Title: Intrinsic Safety Testing by
1Intrinsic Safety Testingby
- Gail Nicola, Electrical Engineering Technician
- Ed Vensko, Electrical Engineering Technician
2Battery Flash Current Testing
- Purpose To determine the maximum short circuit
current of a battery. - Pass/Fail Criteria None. The data is used to
determine the intrinsic safety of a particular
circuit. - Samples 3 fresh or fully charged batteries for
each battery manufacturer specified. - Recommendations
- Submit samples with the application package, if
possible. - Individual cells should be submitted instead of a
complete battery pack that may contain
polyswitches or fuses. - Verify that manufacturer part number of samples
agree with documentation.
3(No Transcript)
4(No Transcript)
5(No Transcript)
6(No Transcript)
7Cap Lamp Bulb Life
- Purpose To determine compliance with 30 CFR
19.9(b) and 19.9( c)2. - Pass/Fail Criteria
- 19.9(b) Average life of the bulb shall not be
less than 200 hours and 92 shall have a life of
150 hours. - 19.9(c)(2) Current consumption of at least 94 of
the bulbs shall not exceed the average current by
more than 6. The candlepower of at least 90
shall not fall short of the average candlepower
by more than 30.
8Cap Lamp Bulb Life
- Samples 50 marked bulbs, discharge rack capable
of testing 10 bulbs max. - Recommendations
- Submit samples with application package
9(No Transcript)
10(No Transcript)
11Accuracy of Methane Detectors
- Purpose To determine compliance with 30 CFR
Part 22 within the limits
of error specified in 22.7(d)(2). - Pass/Fail Criteria When more than 2 readings
for each percentage or the average of all 10
readings of any of the four samples exceeds the
limits of error. - Samples 4 representative samples, calibration
kit and calibration procedures, probes, maximum
length specified sampling lines, batteries and/or
battery chargers.
12(No Transcript)
13Accuracy of Methane Detectors
- Problems
- Sensors have not been burned in.
- Calibration gas is not accurate.
- All specified battery packs have not been
submitted. - How detectors react with low battery voltage
- No low flow pump alarms
- Flow rate, gas concentration, and pump
calibration procedures not adequately specified. - Recommendations
- Check performance of detectors before submitting
- Verify concentration of calibration gas.
14- 4 instruments (2 with pumps, 2 without
pumps) - calibration gas and instruction
manual - regulators - probes -
sampling tubing , specify length - battery
chargers
15(No Transcript)
16Surface Temperature Test
- Purpose To determine the maximum surface
temperature of a component. - Pass/Fail Criteria The temperature of the
external surfaces of components shall not exceed
150 C if exposed to coal dust or 530 C if
exposed to a methane-in-air atmosphere. - Samples
- 10 samples of the component under test.
- 10 samples of the current-interrupting device (if
applicable).
17Surface Temperature Test
- Recommendations
- Position the surface mount components on a PCB
with 2 leads. - Use adequately rated components.
- Use dust tight enclosures.
- Submit 10 samples of components likely to
overheat (e.g. low value/rated resistor
and zener diodes, etc.) with your application
package. - Submit fuse manufacturers time versus current
characteristic curves.
18(No Transcript)
19(No Transcript)
20(No Transcript)
21Coal Dust Blanketing Test
- Purpose If a small component exceeds 150 C
during surface temperature testing then the
component is subjected to the Dust Blanketing
Test. - Pass/Fail Criteria The component fails the test
if there is evidence of smoldering or ignition of
the coal dust. - Samples 10 samples of each component
- Recommendations
- Design circuitry with fuses to prevent
overheating of components.
22Hot Wire Calibration and Small Component Ignition
- Purpose To determine if the heated element will
ignite a methane-in-air mixture. - Pass/Fail The component must not ignite the
test gas. - Samples 10 samples of each component specified
- Problems Sensors are submitted without the
elements exposed (sintered metal screen removed) - Recommendations
- Submit samples with the application package.
- Submit samples with elements exposed.
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27Current-Limiting Resistor Tests
- Purpose To determine if the resistor decreases
in resistance by more than 10 . - Pass/Fail Criteria The resistor shall not
decrease in resistance by more than 10 of its
pre-test value, flame, or deform such that it
would be short-circuited by an adjacent
conductor. - Samples 10 samples of each CLR specified on
the documentation and 10 samples of the
current-interrupting device (if applicable). - Recommendations
- Submit samples with the application package.
- Design circuitry with fuses to prevent
overheating of components. - Submit fuse time versus current curve (if
applicable).
28Spark Ignition Test
- Purpose To determine whether the circuit is
capable of releasing enough electrical energy to
cause an ignition of a flammable mixture of
methane and air at the most easily ignitable
composition. - Pass/Fail Criteria An ignition occurs.
- Samples 3 samples each of motors, inductors,
speakers, etc. - Problems
- Unable to obtain a pretest calibration due to
environmental conditions. - Inductive calibration with copper electrodes
- Recommendations
- Design circuits with adequate current limiting
resistance so spark testing may be waived.
(Reference ignition curves.)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32Optical Isolator Test
- Purpose Each optically-coupled isolator shall
withstand a minimum dielectric voltage of either
2500 volts (rms) or four times the maximum
safe-area voltage (whichever is greater) between
its input and output. - Pass/Fail Criteria No breakdown shall occur.
- Samples 9 of each type of optical isolator
specified on the submitted documentation.
33Optical Isolator Test
- Problems
- Verifying internal spacing between input and
output circuitry. - Specification ratings of the optical isolator are
not submitted. - Recommendations
- Submit adequate specifications for the optical
isolator so the device is accepted based on
evaluation only and testing of the component is
waived. - Submit nine samples of each optical isolator of
all manufacturers specified on the submitted
documentation.
34Protective Transformer Test
- Purpose Transformers for direct connection to a
supply voltage shall be evaluated for dielectric
strength. - Pass/Fail Criteria There shall be no breakdown
of the insulation between the test points during
testing. - Samples 3 samples of each transformer specified
in your application. - Recommendations
- Submit samples that are adequately marked with
manufacturer and manufacturer part number. - Submit samples with application package.
35Drop Test
- Purpose To determine whether portable apparatus
continue to be intrinsically safe after being
subjected to 6 drops from a height of 3 feet onto
an oak plank. - Pass/Fail Criteria There shall be no separation
or ejection of the battery or batteries from the
apparatus, nor other fault that could affect
intrinsic safety. For equipment requiring a
dust-tight enclosure to exclude coal dust entry,
the enclosure of the sample shall continue to be
dust-tight after the drop test. - Samples 1 representative sample of the
manufactured portable instrument.
36Drop Test
- Recommendations
- Drop an instrument at your facility before
submitting for approval.
37(No Transcript)
38Piezoelectric Component Impact Test
- Purpose To determine the maximum output energy
generated by the piezoelectric component when it
is impacted with an energy of 20 joules (2 kg at
1 m). - Pass/Fail Criteria The maximum output energy
generated by the piezoelectric component shall
not exceed 1500 micro joules. - Samples 3 each of the apparatus containing the
piezoelectric component of a quality, design, and
construction consistent with that of the final
manufactured product.
39Piezoelectric Component Impact Tests
- Problems
- Capacitance of the crystal is not specified
and/or doesnt match submitted drawing. - Connection directly to the crystal is not
possible crystal is located in a potted assembly
with other oscillating circuitry. - 3 samples of the component were not submitted in
a test mockup with the samples mounted in
their normal position.. - Unable to obtain a second impact on the sample of
the component since the first impact completely
destroys the sample. - Recommendations
- Submit three samples mounted in test mockups.
- Attach output leads directly to the crystal or to
amplification circuitry. - Submit specification data with regard to the
maximum capacitance of the crystal.
40(No Transcript)
41(No Transcript)
42(No Transcript)
43(No Transcript)
44(No Transcript)
45Standard Test Procedures
- ASTP2002
- ASTP2004
- ASTP2008
- ASTP2009
- ASTP2010
- ASTP2012
- ASTP2022
- ASTP2026
- ASTP2030
- ASTP2036
- ASTP2040
- Battery Flash Current Test
- Accuracy of Methane-Indicating Detectors
- Cap Lamp Bulb Life Test
- Current Limiting Resistor/Surface Temperature
Test - Dust Blanketing Temperature Test
- Hot Wire Calibration and Small Component Ignition
Test - Spark Ignition Test
- Optical Isolator Test
- Protective Transformer Test
- Drop Test for Portable Instruments
- Piezoelectric Component Impact Test