Title: Derek Pfeifer


1
Drayton Bridge
  • Part 2
  • Derek Pfeifer

2
ITS JUST NOT DIRT ANYMORE
3
(No Transcript)
4
Earth Runs
  • Separated between Minnesota and North Dakota
  • ND 66 from the junction of ND 44 east to Red
    River
  • TH 11 from Red River east
  • CR 18 from TH 11 south

5
(No Transcript)
6
North Dakota
  • Abutment Embankment and Surcharge
  • Excavation Area Within R/W
  • Will be Backfilled With Existing Roadway Material

7
(No Transcript)
8
Minnesota
  • Abutment With No Surcharge
  • County Road 18
  • Ditches Provided Enough Material

9
(No Transcript)
10
PERMIT REQUIREMENTS
  • Storm Water Pollution Prevention Plan
  • Both use straw mulch, fiber Rolls, and other
    items to prevent erosion
  • MN permit issued by MN Pollution Control Agency
  • Minnesota required separate sheets in plans
  • Minnesota requires a certified individual to be
    on site
  • Minnesota also requires a permanent storm water
    pond with a stabilized outlet

11
Minnesota Storm Water Pond
  • Several requirements go into sizing the pond
  • 1. New Impervious based on one inch
  • 2. Runoff
  • 3. Must be a minimum depth of three feet

12
(No Transcript)
13
Pond Sizing and Location
  • Large amount of runoff being next to the river
  • Where to place the pond?
  • Minnesota Approval

14
(No Transcript)
15
CONSTRUCTION SEQUENCE
  • Developed to minimize traffic disturbance
  • Roadways must have paved surface during winter
    months
  • CR 18 will be allowed to be gravel for one winter
    season
  • Project is to be completed in three phases

16
PHASE ONE 2009
  • Relocate CR 18 in Minnesota
  • Install wick drains and build abutment
    embankment on both ends of bridge
  • Construct surcharge on ND abutment embankment
  • Install sheet pile and jersey barriers where
    needed
  • Start constructing Bridge

17
PHASE TWO - 2010
  • Remove Surcharge ND side
  • Remove and salvage surfacing
  • Finish Bridge
  • Suggest that most of the new surfacing be
    complete prior to bridge completion
  • Finish Surfacing and route traffic over new bridge

18
PHASE THREE 2010 -2011
  • Restore old roadbed to original contours
  • Remove old bridge
  • Finish all remaining work (seeding, etc.)

19
  • END
  • Part 2