Title: Western Area Power Administration


1
Western Area Power Administration
  • Transmission Customer Meeting
  • October 17, 2007

2
Western Area Power Administration
  • AGENDA
  • POWER OPERATIONS UPDATE
  • General Update
  • 890 Filing
  • Darren Buck, Power Operations Manager
  • ATC Calculations
  • Mariam Mirzadeh, Transmission Planning Engr.
  • Rates Update
  • Sean Sanderson, Rates Manager

3
Western Area Power Administration
Physics of Disturbances
  • Thermal Overloads
  • Voltage Limits
  • System Stability
  • Transient Voltages
  • Frequency Limits
  • Damping
  • VARs and Voltage Stability
  • Remedial Action Schemes
  • System Synergy
  • Islanding
  • Cascading

4
Western Area Power Administration
Transfer Capability Limit Criteria
  • Total Transfer Capability (TTC)
  • Maximum amount of power that can be transferred
    across an interconnection or a transfer path from
    one control area to another or within an area
    while ensuring that the transmission system is
    able to suffer and recover from a severe outage
    (meeting the NERC/WECC reliability criteria).
  • Net schedules shall not exceed TTC
  • TTC ATC are directional
  • Operating Limits
  • No element shall be scheduled above its
    continuous operating limits

5
Western Area Power Administration
Transfer Capability Limit Criteria Contd
  • Stability Following an Outage
  • N-1s shall not cause cascading
  • System Response to Contingencies Prior to
    Readjustment (Transient period)
  • Voltages and element loading shall meet the
    WECC/NERC corresponding criteria, loading shall
    not exceed emergency ratings

6
Available Transfer Capability (ATC) OATT
Mandatory Reliability Requirements
7
Western Area Power Administration
  • ATC TTC (allocated to Western) Committed Uses
  • Where Committed Uses Existing Transmission
    Commitments Transmission Reliability Margin
    (TRM) Capacity Benefit Margin (CBM)
  • TRM Includes Unscheduled Flow (Loop Flow)
    Accommodation for any simultaneous limitations
    associated with operation under a nomogram
    Uncertainty in load forecasting regulation,
    etc.

8
Western Area Power Administration
  • CBM Includes Capacity for movement of water in
    order to meet Bureau of Reclamation/Corp of
    Engineers water schedules, or for moving
    generation under black starts conditions.
  • All transmission (PACI, COTP, network and P-P)
    reservations are subject to real-time operation
    operating limitations especially the Sacramento
    area simultaneous import Nomogram.

9
Western Area Power Administration
  • CVP Network transmission ATC calculation
    methodology, SNR business practice 20
  • https//www.westtrans.net/WASN/WASNdocs/CVP_Trans_
    BP-20_V_01_10-15-07.pdf
  • OATT
  • http//www.oatioasis.com/WASN/WASNdocs/tariff_mast
    ercopy_(11_05).pdf
  • Rates http//www.wapa.gov/sn/marketing/rates/

10
Western Area Power Administration
  • Questions/Discussion