COM369 Activity Planning Unit 2 - PowerPoint PPT Presentation

1 / 64
About This Presentation
Title:

COM369 Activity Planning Unit 2

Description:

Precedence analysis. Must be done before an activity plan can be produced ... Precedence networks must start with a start node and end with a end node ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 65
Provided by: osirisSun
Category:

less

Transcript and Presenter's Notes

Title: COM369 Activity Planning Unit 2


1
COM369 Activity PlanningUnit 2
2
Introduction 1
  • The unit will cover several methods
  • Precedence analysis
  • Gantt Charts
  • PERT / CPA
  • On Arrow Networks
  • Precedence Networks
  • Also ..
  • Microsoft Project will be covered in labs
  • This is based on Gantt Charts and Precedence
    Networks

3
Introduction 2
  • Activity Planning will help to
  • ensure that the appropriate resources will be
    available precisely when required
  • avoid different activities competing for the same
    resource at the same time
  • produce a detailed schedule showing which staff
    carry out each activity
  • Produce a detailed plan against which actual
    achievement may be measured
  • produce a timed forecast
  • re-plan the project during its life to correct
    drift from a target

4
Precedence analysis
  • Must be done before an activity plan can be
    produced
  • Reviews the activities that are to be carried out
  • Decides what activities must be carried out
    before particular activity can start

5
Gantt Charts
  • Developed by Henry Gantt, around 1917
  • Gantt charts are easy to use and produce
  • They are very useful for use on less complex
    projects
  • Commonly used due to there simplicity
  • Gantt charts are easily understood and easy to
    read

6
Gantt Charts
7
Gantt Charts
  • Draw the following Gantt chart
  • Tasks Precedence Time
  • a - 5 days
  • b - 4 days
  • c a 6 days
  • d b 2 days
  • e b 5 days
  • f c,d 8 days

8
Gantt Charts
9
Network planning models
  • PERT
  • The Program Evaluation and Review Technique
  • Developed by
  • US Navy with
  • BOOZ-Allen Hamilton and
  • Lockheed Corporation for the
  • Polaris missile/submarine project in 1958

10
Network planning models
  • CPM
  • Critical Path Method
  • Also know as CPA
  • Critical Path Analysis
  • Developed by
  • DuPont Inc in the
  • Late fifties early sixties to facilitate
  • building of complex process plant

11
Network planning models
  • PERT
  • developed for use on RD projects
  • CPM
  • developed for use in construction projects
  • When developed the two techniques were very
    similar
  • Now there is virtually no difference between the
    two

12
Network planning models
  • A simple on arrow network model

13
Terminology
  • Activity
  • A specific task, uses resources takes time to
    complete
  • Event
  • The result of completing an activity
  • Events use no resources
  • They are instances in time, points on the
    network, conditions of a system that can be
    recognised

14
Terminology
  • Network
  • The combination or all activities (often drawn as
    lines) and events (often drawn as nodes at the
    beginning and end of each line) defines the
    project and the activity precedence relationship.
  • Arrow heads placed on the lines indicate the
    direction of flow. Before and an event can be
    realised all the activities that immediately
    precede it must be completed

15
Terminology
  • Path
  • The series of connected activities (or
    intermediate events) between any two events in a
    network
  • Critical
  • Activities, events, or paths, which, if delayed,
    will delay the completion of the project
  • A projects critical path is understood to mean
    that sequence of critical activities (and
    critical events) that connect the projects start
    event to its finish event

16
Terminology
  • On Arrow Network diagram showing critical path in
    red

17
Network syntax
  • Time moves from left to right
  • Nodes are numbered sequentially
  • A network may not contain loops
  • A network may not contain dangles
  • Precedents are the immediate preceding activities
  • Dummy activities can be used to indicate a
    particular precedence

18
Network syntax
  • Time moves from left to right
  • Nodes are numbered sequentially

19
Network syntax
  • A network may not contain loops

20
Network syntax
  • A network may not contain dangles

21
Network syntax
  • Precedents are the immediate preceding activities

22
Network syntax
  • Dummy activities can be used to indicate a
    particular precedence

23
On Arrow Networks
  • Draw the following as an on arrow network
  • Tasks Precedence Time
  • a - 5 days
  • b - 4 days
  • c a 6 days
  • d b 2 days
  • e b 5 days
  • f c,d 8 days

24
On Arrow Networks
  • How to start ..

25
On Arrow Networks
  • What not to do

26
On Arrow Networks
  • A better way

27
On Arrow Networks
  • It is then less confusing that c d go to the
    same event but what about e f ?

28
On Arrow Networks
  • The completed on arrow network .

29
On Arrow Networks
  • Another on arrow network to draw
  • Tasks Precedence Time
  • a - 6 weeks
  • b - 4 weeks
  • c a 3 weeks
  • d b 4 weeks
  • e b 3 weeks
  • f - 10 weeks
  • g e,f 3 weeks
  • h c,d 2 weeks

30
On Arrow Networks
  • The network with activity times added

31
On Arrow Networks
  • Each event circle can contain the information
    below

32
Event numbers
33
Timed activities
34
Forward pass
35
Backward pass
36
Event, Slack and Activity Float
37
The Complete On Arrow Network
38
Precedence Networks
  • Precedence network also known as Activity on Node
  • Becoming more common as it is used by many
    project planning software packages
  • Often preferred by project managers

39
Precedence Networks
  • Syntax the same as for On Arrow networks
  • Except there are no dummy activities
  • Precedence networks must start with a start node
    and end with a end node

40
Precedence Networks
  • A simple precedence network

41
  • This is the same network drawn as an On Arrow
    network

42
Precedence Networks
  • A simple precedence network

43
Precedence Networks
  • Draw the following as an Precedence network
  • Tasks Precedence Time
  • a - 5 days
  • b - 4 days
  • c a 6 days
  • d b 2 days
  • e b 5 days
  • f c,d 8 days

44
Precedence Networks
  • The completed Precedence Network

45
  • The same network drawn as an On Arrow Network

46
Precedence Networks
  • The completed Precedence Network

47
Precedence Networks
  • Another on precedence network to draw
  • Tasks Precedence Time
  • a - 6 weeks
  • b - 4 weeks
  • c a 3 weeks
  • d b 4 weeks
  • e b 3 weeks
  • f - 10 weeks
  • g e,f 3 weeks
  • h c,d 2 weeks

48
Precedence Networks
  • The completed Precedence Network

49
  • This is the same network drawn as an On Arrow
    network

50
Precedence Networks
  • The completed Precedence Network

51
Precedence Networks
  • Adding more information to the node

52
Precedence Networks
  • ES latest (largest) EF of preceding activity
  • e.g. event may start at day zero - this actually
    means the end of day zero or the beginning of day
    one !!!
  • EF activity ES activity duration
  • LS activity LF activity duration
  • LF earliest (smallest) LS of subsequent
    activities.
  • Float LS ES or LF EF

53
Description
Description
Description
54
Description
Description
Description
55
Precedence Networks
  • Redraw the following with complete information in
    each node box
  • Tasks Precedence Time
  • a - 5 days
  • b - 4 days
  • c a 6 days
  • d b 2 days
  • e b 5 days
  • f c,d 8 days

56
Precedence Networks
  • Redraw the following with complete information in
    each node box
  • Tasks Precedence Time
  • a - 6 weeks
  • b - 4 weeks
  • c a 3 weeks
  • d b 4 weeks
  • e b 3 weeks
  • f - 10 weeks
  • g e,f 3 weeks
  • h c,d 2 weeks

57
Conclusion
  • Activity Planning
  • Precedence analysis
  • On Arrow networks
  • Precedence networks

58
Exercise 1
  • Tasks Precedence Time
  • a - 6 weeks
  • b - 4 weeks
  • c - 3 weeks
  • d a 4 weeks
  • e b 3 weeks
  • f b 2 weeks
  • g c 3 weeks
  • h d,e 2 weeks
  • i f 1 week
  • j g,i 2 weeks

59
Exercise 2
  • Tasks Precedence Time
  • a - 3 weeks
  • b - 5 weeks
  • c a 7 weeks
  • d b 5 weeks
  • e c, d 6 weeks
  • f b 4 weeks
  • g b 8 weeks
  • h c, d 4 weeks
  • i e, f 3 weeks

60
Exercise 3
  • Tasks Precedence Time
  • a - 2 weeks
  • b - 4 weeks
  • c - 3 weeks
  • d a 3 weeks
  • e a 5 weeks
  • f c 6 weeks
  • g c 4 weeks
  • h d 4 weeks
  • i d 8 week
  • j b, e, f, i 2 weeks
  • k - 4 weeks
  • l g, k 3 weeks

61
Exercise 4
  • Tasks Precedence Time
  • a - 3 weeks
  • b a 5 weeks
  • c a 3 weeks
  • d c 1 weeks
  • e b 3 weeks
  • f b, d 4 weeks
  • g c 2 weeks
  • h g, f 3 weeks
  • i e, h 1 weeks

62
Exercise 5
  • Tasks Precedence Time
  • a - 3 weeks
  • b - 5 weeks
  • c a 14 weeks
  • d a 5 weeks
  • e b 4 weeks
  • f b 7 weeks
  • g d, e 8 weeks
  • h g, f 5 weeks

63
Exercise 6
  • Tasks Precedence Time
  • a - 4 weeks
  • b - 2 weeks
  • c a 5 weeks
  • d b 3 weeks
  • e b 1 week
  • f c, d 7 weeks
  • g c, d, e 1 week
  • h c, d, e 3 weeks
  • i f, g 1 week

64
Exercise 7
  • Tasks Precedence Time
  • a - 3 weeks
  • b - 5 weeks
  • c a 4 weeks
  • d b 5 weeks
  • e b 4 weeks
  • f b, c 2 weeks
  • g d 3 weeks
  • h d, f 5 weeks
  • i e, g, h 3 weeks
  • J e 2 weeks
Write a Comment
User Comments (0)
About PowerShow.com