Minimising the Impact Maximising the Benefit - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

Minimising the Impact Maximising the Benefit

Description:

... A B C D E F G H I J K L M N O P Q R S T U V W X Y Z [ ] ^ _ ` ... 456789:CDEFGHIJSTUVWXYZcdefghijstuvwxyz GpSs tFTO ... – PowerPoint PPT presentation

Number of Views:15
Avg rating:3.0/5.0
Slides: 30
Provided by: luciwestp
Category:

less

Transcript and Presenter's Notes

Title: Minimising the Impact Maximising the Benefit


1
Minimising the Impact Maximising the Benefit
  • Designing the New EMEA Data Centre

John Killey EMEA Head Citi Realty Services
2
The Challenge
  • By 2011 Citi is committed to reducing our
    greenhouse gas emissions by 10 from our 2005
    baseline.
  • With more than 85 million SF of Real Estate this
    equates to 130,000 tonnes of CO2.
  • To be achieved through our corporate culture that
    embeds principles of environmental responsibility
    and sustainable growth.
  • We recognize that climate change is a major
    economic, social and environmental challenge
    globally.
  • We have set a target to reduce our greenhouse gas
    emissions and work with our clients to provide
    innovative solutions as they strive to reduce
    their own emissions.
  • Chuck Prince,
  • Chairman and CEO of Citigroup
  • Citigroup Citizenship Report 2006

3
The Challenge
  • To deliver a 100,000 SF state of the art of
    1000 W/m2 (scaleable to 1500 W/m2) data centre.
  • To ensure the data centre achieves the following
    key design requirements of
  • Reliability
  • Performance
  • Cost optimisation
  • Energy efficiency
  • Minimising the environmental impact
  • To achieve greater than Tier IV reliability (gt
    99.995 availability).
  • To minimise the environmental impact through all
    phases of the facilities life .

4
Minimising the Impact
  • LEED (Leadership in Energy and Environmental
    Design) an accepted benchmark for a buildings
    energy and environmental impact during
  • Design
  • Construction
  • Operation
  • Provides an immediate tool for measuring and
    comparing the environmental impact performance.
  • Promotes a whole building approach to
    sustainability looking at 5 key areas of human
    and environmental health
  • Sustainable site development
  • Water savings
  • Energy Efficiency
  • Material selection
  • Indoor environmental quality
  • Initial target was for Silver LEED certification.

5
Minimising the Impact
  • LEED estimate at concept design- Silver 3 points
    from Gold

6
Minimising the Impact
  • Key Procurement Considerations
  • Senior management commitment from
  • Client
  • Designers
  • Contractors
  • Environmental requirements embodied in
  • Consultant Briefing Documentation
  • Design Documentation
  • Procurement Documentation
  • and forms part of contract documentation
  • Collaboration will be vital during construction
    and commissioning phase

7
Minimising the Impact
  • Key Design Considerations for the Sustainable
    Vision
  • Use of low environmental impact materials.
  • Consideration of embodied energy of construction
    materials and their benefit as environmental
    modifiers.
  • Minimisation and reuse of excavated materials on
    site.
  • Minimisation of site waste and maximisation of
    on-site recycling.
  • Water efficiency and rainwater salvage.
  • Site planting, garden zones the vegetation of
    external facades.

8
Minimising the Impact
  • Embodied CO2
  • Embodied CO2

9
Minimising the Impact
  • Key Design Elements
  • Green Roof and Green Wall
  • Creates biodiversity lost in the construction
  • Increased roof life/reliability waterproof
    membrane life increased to 40 years
  • Reduced rain water run off with reduced
    construction, sewer/storage costs
  • Benefits to ecology through rainwater attenuation
    and re-use
  • Converts CO2 to O2.

10
Minimising the Impact
  • Green Wall
  • Embodied CO2

11
Minimising the Impact
  • Material Selection
  • External shading (brise soleil) constructed from
    zero maintenance timber from sustainable sources
  • External aluminium panel screening with high
    recycled content
  • High use of locally extracted/produced building
    materials to reduce cost and transportation CO2
    emissions.

12
Minimising the Impact
  • Aluminium Louvred Fins
  • 300 blades x 150 mm Centres
  • Embodied Energy 12,681 kg of CO2
  • Chosen Scheme
  • Timber Louvered Fins
  • 300 blades x 300 mm Centres
  • Embodied Energy 4,081 kg of CO2
  • 33 IMPROVEMENT OVER ALUMINIUM

Citigroup Operations Technology - INTERNAL
13
Minimising the Impact
  • Water Management
  • Reverse Osmosis water treatment plant in lieu of
    conventional base exchange softeners. Blow down
    Recycling
  • Higher reliability with reduced water usage for
    backwashing and regeneration saving 11.6MM US
    galls p.a./ 217m p.a.
  • Lower chemical and CO2 emissions
  • Capturing up to 90 of rainwater for reuse on
    site.
  • Air Flow Management
  • Under floor baffling converts velocity into
    static pressure, eliminating recirculation and
    low pressure zones under the active area of the
    raised floor.
  • High level data cabling eliminates under floor
    cable dams and requires no data cable
    penetrations.
  • A false ceiling provides a return air plenum that
    captures hot exhaust air from servers, reducing
    recirculation.
  • CRAC units controlled on supply air temperature
    improves cooling efficiency as units cannot fight
    each other.

14
Minimising the Impact
  • Good practice in airflow management means
    segregating cool supply air and hot exhaust air

The hot exhaust air must be captured by the CRAC
units without mixing with cool supply air.
To avoid overheat, the cool air must make its
way to the equipment inlets without mixing with
exhaust air.
The CRAC units supply air to the floor void.
The air enters the room through perforated tiles
15
Minimising the Impact
  • Under floor airflow management
  • Perforated baffles attached to floor jacks in
    front of CRAC convert velocity into an even
    static pressure.
  • High velocity jets and recirculation under the
    active floor area are eliminated.
  • Variable speed drive fans automatically maintain
    the even pressure in the event of CRAC failure.
  • Typical pressure distribution under a raised
    floor
  • New Citigroup Data Centre

16
Minimising the Impact
  • Above floor airflow management
  • Open network frames are interleaved with server
    racks to reduce length of data cabling.
  • All data cabling is at high level to eliminate
    cable dams and data cable penetrations.
  • Novel Hot-Aisle/Cold-Aisle/Cold-Aisle layout
    overcomes typical problems with open frames
  • Typical problems with open frames
  • Open network frames cause breakdown of the
    Hot-Aisle/Cold Aisle concept.
  • Hot exhaust air from server racks recirculates
    around the network equipment causing overheat.
  • New Citigroup layout
  • Hot exhaust air from server racks is captured by
    ceiling plenum.
  • Network equipment in open frames is cooled
    successfully.

Hot
Cold
Cold
Hot
Cold
Hot
Hot
Cold
Cold
Hot
Cold
Hot
Cold
Cold
17
Minimising the Impact
  • Using a Virtual Facility
  • Airflow and temperature can be visualised and
    managed
  • Courtesy of Future Facilities Ltd.

18
Minimising the Impact
  • Free Cooling
  • High internal air temperature.
  • CRAC supply 20C (5-7C higher than a typical
    data centre)
  • CRAC return 27-29C (5-7C higher than a typical
    data centre)
  • High chilled water temperature.
  • Flow 10C (3C higher than a typical data
    centre)
  • Return 18C (6C higher than a typical data
    centre)
  • 2 coil CRACs linked to free cooling heat
    exchangers.
  • Free and pre cooling available from 17C external
    WBT.
  • Provides free and pre cooling for 8,183hrs per
    annum (93 of the time)
  • Provides 8,486 MWhr of free cooling per annum.
  • 2 coils provide a 2N cooling system at the CRAC
    (gt Tier IV stds.)
  • Free cooling increases 3N system redundancy in
    winter period (gt Tier IV stds)

19
Minimising the Impact
  • Contractor Involvement
  • LEED language in each specification section
  • LEED Pre-Construction Manual
  • Pre-Bid Meetings
  • Post/Award Meetings
  • Subcontractor Orientation
  • The Contractors role in specific LEED Credits
  • Erosion and Sedimentation Control Plan
  • Commissioning Coordination
  • Construction Waste Management
  • Performance-based Material and Resource Selection
  • Construction IAQ Management
  • Low Emitting Material Management

20
LEED Point Summary
21
LEED Point Summary
22
LEED Point Summary
23
Maximising The Benefit
  • What does this all save us?

24
Maximising The Benefit
  • What does this save us overall?

25
Maximising The Benefit
  • or to put it another way
  • Power Consumption of a typical Data Centre

26
Maximising The Benefit
  • Power Consumption CG Data Centre

27
Maximising The Benefit
  • What does this deliver?
  • A data centre with greater than tier IV
    reliability.
  • A data centre that delivers the design loads.
  • A data centre with a capital cost -8 than
    conventional facility.
  • A data centre that uses 20 less energy in its
    services.
  • At data centre that saves 11,700 tonnes of CO2
    per annum.

28
Maximising The Benefit
  • Sound environmental design does make business
    sense and can enhance reliability.
  • Can only be achieved by embedding the concepts of
    sustainability within the design, construction
    and operations processes.
  • Will only be achieved through a collaborative,
    integrated design and construction process.
  • Must start with the initial project planning and
    run through the whole building life cycle.

29
Maximising The Benefit
  • Sound environmental design does make business
    sense and can enhance reliability.
  • Can only be achieved by embedding the concepts of
    sustainability within the design, construction
    and operations processes.
  • Will only be achieved through a collaborative,
    integrated design and construction process.
  • Must start with the initial project planning and
    run through the whole building life cycle.
Write a Comment
User Comments (0)
About PowerShow.com