DOI ITIM Maturity Framework - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

DOI ITIM Maturity Framework

Description:

... One Independent Contractor ... Validation would not be totally independent. Option Two Department Assessment. 14 ... Independent Peer Review Team. 16 ... – PowerPoint PPT presentation

Number of Views:59
Avg rating:3.0/5.0
Slides: 17
Provided by: doi
Category:

less

Transcript and Presenter's Notes

Title: DOI ITIM Maturity Framework


1
  • DOI ITIM Maturity Framework
  • Capital Planning
  • Working Team Meeting
  • October 25, 2006

2
What is the GAO ITIM Maturity Framework?
  • Identifies and organizes 13 processes that are
    critical for successful management of
    investments.
  • The framework provides three key capabilities
  • Rigorous, standardized tool for internal and
    external evaluations of an agencys IT investment
    management process
  • Consistent and comprehensible mechanism for
    reporting the results of these assessments to
    agency executives, the Congress, and other
    interested parties and
  • Road map that agencies can use for improving
    their investment management processes.

3
Integration Requirements
  • Framework requires integration with other key
  • processes
  • Strategic Planning
  • project Management
  • Enterprise Architecture (EA) management
  • Human capital management
  • Software and system acquisition management.

4
Achievement of Stage 3 Maturity at DOI
  • Achievement of Stage 3 is DOI GPRA Goal
  • The 1993 Government Performance and Results Act
    (GPRA or the Results Act) introduced the concept
    of performance management to government. This
    important law required strategic and performance
    planning. It required agencies to set annual
    goals and then report annually on the extent to
    which they were achieving their goals.
  • DOI Expectations
  • 70 of Key Practices by end of FY 2007
  • 100 of Key Practices by end of FY 2008

5
GAO ITIM Maturity Framework Stages
6
Stage 3 Maturity Criteria
  • 1) Defining the Portfolio Criteria
  • Developing quantitative and qualitative factors
    to compare and select projects for the investment
    portfolio.
  • Purpose To ensure that the organization
    develops and maintains IT portfolio selection
    criteria that support its mission, organizational
    strategies, and business priorities.
  • Organizational commitments
  • The organization has documented policies and
    procedures for creating and modifying IT
    portfolio selection criteria.
  • Responsibility is assigned to an individual or
    group for managing the development and
    modification of the IT portfolio selection
    criteria.
  • Activities
  • The enterprise-wide investment board approves the
    core IT portfolio selection criteria, based on
    the organization's mission, goals, strategies,
    and priorities.
  • Project management personnel and other
    stakeholders are aware of the portfolio selection
    criteria.
  • The enterprise-wide investment board regularly
    reviews the IT portfolio selection criteria,
    using cumulative experience and event-driven
    data, and modifies the criteria as appropriate.

7
Stage 3 Maturity Criteria - continued
  • 2) Creating the Portfolio Criteria
  • Process of comparing worthwhile investments and
    then combining the investments selected into a
    funded portfolio.
  • Purpose To ensure that IT investments are
    analyzed according to the organization's
    portfolio selection criteria and to ensure that
    an optimal IT investment portfolio with
    manageable risks and returns is selected and
    funded.
  • Organizational commitments
  • The organization has documented policies and
    procedures for analyzing, selecting, and
    maintaining the investment portfolio.
  • Activities
  • Each IT investment board examines the mix of new
    and ongoing investments and their respective data
    and analyses and selects investments for funding.
  • Each investment board approves or modifies the
    performance expectations for the IT investments
    it has selected.
  • Information used to select, control, and evaluate
    the portfolio is captured and maintained for
    future reference.

8
Stage 3 Maturity Criteria - continued
  • 3) Evaluating the Portfolio
  • Process that builds upon the Providing Investment
    Oversight critical process from Stage 2 by adding
    the element of portfolio performance to the
    organizations control process activities
  • Purpose To review the performance of the
    organization's investment portfolio(s) at
    agreed-upon intervals and to adjust the
    allocation of resources among investments as
    necessary.
  • Organizational commitments
  • The organization has documented policies and
    procedures for reviewing, evaluating, and
    improving the performance of its portfolio(s).
  • Activities
  • Data on performance of the IT portfolio are
    defined and collected consistent with portfolio
    performance criteria.
  • Adjustments to the IT investment portfolio are
    executed in response to actual portfolio
    performance

9
Stage 3 Maturity Criteria - continued
  • 4) Conducting Post-Implementation Reviews
  • The PIR is conducted to
  • Examine differences between estimated and actual
    investment costs and benefits and possible
    ramifications for unplanned funding needs in the
    future and
  • Extract lessons learned about the investment
    selection and control processes that can be used
    as the basis for management improvements.
  • Purpose To compare the results of recently
    implemented investments with the expectations
    that were set for them and to develop a set of
    lessons learned from these reviews.
  • Organizational commitments
  • The organization has documented policies and
    procedures for conducting PIRs.
  • Activities
  • The investment board identifies which projects
    will have a PIR conducted.
  • Quantitative and qualitative investment data are
    collected, evaluated for reliability, and
    analyzed during the PIR.
  • Lessons learned and recommendations for improving
    the investment process are developed during the
    PIR, documented, and then distributed to all
    stakeholders.

10
CPWT Brainstorming
  • What are the most significant challenges that
    each bureau faces in achieving Stage 3 maturity?
  • What key practices are most challenging to
    implement?
  • How can the Department help each bureau address
    these challenges?
  • What do you need from your Bureau to address
    these challenges?

11
Validation of Achievement of Stage 3
  • Three Options for DOI to Consider
  • Independent assessment by contractors
  • Department Assessment
  • Independent assessment by peer team

12
Option One Independent Contractor Assessment
  • Pros
  • Less time by Government staff
  • Validation would be independent outside source
  • Thoroughly documented results
  • Cons
  • Cost for funding contract support.
  • Staff time to coordinate with contracting staff
  • CPIC Coordinators still have to evaluate work
    product and facilitate data collection
  • Audit-like report

13
Option Two Department Assessment
  • Pros
  • In-depth knowledge of DOI processes and
    procedures
  • Cost effective
  • Demonstrates Departments commitment to achieving
    goal
  • Cons
  • Constrained DOI CPIC Resources.
  • Bureau / Department tension Department
    judging performance of bureau.
  • Validation would not be totally independent

14
Option Three Independent Peer Assessment
  • Pros
  • CPIC Coordinators would have greater opportunity
    to learn about other bureaus processes.
  • Cost effective.
  • Minimizes confrontation promotes collaboration
  • Improved understanding on overall Department
    processes and other IT portfolios.
  • Cons
  • Requires CPIC Coordinators to take on additional
    responsibility
  • Some training time commitment
  • Validations would not be totally independent

15
DOI OCIO Preference Independent Peer Review Team
  • Format for Review
  • CPIC volunteers, teams of five to seven
  • Develop process/methodology for conducting peer
    assessments (November/December)
  • One bureau per quarter in order to spread out
    time-commitment
  • Start in FY 2007 2nd Quarter

16
Closing Thoughts
  • DOI and the bureaus need to partner and work
    together to meet ITIM Maturity Goals.
  • Achievement of Stage 3 maturity is a GPRA goal
  • Achievement of Stage 3 helps us better serve our
    customers
Write a Comment
User Comments (0)
About PowerShow.com