Title: TAJIKISTAN Energy Sector Situation Report
1TAJIKISTANEnergy Sector Situation Report
- A presentation by the World Bank to the meeting
of the Principals Group - November 20, 2008
- Dushanbe, Tajikistan
2Outline
- Lessons learned from last years emergency
- Energy Sector Situation Update
- Summary and Challenges Ahead
3LESSONS LEARNED FROM LAST YEARS EMERGENCY
4A Tajik man carries a stove pipe on a street of
Dushanbe January 22, 2008. Extreme cold is no
surprise to the 60 million people scattered
across a region wedged between Russia, China and
Iran, but this year's winter has exposed the poor
state of crumbling Soviet-era utilities and
pipelines and sparked energy shortages. Photo
Credits CENTRALASIA-COLD/ REUTERS/Nozim
Kalandarov (TAJIKISTAN)
5A trolley cannot move due to lack of power.
January 2008. Dushanbe, Tajikistan. Photo
credits Sodiq Haitov (Tajikistan)
6(No Transcript)
7ENERGY SECTOR SITUATION REPORT
8Nurek Reservoir Managed Relatively Well
- July inflow was considerably lower than average
while differences in other months were smaller
- Reached Dead Zone Mark on Feb 24/25
- Since May 14/15 Level has been above the
dead-zone mark - This year the full service level at Nurek
Reservoir was not attained - Maximum Nurek level was 902masl on September 20-21
9Better Nurek Reservoir Management Helping Manage
Situation
- Power supply in September-October was lower as
compared with same period last year - The Nurek Reservoir Management Model adopted by
Barki Tajik envisages an optimal alternative for
water release in November-March - Power supplies during 12/2008 through 02/2009 are
expected to be better than the last year
10Electricity Imports Assured Early On
- Generally achieved last winter
- Tajikistan imported 1350 GWh in January-April
2008 and - IQ 2008 Thermal generation was 24.2 GWh and about
double of this amount in form of thermal energy
was supplied to the Dushanbe District Heating
System - That is because gas supply was ensured and Fuel
Oil supply was managed well - There are two import agreement for 2008/2009
winter - With Turkmenistan for 1200 GWh in November
08-April 09 and - With Uzbekistan for 600 GWh in January-April 2009
11Power Supply Situation
Tajikistan Energy Balance
12Natural Gas Supplies
- Natural gas supplies have increased
- Industrial enterprises are main recipients
- Residential consumers are getting just 10 of
this volume - There are still arrears which need to be settled
soon
13SUMMARY AND CHALLENGES AHEAD
14Summary and challenges ahead - I
- Situation is muddling through, albeit in a
relatively better managed manner - Nurek Reservoir is managed relatively well
- This year the reservoir did not achieve the full
service level - At the moment, its about 17 meters below the
full service level mark and 36 meters above
dead-zone mark - Electricity imports started earlier
- Electricity imports from Uzbekistan September 1
onwards - Electricity imports from Turkmenistan October 31
onwards - Sangtuda-1 HPP output has doubled compared to
last winter - Third unit was put into operation in November
2008 - Thermal capacity at Dushanbe CHP was increased
- 120MW before circa 180 MW now
15Summary and challenges ahead - II
- Near-term challenges
- Reduce gas arrears and increase gas supplies
- In the cold weather, the electricity system is
severely burdened as a result of low volume of
gas supplies - Ensure all receive power and gasto make sure no
one is left in the cold - Tajikistan Energy Emergency Recovery Assistance
Project is under implementation - Medium-term challenges
- CASA 1000 Regional Transmission Project between
Afghanistan, Pakistan, Kyrgyz Republic and
Tajikistan is proceeding well - Funded jointly by ADB, WB/IFC, IsDB PSP
envisaged (10) - WB is financing Rogun HEP Feasibility Study
- WB is financing F/S for Nurek HPP Modernization
- USTDA is financing Fon Yagnob Coal-Cum-Power
Feasibility
16THANK YOU!