Title: GWTIG Integration Proposal Near Term Functions
1GW/TIG Integration ProposalNear Term Functions
- Technical Work Group (TWG)
- October 14, 2005
2Outline
- TWG Charter Team
- Major Assumptions
- TWG Selection Principles
- Recommended Near Term Functions
- Work outline and cost estimate
3TWG Charter Schedule
- GW/TIG Integration Technical Work Group (TWG)
charter is to develop a report that recommends
the functions to be provided in the near term
(the first two years 2006/2007) under the
integration proposal including a rough outline of
the work to be done and an estimate of the cost - A first draft of the near term functions must be
completed and presented to the Integration
Steering Committee by October 20, 2005 - The final report must be presented October 31,
2005
4GW/TIG Integration TWG Team and Participation
5Major Assumptions
- Work outline and cost figures are preliminary in
nature - Cost estimates do not include
- Overhead costs (administration and oversight)
- We assume that they are covered as part of cost
of the GW development effort - It does include staff overhead
- Cost of TO participation
- We did not address expense allocation among
funding members - Open issue on funding near term services
- TA service fees, or
- Inclusion in funding agreement
- The earliest that the Integration Board will be
in place will be Q1, 2006 - No expenditures until Board is seated and the
Bylaws are adopted - Decision Point 4 will take place at least 2 years
after the Board is seated and the bylaws are
adopted, - Once the Near term implementation transmission
agreement (TA1) is implemented, there will be at
least 12 months where these services are
operational
6Major Assumptions Cont.
- We developed our own cost estimates ground up and
verified their overall consistency with GW/TIG
cost estimates whenever possible - The Integration Board will oversee
design/development of TSLG basic features and the
implementation of near term functions
Integration Board will also play the role of the
following bodies for the near term (2006-2007) - Transmission Expansion Review Council (TERC)
- Market Monitoring Committee (MMC)
7Major Assumptions Cont.
- In the near term, for functions TIG addressed
that are being directly funded and developed by
another regional entity such as WECC, PNSC, or
NWPP, the Integration Board will - Actively monitor and support their development to
ensure their successful and timely completion and
operation - Participate in the development of requirements,
standards, business practices and desired
outcomes - Participate in the design, development and
implementation of all the necessary
infrastructure - If the development of such functions is delayed
or abandoned, step in, subject to feasibility and
continued value, to complete appropriate elements
as part of this near term effort - Review such functions at the time for value and
feasibility - Designate the necessary resources for their
timely completion and deployment - Cost of such potential undertakings is not
included here
8TWG Selection Principles for Near Term Functions
- Function is recommended by the TIG report and
provides immediate value for the region - Function can be reasonably implemented and be
operational in the near term - next two (2) years - Function is not inconsistent or incompatible with
the solution proposed in the TSLG Basic Features - We have also assumed that design/development of
the TSLG Basic Features will move forward in
parallel and close coordination with the
development of the near term functions proposed
here
9Near Term Transmission Planning Functions
- Integration Board to hire staff for a planning
organization whose near term responsibilities
will be to - Develop open planning processes and procedures
- Develop transmission adequacy standards in
coordination with region - Use existing standards for the first biennial
plan - Participate in WECCs transmission adequacy
development process - Coordinate planning with all regional entities,
run studies and produce Biennial Plans - Collect system info and build basecases
- Perform some system studies and coordinate with
other entities for others - Document "Problem Need Statements"
- Use WECC/NERC minimum criteria supplemented with
TOs criteria as needed - Coordinate congestion analysis responsibility
with NTAC - Propose projects to relieve major congestion
problems as identified by the Integration Board
in coordination with the region
10Near Term Transmission Planning Functions Cont.
- Planning organizations near term
responsibilities (cont.) - Submit Biennial Plans to Integration Board
- Integration Board will play the role of TERC
- Modify the plan per Integration Board
instructions - Facilitate the development of cost and capacity
allocation methodology and backstop model for
reliability and firm obligation projects - Apply to the first biennial plan
- Planning organization will rely heavily on TOs
and other regional entities to conduct many of
the necessary planning studies - The scope of this reliance to be determined as
part of the open planning process design
11Work Outline Cost Estimate for the Near Term
Transmission Planning Functions
12Near Term IMM Functions
- Integration Board to contract with a qualified
independent contractor as the Independent Market
Monitor (IMM) - Integration Board would also play the role of MMC
for the near term - IMMs near term responsibilities will be to
- Produce state of market (SOM) reports annually
- Report to Integration Board
- Establish direct relationships with states,
federal, and provincial regulatory/enforcement
and oversight entities and submit un-redacted
reports, governed by non-disclosure agreements,
to such entities - Establish data exchange protocols and solution
with market participants
13Near Term IMM Functions Cont.
- IMMs near term responsibilities (continued)
- Monitor and analyze regional transmission and
wholesale power markets - For the initial SOM, the IMM would prepare a
general retrospective report based to the
greatest extent possible on publicly available
information - Report to the Integration Board as well as other
appropriate oversight/regulatory bodies about
market irregularities without intervening itself
to remedy behavior or market structure - Monitor activities in adjacent wholesale power
and transmission markets as well as related
commodities (e.g., gas market) for their impact
on the wholesale power and transmission markets
in the region - Recommend and assist in market investigations in
response to complaints as well as on own
initiative
14Work Outline Cost Estimate for Near Term IMM
Functions
15Near Term Common OASIS Functions
- Integration Board to hire a Common OASIS
Coordinator - Common OASIS Coordinators near term
responsibilities will be to - Develop and implement an OASIS Agreement for
signature by TOs - Select and put into place contract between an
OASIS vendor and TOs to implement a Common
Northwest OASIS on an outsource basis - The TOs will sign appropriate agreements and pay
associated costs - Consider WesTTrans as an available option
- Coordinate Common OASIS operation including all
path offerings from multiple owners. - Develop common business practices among TOs
16Work Outline Cost Estimate for Near Term
Common OASIS Functions
17Near Term Reliability and Security Functions
- Integration Board to assign resources to monitor
and support Reliability and Security initiatives
by regional entities - Development of PNSCs tools for flow and voltage
and transient stability analyses for real-time
and hour-ahead use - Development of PNSCs day ahead operational
analysis - Development of PNSCs infrastructure to comply
with updated security coordination requirements - Development of NWPPs ACE Diversity Interchange
through reserve sharing system - Development of WECCs regional database for
reliability data that can be shared among
participants - Development of TSLGs Consolidated Control Area
(CCA) - Cost of CCA development is addressed separately
18Near Term Reliability and Security Functions
Cont.
- Step in to complete above functions, subject to
feasibility and continued value, if their
development is delayed or abandoned - Cost of such undertakings is not included here
- If at Decision Point 4, the region decides not to
implement Grid West, the Integration Board will
pursue development of additional necessary
reliability measures including the voluntary
consolidation of control areas
19Work Outline Cost Estimate for Near Term
Reliability Security Functions
20Near Term Flow Based ATC Calculation Function
- Support development and implementation of TSLGs
Flow Based ATC calculator - The cost of development and implementation of
Flow Based ATC calculator is addressed separately - Use the developed Flow Based ATC calculator in
parallel with actual operation for testing and
evaluation purposes as judged effective
21Work Outline Cost Estimate for Near Term Flow
Based ATC Calculation Function
22Near Term Admin and Legal
- Secretarial and administration support needed for
the Near Term Implementation staff. - Hire contract legal assistance to assist with
writing the Near Term Implementation Transmission
Agreement (TA1) and providing Near Term
Implementation Staff legal advice on operational
and development issues.
23Work Outline Cost Estimate for Near Term Admin
and Legal
24Cost Estimate for All Near Term Functions
25TWG Next Steps
- Factor in input from today into TWG proposal
- Modify selected near term functions as well as
work outlines and cost estimates as necessary - Prepare a report based on the final list of near
term functions as well as their work outlines and
cost estimates - Present the report to the Regional Forum on
10/28/2005
26Comparison to TIG cost estimate
- The TIG estimated cost was 50.5 million per
year, of this - 22.4 million was associated with the RABA
function, which will not be implemented in the
near term - 28.1 million was associated with non-RABA
functions - Of the 28.1 million of non-RABA cost
- Significant cost was associated with moving to
flow based ATC calculation. This is not expected
to be implemented in the near term, - Given the uncertainty of the development of
Reliability and Security initiatives, it was
assumed that TIG would fund and develop these. - The region will still carry these costs, but
under the WECC, NWPP, and PNSC - There are also some non-RABA reliability
functions not being implemented in the near term