TAJIKISTAN Energy Sector Situation Report - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

TAJIKISTAN Energy Sector Situation Report

Description:

... Report. A presentation by the World Bank to the meeting of the Principal's Group ... Photo Credits: CENTRALASIA-COLD/ REUTERS/Nozim Kalandarov (TAJIKISTAN) ... – PowerPoint PPT presentation

Number of Views:48
Avg rating:3.0/5.0
Slides: 17
Provided by: wb177
Category:

less

Transcript and Presenter's Notes

Title: TAJIKISTAN Energy Sector Situation Report


1
TAJIKISTANEnergy Sector Situation Report
  • A presentation by the World Bank to the meeting
    of the Principals Group
  • November 20, 2008
  • Dushanbe, Tajikistan

2
Outline
  • Lessons learned from last years emergency
  • Energy Sector Situation Update
  • Summary and Challenges Ahead

3
LESSONS LEARNED FROM LAST YEARS EMERGENCY
4
A Tajik man carries a stove pipe on a street of
Dushanbe January 22, 2008. Extreme cold is no
surprise to the 60 million people scattered
across a region wedged between Russia, China and
Iran, but this year's winter has exposed the poor
state of crumbling Soviet-era utilities and
pipelines and sparked energy shortages. Photo
Credits CENTRALASIA-COLD/ REUTERS/Nozim
Kalandarov (TAJIKISTAN)
5
A trolley cannot move due to lack of power.
January 2008. Dushanbe, Tajikistan. Photo
credits Sodiq Haitov (Tajikistan)
6
(No Transcript)
7
ENERGY SECTOR SITUATION REPORT
8
Nurek Reservoir Managed Relatively Well
  • July inflow was considerably lower than average
    while differences in other months were smaller
  • Reached Dead Zone Mark on Feb 24/25
  • Since May 14/15 Level has been above the
    dead-zone mark
  • This year the full service level at Nurek
    Reservoir was not attained
  • Maximum Nurek level was 902masl on September 20-21

9
Better Nurek Reservoir Management Helping Manage
Situation
  • Power supply in September-October was lower as
    compared with same period last year
  • The Nurek Reservoir Management Model adopted by
    Barki Tajik envisages an optimal alternative for
    water release in November-March
  • Power supplies during 12/2008 through 02/2009 are
    expected to be better than the last year

10
Electricity Imports Assured Early On
  • Generally achieved last winter
  • Tajikistan imported 1350 GWh in January-April
    2008 and
  • IQ 2008 Thermal generation was 24.2 GWh and about
    double of this amount in form of thermal energy
    was supplied to the Dushanbe District Heating
    System
  • That is because gas supply was ensured and Fuel
    Oil supply was managed well
  • There are two import agreement for 2008/2009
    winter
  • With Turkmenistan for 1200 GWh in November
    08-April 09 and
  • With Uzbekistan for 600 GWh in January-April 2009

11
Power Supply Situation
Tajikistan Energy Balance
12
Natural Gas Supplies
  • Natural gas supplies have increased
  • Industrial enterprises are main recipients
  • Residential consumers are getting just 10 of
    this volume
  • There are still arrears which need to be settled
    soon

13
SUMMARY AND CHALLENGES AHEAD
14
Summary and challenges ahead - I
  • Situation is muddling through, albeit in a
    relatively better managed manner
  • Nurek Reservoir is managed relatively well
  • This year the reservoir did not achieve the full
    service level
  • At the moment, its about 17 meters below the
    full service level mark and 36 meters above
    dead-zone mark
  • Electricity imports started earlier
  • Electricity imports from Uzbekistan September 1
    onwards
  • Electricity imports from Turkmenistan October 31
    onwards
  • Sangtuda-1 HPP output has doubled compared to
    last winter
  • Third unit was put into operation in November
    2008
  • Thermal capacity at Dushanbe CHP was increased
  • 120MW before circa 180 MW now

15
Summary and challenges ahead - II
  • Near-term challenges
  • Reduce gas arrears and increase gas supplies
  • In the cold weather, the electricity system is
    severely burdened as a result of low volume of
    gas supplies
  • Ensure all receive power and gasto make sure no
    one is left in the cold
  • Tajikistan Energy Emergency Recovery Assistance
    Project is under implementation
  • Medium-term challenges
  • CASA 1000 Regional Transmission Project between
    Afghanistan, Pakistan, Kyrgyz Republic and
    Tajikistan is proceeding well
  • Funded jointly by ADB, WB/IFC, IsDB PSP
    envisaged (10)
  • WB is financing Rogun HEP Feasibility Study
  • WB is financing F/S for Nurek HPP Modernization
  • USTDA is financing Fon Yagnob Coal-Cum-Power
    Feasibility

16
THANK YOU!
Write a Comment
User Comments (0)
About PowerShow.com