2SAP GeBIZ
- Purchasing Briefing by
- Office of Finance (FIN)
- 25th and 26th September 2006
3SAP GeBIZ
- What is SAP Purchasing Module?
- What is GeBIZ Enterprise System?
- When to use?
- Critical Points
- Frequently Asked Questions
4What is SAP Purchasing Module?
- SAP stands for Systems, Applications and Products
in data processing. - SAP Purchasing Module is one of the modules
available in the SAP Financial System.
5When to use it?
- This module is to be used for the purposes of
- (a) creating Purchase Orders (POs) for awarded
tenders (one-off purchase) - (b) obtaining Goods Receipt (GR) Document Number
for interfaced GeBIZ POs - (c) creating asset master records
6Critical Points
- (1) Ensure correct PO Document Type is used.
- Rationale
- PO Document Type is a non-changeable field
- if the selection is incorrect
- The PO created will not reach the intended FIN
Approving Officer for approval. - The entire PO has to be cancelled and created
again.
7Critical Points- (continue)
8Critical Points- (continue)
- (2) Ensure name and address of vendor selected
are correct. - Rationale
- Vendor, once selected, cannot be amended.
- The entire PO has to be cancelled and created
again if the selection is incorrect.
9Critical Points- (continue)
- (3) Ensure correct tender reference number is
being indicated under the Reference No. field
and only 1 line is used. - Rationale
- Facilitate verification by FIN to ensure PO
raised is for an approved tender. - Purchase will be delayed if incorrect tender
reference number is used. - PO cancellation letter will not be in order as
the additional lines entered will be shown.
10Critical Points- (continue)
- (4) Ensure no exception message encountered
before checking GR document number in SAP. - Rationale
- Avoid undue delay in processing.
11Critical Points- (continue)
- (5) Ensure cost centre of asset master record
created is correct. - Rationale
- Avoid undue delay in PO creation in GeBIZ.
12Summary
- To recap, the following have been discussed -
- 1. Use of the SAP Purchasing Module
- - creating POs for awarded tenders (one-
- off purchase)
- - obtaining Goods Receipt (GR)
- Document Number for interfaced GeBIZ
- POs
- - creating asset master records
13Summary- (continue)
- 2. Critical Points
-
- Correct PO Document Type
- Correct vendor
- No exception message on GR
- Correct cost centre for asset master
- Reference No. field
14What is GeBIZ Enterprise System?
- GeBIZ stands for Government electronic Business.
- GeBIZ Enterprise System is an easy to use
Government Intranet Application to facilitate
procurement by public sector officers. - The usage of this system has been extended to NTU
even though we have been corporatised.
15When to use it?
- There are various procurement modules available
namely -
16GeBIZ Charges
- Rates are as determined and set by Defence
Science and Technology Agency (DSTA) for each
Financial Year (FY) - It is incurred once a PO number has been
generated regardless of whether the PO has been
interfaced successfully to SAP. - Termination/cancellation of PO will not incur
charges
17GeBIZ Price Plan for FY 2006/2007
Source http//intranet.gebiz.gov.sg/scripts/doc/p
rice_plan.pdf
18Critical Points
- (1) Ensure sufficient fund is set aside for GeBIZ
charges, especially during closing of FY. - Rationale
- POs created are subject to Admin Fee (where
applicable) and relevant GeBIZ charges.
19Critical Points- (continue)
- (2) Ensure for period contracts, the best option
that suit specifications and budget is being
selected. - Rationale
- Proper selection of options would ensure optimal
usage of limited budget.
20Critical Points- (continue)
- (3) Ensure these 2 standard clauses are stated at
the Instructions to Supplier field - - (i) Please note that the University does not
accept - e-invoice
- (ii) Payment Terms Within 30 days upon receipt
of - invoice subject to successful
commissioning - Rationale
- Avoid payment dispute with suppliers.
21Critical Points- (continue)
- (4) Ensure Complete PO function is carried out
only when Goods Receipt has been done. - Rationale
- Once this function has been done, no further
action can be taken on this PO.
22Critical Points- (continue)
- (5) Ensure maximum of 15 assets per PO line item.
If more than 15 assets are to be purchased, split
the quantity in the Invitation to Quote (ITQ) to
different line item. - Rationale
- This is a system constraint of the financial
interface to SAP.
23Critical Points- (continue)
- (6) Ensure that account assignment (i.e. K for
cost centre buy, P for project buy and A for
asset buy) is being selected correctly. - Rationale
- Incorrect account assignment will lead to PO
failing financial interface.
24Critical Points- (continue)
- (7) Ensure that correct Goods Acceptance Officer
(GAO) is being assigned to perform GR. - Rationale
- Incorrect assignment of GAO will create
unnecessary administrative work.
25Critical Points- (continue)
- (8) Ensure Close PO function is used only when
a PO cannot be concluded naturally. - Rationale
- Close PO will lead to exception messages that
may not be resolved.
26Critical Points-(continue)
- (9) Ensure specified details for PO are in place
before seeking approval. - Rationale
- PO with incorrect details may have to be
cancelled. - Time is wasted
- Additional costs incurred for GeBIZ charges.
27Critical Points- (continue)
- (10) Ensure GeBIZ e-test is passed before
applying for GeBIZ user account. - Rationale
- Stipulated requirement for using GeBIZ.
28Critical Points- (continue)
- (11) Ensure there are no outstanding GeBIZ
charges when closing Research Account. - Rationale
- Payment of GeBIZ charges is delayed as user have
to suggest an alternate account chargeable.
29Critical Points- (continue)
- (12) Ensure for Research Accounts with pre-fix
M46 and M47, the G/L for GeBIZ charge is not
705000 (Equipment vote). - Rationale
- Per AStar instruction as these accounts are
sponsored by AStar.
30Critical Points- (continue)
- (13) Ensure when staff member having a GeBIZ
account has resigned/transferred, his outstanding
documents (GR/POs/ITQs etc) are being re-assigned
to another staff member - Rationale
- Proper handling over will avoid unnecessary delay
in processing outstanding work.
31Frequently Asked Questions
- How to apply/terminate Account?
- Download application form from Staff Forms and
Procedures folder and send duly endorsed form by
Approving Officer to FIN. -
32Frequently Asked Questions -(continue)
- How to reset Password?
- For SAP
For GeBIZ
Mr. Pang Ghee Keong gkpang_at_ntu.edu.sg 6316-8875
33Frequently Asked Questions -(continue)
- Where to get help on using the systems?
- For SAP
- Refer to SAP Purchasing System Manual and FAQs
that are available in FIN Homepage
(www.ntu.edu.sg/finance) and Staff Forms and
Procedures folder.
34Frequently Asked Questions -(continue)
- For GeBIZ
- Attend GeBIZ courses held at Civil Service
College (http//www.cscollege.gov.sg/). - Refer to various manuals that are available in
FIN Homepage (www.ntu.edu.sg/finance) and Staff
Forms and Procedures folder.
35Frequently Asked Questions -(continue)
- Refer to on-line user guides that are available
in GeBIZ intranet website (http//intranet.gebiz.g
ov.sg/). - Call GeBIZ Service Centre at 6274 5717 (Tel),
6274 1321 (Fax), gebiz_at_d-s-t-a.gov.sg (e-mail). - Contact FIN Purchasing Section at x5144 or x5790.
36Summary
- To recap, the following have been discussed -
- 1. What is GeBIZ Enterprise System?
- 2. Information on GeBIZ Charges
- 3. Critical Points
- 4. Frequently Asked Questions
- How to apply/terminate Account?
- How to reset password?
- How to use the systems?
37Procurement Process
38Overview of Purchasing Process
- Procurement Principles
- Prior To Purchase
- Purchasing Procedure
- Small Value Purchase
- Quotation
- Tender
- Cases to Share
39Procurement Principles
- The Purchasing Procedure Manual outlines the
University Procurement principles, policies and
procedures to be followed by all
Schools/Departments/Centres (Users). - The principles governing the University
Procurement are as follows- - Transparency
- Value for Money
- Open and Fair Competition
40Prior to Purchase
- Pre-Procurement Approval for any purchases must
be obtained from, Chairs of Schools, Heads of
Departments and Directors of Centres.
41Prior to Purchase (Continue)
- Additional Approving Authority for the following
4 categories-
42Purchasing Procedures
- All procurement shall be made through GeBIZ.
- Exceptions-
- Small Value Purchase.
- Sole Supplier that is not a GeBIZ Trading Partner
(GTP).
43Purchasing Procedures (Continue)
- Suppliers need to be registered as GeBIZ Trading
Partners to respond to our Invitation to Quote or
Tender. - For non-GTPs both local and overseas, it is
recommended to invite them to sign up as a GTP. - www.gebiz.gov.sg
- With effect from 1 April 2005 , all GeBIZ Trading
Partners (GTPs) will enjoy the use of one
Authorised Representative (AR) user account
free-of-charge.
44Purchasing Procedures (Continue)
45Purchasing Procedures (Continue)
46Purchasing Procedures (Continue)
- Users shall base on the Estimated Procurement
Value (EPV), exclusive of GST to select the
Procurement Procedure. - Small Value Purchase (EPV not exceeding 3,000).
- Quotation (EPV above 3,000 but not exceeding
70,000). - Tender (EPV exceeding 70,000).
47Purchasing Procedures (Continue)
- Request for Proposal (RFP)
- RFP can be applied in instances when-
- Tendering procedures do not result in responsive
bids - Not industry practice to tender out the items in
question - RFP should be conducted by Open Tender with-
- Clear requirement statement
- Fair and effective competition
48Purchasing Procedures (Continue)
- Procurement exempted from adherence to the
Purchasing Procedures- - A) Subscriptions for local or overseas journals,
- magazines and periodicals.
- B) Supply of water.
- C) Supply of piped gas.
- D) Supply of basic postal services.
- E) Supply of cable vision services.
- F) Services for diversion of the suppliers listed
in - (B) to (E) above, where term contractors have
- been appointed by the service providers.
49Small Value Purchase
- EPV not exceeding 3,000.
- Where price is known by-
- Previous Purchase.
- Posted prices by suppliers, media or other
sources eg. past purchases, flyers and internet. - Where price is unknown, minimum of 2 quotes are
required. - PO is required for asset purchase of unit price
2,000 and above.
50Quotation
- EPV above 3,000 and not exceeding 70,000.
- Open Quotation is the default mode of inviting
quotations. - Limited Quotation
- Only selected suppliers are invited to quote.
51Quotation (Continue)
- Conditions-
- Sole supplier and no alternative.
- Additional deliveries by original supplier (for
parts replacement, extension of existing
supplies, maintain service quality level).
52Quotation (Continue)
- Extreme urgency.
- Unforeseen and urgent events
- Prototypes or a first product or service.
- Public Interest to limit competition eg. printing
of degree scrolls, examination scripts.
53Quotation (Continue)
- Invitation to Quote should have the following
attributes- - Clear scope of the Intended Procurement.
- Closing date and time (must be on a working day).
- Reasonable time period for response (minimum 3
working days). - Approval from Quotation Approving Authority (QAA)
is required if quotation opening period is less
than 3 working days.
54Quotation (Continue)
- Quotation Reference Numbers shall be assigned.
- Recommendation
- Quotations received shall be evaluated and
recommended for award to QAA based on- - Most advantageous to the University
- Lowest priced of acceptable quality
- Meet requirements within required delivery period
55Quotation (Continue)
- QAA can approve the recommendation if Actual
Procurement Value (APV), does not exceed 80,000
exclusive of GST. - Quotations should be voided and fresh tender
invited for APV exceeding 80,000.
56Purchasing Procedures (Continue)
57Tender
- EPV above 70,000
- Types of Tender
- Open Tender
- Open to all GTPs
- Selective Tender
- Open to shortlisted GTPs only
- Normally used in complex procurement requiring
sophisticated and high level know-how,
capabilities and related experiences -
58Tender (Continue)
- Limited Tender
- Open to a few GTPs
- Open to a single GTP/supplier
- Before proceeding, ensure that the procurement
falls under one of the specified conditions
(please refer to Purchasing Procedures Manual
Section 16.1). Otherwise approval from
President, through FIN, needs to be sought
59Tender Process
- Step 1 decide on the template for the Invitation
to Tender (ITT)
60Tender Process (Continue)
- Step 2 prepare the ITT
- For expenditure tenders, unit price is submitted
electronically while other documents are
submitted in hardcopy into tender box at FIN. - Date of tender publication shall be on a Friday
(if this happens to be a Public Holiday, then it
shall be one day before, that is, Thursday) - Date of tender closing shall also be on a Friday
(if this happens to be a Public Holiday, then it
shall be on the following Monday), 4 pm - Exception For revenue tender, the entire
submission is - manual and will close on the following
Monday at 11 am
61Tender Process (Continue)
- date of tender opening shall be on a Monday (if
this happens to be a Public Holiday, then it
shall be on Tuesday), 11 am at FIN - Exception for limited tender to a single
GTP/supplier, tender opening is by respective
School/Department/Centre so time for tender
opening is decided by users but must be opened by
at least 2 persons of Division 1 status - minimum tender notice period is 2 weeks, if there
is site briefing/showround, tender notice period
must be at least 2 weeks from site
briefing/showround
62Tender Process (Continue)
- Step 3 Request for Invitation of Tenders Form
- Complete the Form
- Obtain endorsement from Chair of School/Head of
Department/Director of Centre - Obtain additional approval from Acting
Provost/CITS/FPM/CCO, where applicable -
63Tender Process (Continue)
- Step 4 Submission to FIN
- endorsed Request for Invitation of Tenders Form
and final ITT (2 sets) to be received by FIN at
least 1 week before the tender publication date - input Tender Notice in GeBIZ at least 1 week
before the tender publication date
64Tender Process (Continue)
- upload map of FIN at SS1-01-04 Guide On How To
Proceed to FIN at SS1-01-04 for reference by GTP
for all tender publication. - Exception For limited tender to a single
GTP/supplier, submission of hardcopy documents is
to School/Department/Centre - password protect or convert ITT into pdf format
to prevent unknown modification
65Tender Process (Continue)
- Step 5 Tender is published
- Make sure prospective supplier must be registered
as a GTP in order to participate in our tender -
- Exception-
- (1) tenderer who is participating in revenue
tender - whereby submission is fully manual
-
- (2) limited tender to a single supplier whereby
sole - supplier refuses to register as a GTP. If
so, - document relevant correspondences on this to
be - kept for record and submission will be fully
manual
66Tender Process (Continue)
- Step 6 Tender opening
- be punctual for tender opening at FIN SS1-01-04
as this is an established stipulation in
Purchasing Procedures Manual - for limited tender to a single supplier,
School/Department/Centre shall open the tender.
If bid is submitted electronically, users to
print the Tender Schedule from GeBIZ
67Tender Process (Continue)
- Tender Opening Committee shall endorse on all
pages of the Form of Tender and quotation
schedules - if tenderer submits electronic bid but did not
submit the required hardcopy documents, user to
check GeBIZ system on whether the submission was
via softcopy. Evaluation will be based on these
information
68Tender Process (Continue)
- Step 7 evaluate tender
- Check that Form of Tender (all pages) and
quotation schedules have been endorsed by all
Tender Opening Committee members. If any
signature is missing, contact FIN to arrange for
the necessary. - Check for any counter-proposals eg. payment
terms. If it is acceptable, then provide strong
justifications in Tender Evaluation Report. If
not acceptable, obtain written compliance. - Obtain written clarification from GTP/supplier if
there is discrepancy in pricing schedule. Where
a genuine computation error arises, indicate
details in the Tender Evaluation Report.
69Tender Process (Continue)
- Where a need to revise specifications after
tender was closed, users can invoke a two-stage
tender. - Operational processes-
- send a letter to FIN at least 1 week before the
proposed invitation date through Chair of
School/Head of Department/Director of Centre - To inform reason of the decision, shortlisted
tenderers and how shortlisting is done. - Attach original set of revised Tender Document
with the words Two-stage tender in the tender
description.
70Tender Process (Continue)
- Notes for 2-stage tender -
- (1) invitation date need not be a Friday
- (2) closing date is to be on a Monday, 11am.
- (3) reasonable tender notice period (at least 1
week) for - shortlisted tenderers to submit the
proposals - (4) there is no need to input GeBIZ Tender Notice
- (5) tender proposal shall be deposited into the
relevant - tender box
- (6) invitation letter and ITT can be sent through
email - on the same day, preferably under bcc
function for - confidentiality reason
71Tender Process (Continue)
- Step 8 Prepare Tender Executive Summary (TES)
and Tender Evaluation Report (TER) and submit to
FIN
72Tender
73Tender
74Tender Process (Continue)
- Important notes for TER-
- indicate whether price is fair and the basis for
this conclusion, eg. in comparison with past
procurement, prevailing market prices, etc - number of complete sets of TES and TER is based
on APV for award cases - number of complete sets of TES and TER is based
on EPV for no award cases - recommendation shall be in accordance with
specified Evaluation Criteria. If other
considerations are necessary, these should be
specified in the ITT in the first instance
75Tender Process (Continue)
- Step 9 User to create PO once approval is
granted by TAA - Create PO in SAP for one-off purchase
- Create PO in GeBIZ for period contracts
76Purchasing Procedures (Continue)
77Tender Process Milestone
78Tender Process Milestone (Continue)
79Summary
- Comply with purchasing procedures to be in line
with procurement principles - Transparency
- Value for money
- Open and fair competition
- Proper planning for efficiency in procurement
80Enquiries
- Further enquiries-
- Procurement Related Matters Finance
- Alvin Ext 5796 angbh_at_ntu.edu.sg
- Cindy Ext 4790 clcheong_at_ntu.edu.sg
- Yew Wah Ext 5056 ywlim_at_ntu.edu.sg
- Catherine Ext 5147 chchew_at_ntu.edu.sg
-
81Purchasing Briefing