007
cont.
Current and Capital Expenditure
Economic Classification Budget Projected Expenditure Actual Expenditure Variance
Compensation of employees 93,378 24,215 24,055 160
Goods and Services 32,700 7,907 11,749 -3,842
Buildings and other fixed structures 53,925 13,580 8,977 4,603
Machinery and equipment 4,446 2,077 302 1,775
184,449 47,779 45,083 2,696
13Second Quarter Expenditure Profile 2006/2007
cont.
Urban Renewal
GRANT BUDGET Projected Expenditure Actual Expenditure Variance
Urban Renewal 369,433 89,787 42,930 46,857
Payments made for projects that concerned
previous financial year
14Service Delivery Statistics for the 2nd Quarter
of the2006/07 Financial Year
Programme Unit of Measure Projected Actual delivery
Essential Services Houses - 693
Essential Services Stands 3,287 10, 433
PHP / CBP Houses 1,935 450
Project Linked Stands 1, 340 2.573
Project Linked Houses 4,627 4,155
Individual Stands 877 112
Individual Houses 877 112
Relocation assistance Stands 17 7
Relocation assistance Houses 17 7
Upgrading of Hostels Beds 1.100 264
TOTAL STANDS 5,521 13,125
TOTAL HOUSES 7,403 5,417
TOTAL BEDS 18,697 2 790
Institutional Subsidies units 605 -
15Reasons for Variance
- A deliberation of the reasons for the variance
in expenditure in comparison the allocation In
terms of DORA is as follows - Certified Claims to the value of R 32 million for
work completed during and prior to 30 September
2006 could not be paid in time and had to be
effected in October 2006 of which should have
been accounted for in terms of actual expenditure
incurred during the 2nd Quarter. - Similarly, an amount of R30 Million of which was
accounted for during the seconded quarter of
which relate to the 1st quarter.
16Payment Summary MTEF Baseline 07/10
Medium-Term Estimates Medium-Term Estimates Medium-Term Estimates
PROGRAMME Â 2007/08 Â 2008/09 Â 2009/10
1. Administration 84,595 91,770 91,770
2. Housing Planning and Research 12,432 12,154 12,154
3. Housing Development Implementation 2,361,356 2,562,652 2,562,652
4. Housing Property Management 62,149 61,869 61,869
Total Programmers 2,520,532 2,728,445 2,728,445
Economic Classification   Â
Compensation of Employees 127,513 134,366 134,366
Goods Services 39,573 44,369 44,369
Households 2,387,223 2,589,079 2,589,079
Machinery Equipment 5,796 5,000 5,000
Total 2,520,532 2,728,445 2,728,445
17Overview of the organisational environment
- During the second quarter the Department
implemented its revised organisational
structure. - The implementation of its Regional Offices took
effect in terms of negotiations around the office
accommodation and other related infrastructure
requirements, had taken place. - The Department has rearranged its expenditure
management processes and delegations have been
finalised. - Newly appointed Professional Resource Teams
(PRTs) to replace the Regional Professional
Teams whose contract ended on the 30th of June
2006 had been finalised. - Regrouping of established developers and improve
on the procurement system. - The Department also appointed contractors on the
procurement rooster who will assist in
implementing projects. The contractors have been
appointed in two categories which are the
established and emerging contractors
18Constraints hampering delivery
- Submission of insufficient information and
supporting documents for payments - Fast track the enrolment of projects with NHBRC
- Improvement of contract management processes
- Submission of trench payments by Municipalities
on quarterly basis. - Improvement of house inspections by the
Department and Municipal inspectors - Improvement of quality as well as meeting
specified targets by contractors and developers. - Slow pace of delivery by emerging developers
- Inability to provide guarantees by appointed
developers and contractors within specified time
frames - Dealing with illegal land and buildings invasions
- Inability of municipalities to implement by Laws
to deal with erection of illegal structures in
newly built subsidized houses. -
19Interventions to deal with challenges
- Established a task team with NHBRC to deal with
approvals change information on weekly basis on
all projects submitted and feedback on those
approves and not approved. - Established an Inspectorate within department to
deal with quality issues as well as inspecting of
houses regularly - Established working protocols between department,
municipalities and NHBRC inspectors to coordinate
and manage inspections process - Regular site visits by Project Managers and
Senior Managers to deal with identified
challenges per project - Provided professional support to emerging
developers to be mentored - Simplified payment process drafted and
improvement now realised - Interaction with Executive Directors of Housing
to agree on payment processes and service
delivery improvement mechanisms for each
Municipality. - Executive Management monitoring projects and able
to shift budget on slow project in favor of those
best performing.
20Monitoring and Evaluation
- A Monitoring and Evaluation Unit has been
established to evaluating progress in the
implementation of the strategy against the
targets set. - It will further recommend intervention mechanisms
in areas where there is little or no progress. - A draft monitoring and evaluation framework has
been developed and will be finalised by end of
financial year 2006/07. - Departments submits various reports as prescribed
by the PMFA to various institutions such as
Provincial Treasury and Legislature.
21Conclusion
- Our delivery processes are starting to yield
results and there's hope amongst communities that
government is addressing housing their needs. - We are putting proper plans and re-prioritizing
our approach that must always adhere to the
principles of the Breaking New Ground policy. - Better coordination with municipalities and
developers - Improved management and monitoring systems within
the Department - Department providing leadership and guidance in
all aspects of housing development - Political support from all spheres of govrnment