Intrinsic Safety Testing by - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

Intrinsic Safety Testing by

Description:

Intrinsic Safety Testing by – PowerPoint PPT presentation

Number of Views:108
Avg rating:3.0/5.0
Slides: 46
Provided by: smithje7
Learn more at: https://www.msha.gov
Category:

less

Transcript and Presenter's Notes

Title: Intrinsic Safety Testing by


1
Intrinsic Safety Testingby
  • Gail Nicola, Electrical Engineering Technician
  • Ed Vensko, Electrical Engineering Technician

2
Battery Flash Current Testing
  • Purpose To determine the maximum short circuit
    current of a battery.
  • Pass/Fail Criteria None. The data is used to
    determine the intrinsic safety of a particular
    circuit.
  • Samples 3 fresh or fully charged batteries for
    each battery manufacturer specified.
  • Recommendations
  • Submit samples with the application package, if
    possible.
  • Individual cells should be submitted instead of a
    complete battery pack that may contain
    polyswitches or fuses.
  • Verify that manufacturer part number of samples
    agree with documentation.

3
(No Transcript)
4
(No Transcript)
5
(No Transcript)
6
(No Transcript)
7
Cap Lamp Bulb Life
  • Purpose To determine compliance with 30 CFR
    19.9(b) and 19.9( c)2.
  • Pass/Fail Criteria
  • 19.9(b) Average life of the bulb shall not be
    less than 200 hours and 92 shall have a life of
    150 hours.
  • 19.9(c)(2) Current consumption of at least 94 of
    the bulbs shall not exceed the average current by
    more than 6. The candlepower of at least 90
    shall not fall short of the average candlepower
    by more than 30.

8
Cap Lamp Bulb Life
  • Samples 50 marked bulbs, discharge rack capable
    of testing 10 bulbs max.
  • Recommendations
  • Submit samples with application package

9
(No Transcript)
10
(No Transcript)
11
Accuracy of Methane Detectors
  • Purpose To determine compliance with 30 CFR
    Part 22 within the limits
    of error specified in 22.7(d)(2).
  • Pass/Fail Criteria When more than 2 readings
    for each percentage or the average of all 10
    readings of any of the four samples exceeds the
    limits of error.
  • Samples 4 representative samples, calibration
    kit and calibration procedures, probes, maximum
    length specified sampling lines, batteries and/or
    battery chargers.

12
(No Transcript)
13
Accuracy of Methane Detectors
  • Problems
  • Sensors have not been burned in.
  • Calibration gas is not accurate.
  • All specified battery packs have not been
    submitted.
  • How detectors react with low battery voltage
  • No low flow pump alarms
  • Flow rate, gas concentration, and pump
    calibration procedures not adequately specified.
  • Recommendations
  • Check performance of detectors before submitting
  • Verify concentration of calibration gas.

14
- 4 instruments (2 with pumps, 2 without
pumps) - calibration gas and instruction
manual - regulators - probes -
sampling tubing , specify length - battery
chargers
15
(No Transcript)
16
Surface Temperature Test
  • Purpose To determine the maximum surface
    temperature of a component.
  • Pass/Fail Criteria The temperature of the
    external surfaces of components shall not exceed
    150 C if exposed to coal dust or 530 C if
    exposed to a methane-in-air atmosphere.
  • Samples
  • 10 samples of the component under test.
  • 10 samples of the current-interrupting device (if
    applicable).

17
Surface Temperature Test
  • Recommendations
  • Position the surface mount components on a PCB
    with 2 leads.
  • Use adequately rated components.
  • Use dust tight enclosures.
  • Submit 10 samples of components likely to
    overheat (e.g. low value/rated resistor
    and zener diodes, etc.) with your application
    package.
  • Submit fuse manufacturers time versus current
    characteristic curves.


18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
Coal Dust Blanketing Test
  • Purpose If a small component exceeds 150 C
    during surface temperature testing then the
    component is subjected to the Dust Blanketing
    Test.
  • Pass/Fail Criteria The component fails the test
    if there is evidence of smoldering or ignition of
    the coal dust.
  • Samples 10 samples of each component
  • Recommendations
  • Design circuitry with fuses to prevent
    overheating of components.

22
Hot Wire Calibration and Small Component Ignition
  • Purpose To determine if the heated element will
    ignite a methane-in-air mixture.
  • Pass/Fail The component must not ignite the
    test gas.
  • Samples 10 samples of each component specified
  • Problems Sensors are submitted without the
    elements exposed (sintered metal screen removed)
  • Recommendations
  • Submit samples with the application package.
  • Submit samples with elements exposed.

23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
Current-Limiting Resistor Tests
  • Purpose To determine if the resistor decreases
    in resistance by more than 10 .
  • Pass/Fail Criteria The resistor shall not
    decrease in resistance by more than 10 of its
    pre-test value, flame, or deform such that it
    would be short-circuited by an adjacent
    conductor.
  • Samples 10 samples of each CLR specified on
    the documentation and 10 samples of the
    current-interrupting device (if applicable).
  • Recommendations
  • Submit samples with the application package.
  • Design circuitry with fuses to prevent
    overheating of components.
  • Submit fuse time versus current curve (if
    applicable).

28
Spark Ignition Test
  • Purpose To determine whether the circuit is
    capable of releasing enough electrical energy to
    cause an ignition of a flammable mixture of
    methane and air at the most easily ignitable
    composition.
  • Pass/Fail Criteria An ignition occurs.
  • Samples 3 samples each of motors, inductors,
    speakers, etc.
  • Problems
  • Unable to obtain a pretest calibration due to
    environmental conditions.
  • Inductive calibration with copper electrodes
  • Recommendations
  • Design circuits with adequate current limiting
    resistance so spark testing may be waived.
    (Reference ignition curves.)

29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
Optical Isolator Test
  • Purpose Each optically-coupled isolator shall
    withstand a minimum dielectric voltage of either
    2500 volts (rms) or four times the maximum
    safe-area voltage (whichever is greater) between
    its input and output.
  • Pass/Fail Criteria No breakdown shall occur.
  • Samples 9 of each type of optical isolator
    specified on the submitted documentation.

33
Optical Isolator Test
  • Problems
  • Verifying internal spacing between input and
    output circuitry.
  • Specification ratings of the optical isolator are
    not submitted.
  • Recommendations
  • Submit adequate specifications for the optical
    isolator so the device is accepted based on
    evaluation only and testing of the component is
    waived.
  • Submit nine samples of each optical isolator of
    all manufacturers specified on the submitted
    documentation.

34
Protective Transformer Test
  • Purpose Transformers for direct connection to a
    supply voltage shall be evaluated for dielectric
    strength.
  • Pass/Fail Criteria There shall be no breakdown
    of the insulation between the test points during
    testing.
  • Samples 3 samples of each transformer specified
    in your application.
  • Recommendations
  • Submit samples that are adequately marked with
    manufacturer and manufacturer part number.
  • Submit samples with application package.

35
Drop Test
  • Purpose To determine whether portable apparatus
    continue to be intrinsically safe after being
    subjected to 6 drops from a height of 3 feet onto
    an oak plank.
  • Pass/Fail Criteria There shall be no separation
    or ejection of the battery or batteries from the
    apparatus, nor other fault that could affect
    intrinsic safety. For equipment requiring a
    dust-tight enclosure to exclude coal dust entry,
    the enclosure of the sample shall continue to be
    dust-tight after the drop test.
  • Samples 1 representative sample of the
    manufactured portable instrument.


36
Drop Test
  • Recommendations
  • Drop an instrument at your facility before
    submitting for approval.

37
(No Transcript)
38
Piezoelectric Component Impact Test
  • Purpose To determine the maximum output energy
    generated by the piezoelectric component when it
    is impacted with an energy of 20 joules (2 kg at
    1 m).
  • Pass/Fail Criteria The maximum output energy
    generated by the piezoelectric component shall
    not exceed 1500 micro joules.
  • Samples 3 each of the apparatus containing the
    piezoelectric component of a quality, design, and
    construction consistent with that of the final
    manufactured product.

39
Piezoelectric Component Impact Tests
  • Problems
  • Capacitance of the crystal is not specified
    and/or doesnt match submitted drawing.
  • Connection directly to the crystal is not
    possible crystal is located in a potted assembly
    with other oscillating circuitry.
  • 3 samples of the component were not submitted in
    a test mockup with the samples mounted in
    their normal position..
  • Unable to obtain a second impact on the sample of
    the component since the first impact completely
    destroys the sample.
  • Recommendations
  • Submit three samples mounted in test mockups.
  • Attach output leads directly to the crystal or to
    amplification circuitry.
  • Submit specification data with regard to the
    maximum capacitance of the crystal.

40
(No Transcript)
41
(No Transcript)
42
(No Transcript)
43
(No Transcript)
44
(No Transcript)
45
Standard Test Procedures
  • ASTP2002
  • ASTP2004
  • ASTP2008
  • ASTP2009
  • ASTP2010
  • ASTP2012
  • ASTP2022
  • ASTP2026
  • ASTP2030
  • ASTP2036
  • ASTP2040
  • Battery Flash Current Test
  • Accuracy of Methane-Indicating Detectors
  • Cap Lamp Bulb Life Test
  • Current Limiting Resistor/Surface Temperature
    Test
  • Dust Blanketing Temperature Test
  • Hot Wire Calibration and Small Component Ignition
    Test
  • Spark Ignition Test
  • Optical Isolator Test
  • Protective Transformer Test
  • Drop Test for Portable Instruments
  • Piezoelectric Component Impact Test
Write a Comment
User Comments (0)
About PowerShow.com