St. Louis River/Interlake/Duluth Tar
Site (SLRIDT)
  • Site Overview
  • Dredge/Cap Hybrid
  • Remedy Description

2
(No Transcript)
3
(No Transcript)
4
  • Industrial activities beginning in 1890s and
    lasting until 1961 contaminated the soil,
    groundwater, surface water and sediment at this
    site.

1939
1910
  • Over 60 years of waste water discharges from
    the water gas, coking, and tar facilities
    formerly located on the Site resulted in
    extensive sediment contamination

1947
5
(No Transcript)
6
Site Contamination
  • Industrial waste discharge of coal tar and tar
    refining waste
  • PAHs polyaromatic hydrocarbons
  • Metals As, Cd, Cr, Cu, Pb, Ni, Zn and Hg

Metals -
7
(No Transcript)
8
Stryker Bay Oil Blooms
9
High Naphthalene Concentration
10
Stryker Bay Depth
11
SURCHARGE-CAPPING
12
Surcharged Consolidation
Peat
Silt
Sand
13
Stryker Bay Depth
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Greater than 8 feet finished water depth
Less than 8 feet finished water depth
CAD
Root Barrier
BAZ
5 Ft
BAZ
1 M
Environmental Media
4 Ft
BAZ
0.5 M
3 Ft
BAZ
2.0-2.5 Ft
IZ
IZ
IZ
IZ
Contamination
Contamination
Contamination
Contamination
5-Foot Cap
4-Foot Cap
3-Foot Cap
2.0-2.5-Foot Cap
19
Treated CAD Water Discharge
Discharge with full treatment
20
St. Louis River/Interlake/Duluth Tar