Intertie Project - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Intertie Project

Description:

Calpine filed for Bankruptcy protection late in 2005 ... When bankruptcy filing done, Western was owed approx. $1M (two months' service) ... – PowerPoint PPT presentation

Number of Views:11
Avg rating:3.0/5.0
Slides: 28
Provided by: toddst4
Category:
Tags: intertie | project

less

Transcript and Presenter's Notes

Title: Intertie Project


1
Intertie Project
  • Public Information Forum
  • February 8, 2007

2
Agenda
  • Overview of the Rate Adjustment Process
  • Review Rate Drivers and Proposed Rates
  • Discuss Approaches to Rate Adjustment
  • Westerns Recommendation
  • Next Steps
  • Questions and Comments

3
Rate Adjustment Process
  • Informal Rate Meeting June 15, 2006
  • Formal Process for Rate Adjustment July 12,
    2006
  • Publication of Federal Register Notice of
    Proposed Rates
  • Beginning of Consultation and Comment Period
  • Public Information Forum August 17, 2006
  • Public Comment Forum August 24, 2006
  • End of Consultation and Comment Period October
    10, 2006
  • Extension of Rates Public Process December
    28, 2006
  • Publication of Federal Register Notice of Order
    Extending Rates and Extension of Public Process
    for Rate Adjustment

4
Rate Drivers FY 2008-2012FY99 Ratebase PRS
5
Rate Drivers FY 2008-2012FY07 Ratebase PRS
6
Summary of Rate Drivers
  • Significant increase in Repayment category as a
    percentage of the average total annual costs
  • Moderate increase in OM and minor increase in
    Other categories
  • Overall, substantial increase in total annual
    costs to recover over short period of time

7
Average Annual Expenses
8
Annual Expense Projections
  • FY 2008 OM expenses derived from budget
    estimates submitted to DOE and OMB.
  • FY 2009-2012 OM expenses indexed off FY 2008
    budget estimates _at_ 3.65, consistent with budget
    submission
  • Repayment applied towards an estimated FY 2006
    unpaid capitalized deficit balance of 54.4M, of
    which 41.7M are required payments

9
Annual Expense Summary
  • Largest contributor to proposed rates is the
    short-term repayment obligation associated with
    capitalized deficits
  • Why the increase in repayment obligation?
  • Lower than projected sales of 500-kV transmission
    service
  • Revenue shortfall resulted in capitalized
    deficits with short-term repayment periods

10
Which Leads Us to Where We Are Today
  • Rate Adjustment necessary to ensure recovery of
    annual costs and repayment of project
  • Rates must be lowest possible consistent with
    sound business principles
  • Several approaches to Rate Adjustment

11
Alternatives to Consider
  • Standard Approach
  • Alternative Approach
  • Restructure 500-kV Sales Assumptions
  • 230/345/500-kV System Rate
  • Combination of the above

12
Standard Approach
  • Update proposed rates presented during the Public
    Information Forum held August 17, 2006
  • Pros
  • No additional deficits planned after FY 2007
  • Most conservative approachminimizes overall
    interest costs over project repayment
  • Cons
  • Highest immediate rate increase
  • Prices 500-kV transmission service significantly
    higher than other providers
  • Higher risk of not achieving 500-kV sales
    assumptions

13
Pinch Points
14
Alternative Approach
  • Use certain repayment flexibilities when
    determining proposed rates
  • Incur additional deficits to cover annual
    expenses and required payments
  • Direct payments to reduce a future year pinch
    point repayment obligation after deficit
    repayment completed
  • Pros
  • Lessens the impact of the immediate rate increase
  • Still makes required payments each year in
    accordance with DOE Order RA 6120.2
  • Ensures project repayment within maximum
    allowable time frame

15
Alternative Approach, Contd
  • Cons
  • Increases interest costs during project repayment
  • Potential future rate increases if sales
    assumptions do not materialize
  • Directing payments is allowed under DOE Order RA
    6120.2 only when no unpaid capitalized deficits
    exist
  • All current and future capitalized deficits must
    be paid off by FY 2017 to begin directing
    payments

16
Restructure 500-kV Sales Projections
  • Existing rates were based on phasing-in sales of
    500-kV transmission service
  • Phase-in period began in FY 1999 with projected
    sales of 62.5 MW, incremental sales of 100 MW
    each fiscal year and ends in FY 2008 with total
    sales of 962.5 MW
  • Current long-term sales are 612 MW
  • Proposed rates from July 2006 proposal assume
    sales of 962.5 MW in FY 2008 and beyond, i.e.
    sales projections were not restructured

17
Restructure 500-kV Sales Projections
  • Extending the phase-in period by five years will
    allow Western additional time to market long-term
    500-kV transmission service
  • Restructuring the sales projections over the next
    five years will give Western flexibility to
    achieve the phase-in total sales of 962.5 MW
  • Aligns sales projections based on performance to
    date and future outlook

18
230/345/500-kV System Rate
  • Legislatively, and from a financial accounting
    and repayment standpoint, the Intertie is one
    project
  • Indirect costs are allocated to the Intertie
    Project, not to the 230/345-kV and 500-kV
    transmission systems
  • Slower than projected sales of 500-kV
    transmission service does not relieve Western
    from Intertie Project repayment responsibility.
  • A 230/345/500-kV rate is consistent with sound
    business principles

19
Westerns Recommendation
  • Combination of the above
  • Alternative Approach
  • 230/345/500-kV System Rate
  • Restructure the 500-kV Sales Assumptions
  • Alternative Approach
  • Makes required payments in all years in
    accordance with DOE Order RA6120.2
  • Incurs additional deficits in FY 2007-2010
  • Pays deficits first, then begins directing
    payments in FY 2017

20
Recommendation, Contd
  • 230/345/500-kV System Rate
  • The same rate for entire transmission system
    regardless of voltage level
  • Potential for additional sales by moving
    reservations from the 230/345-kV to the 500-kV or
    vice versa
  • Beneficial for all customers by keeping the
    500-kV transmission system competitively priced
  • Restructure 500-kV Sales Assumptions
  • Extend phase-in period by five years to achieve
    sales
  • Attain 962.5 MW sales level by FY2013

21
230/345/500 System Rate
  • 15.24 kW-Yr, regardless of voltage
  • Assumes additional deficits incurred FY 2007-2010
    and all deficits paid by FY 2017
  • Begins directing payments in FY 2017
  • Extends phase-in period of 500-kV sales
    projections to FY 2013

22
Transmission Service Rates
23
Credit Risk Mitigation for Transmission Service
Sales
  • Current business practice requires customers to
    pay for transmission service after the fact,
    usually one month in arrears
  • Western can be at risk for up to 4 months
    revenue in event of default
  • All customers will be required to pay in advance
    for long-term transmission service
  • New business practice of pre-payment will reduce
    the revenue risk exposure to one month

24
Credit Risk MitigationExample
  • Calpinefiled for Bankruptcy protection late in
    2005
  • Monthly transmission service bills approx. 500k
  • When bankruptcy filing done, Western was owed
    approx. 1M (two months service)
  • Loss of revenue impacts all rate payers
  • Payment in advance could have reduced exposure

25
Credit Risk Mitigation
  • Current environment - companies financial and
    credit status can change quickly
  • Many of Westerns customers have no credit rating
  • Payment in advance mitigates risks
  • Many customers already pay for long-term
    transmission service in advance
  • Firm Electric Service customers pay in advance

26
Schedule
  • Revised rate brochure will be available on
    Westerns website by 2/12/07 at
    http//www.wapa.gov/dsw/pwrmkt/Intertie/RateAdjust
  • Public Comment Forum scheduled for February 27,
    2007 at 1000 a.m. MST
  • Consultation and comment period ends March 28,
    2007
  • Questions not answered today will be answered in
    writing no later than 15 days prior to the end of
    the comment period.

27
Comments Questions
  • Send written comments to J. Tyler Carlson,
    Regional Manager
  • Comments may also be faxed to 602-605-2490, Attn
    Jack Murray, Rates Team Lead
  • E-mail to Tyler Carlson, carlson_at_wapa.gov or
    Jack Murray, jmurray_at_wapa.gov
  • All written comments must be received by the end
    of the comment period
Write a Comment
User Comments (0)
About PowerShow.com