FABEC Stakeholder Forum Project Implementation Status Peter Naets, Project Manager FABEC Amsterdam,

Description:

CDS. 26-May. Approved. VCS. 20-Oct. Approved. ATFCM/ASM. 21 ... Budget. Answers all Questions - basis for final decision on TFs. 9. VCS specification task force ... – PowerPoint PPT presentation

Number of Views:129
Avg rating:3.0/5.0
Slides: 13
Provided by: Wylie
Category:

less

Transcript and Presenter's Notes

Title: FABEC Stakeholder Forum Project Implementation Status Peter Naets, Project Manager FABEC Amsterdam,


1
FABEC Stakeholder Forum Project Implementation
Status Peter Naets, Project Manager
FABECAmsterdam, 3 November 2008
2
Challenge
  • From Feasibility to Implementation
  • Develop Implementation Plan
  • Meet stakeholder requirements

3
Initiate FABEC Implementation
4
Project setup
  • Project Charter (FPSG) available
  • Project Management Plan (PMO) available
  • PMO operational
  • at Belgocontrol
  • manning completed (PM, 2 D-PM, QM/HoS, Srt).
  • 8 Task Forces started
  • Detailed Working Plan - under development
  • Performance focus
  • Flight efficiency, cost effectiveness
  • Early benefits short- or medium-term
    implementation

5
Task forces
  • Basis
  • Feasibility Study Report
  • High Level Roadmap
  • Criteria
  • FABEC Essential
  • FABEC Opportunity

6
8 Task Forces Project organisation started
  • Hot Spots
  • Scope is adjusted to current developments
  • More than Hot Spots (e.g. Airspace Design,
    Concept elements)
  • ATFCM / ASM
  • Voice Communication System specification
  • Next slides
  • Enhanced OLDI
  • Common Data Service
  • Air Ground Data Link Services
  • Ab Initio Training
  • From Ab Initio towards ATCO training
  • ANSP Agreement
  • ANSP Agreement ready for signature 18 Nov 08

7
8 Task forces status

8
Content ToR and WBS
  • Terms of Reference ToR
  • Objectives
  • Deliverables
  • Method of working
  • Work Breakdown Structure WBS
  • Performance framework
  • Overall schedule
  • Milestones
  • Assumptions
  • Risks
  • Planning
  • Resources
  • Budget
  • Answers all Questions - basis for final decision
    on TFs

9
VCS specification task force
  • Scope extended to common procurement /
    maintenance
  • Meeting common requirements and FABEC specifics
  • Perform ATC from different locations
  • Interoperability requirements (EC Reg 552/2004
    Ann II part B 4)
  • Reality check with industry
  • Cost / benefit statement
  • 260k ANSP manpower
  • Cost reduction when 3 systems procured 6m

10
FABEC Impact Assessment Radio
FAB philosophy
EXTENDED RADIO COVERAGEorRADIO SITE HOSTING
11
Project Baseline
  • Performance Framework
  • Safety
  • Capacity
  • Flight Efficiency
  • Cost Effectiveness
  • Environment
  • Military Mission Effectiveness
  • TIMING FOR IMPLEMENTATION

8 Task forces - 2008
x Task forces - 2009
Tailored Routes, AMAN, CNS Optimisation, ARTAS
Track Services, AIM, Harmonized REG, Safety
5 Task forces States
Decision
Baseline Approval HLIB
12