Title: MEASURE F PROJECT OVERVIEW
1MEASURE F PROJECT OVERVIEW
- Measure F Citizens Bond Oversight Committee
- November 8, 2004
22003 Project Summary
- The following projects are currently under
design - None
- The following projects are currently in the bid
phase - None
- The following projects are currently under
construction - None
- The following projects are currently in the
close-out phase - 9301 Bret Harte Middle Roofing
- 9303 Hammer Elementary Roofing
- 9304 Leland High Roofing
- 9306 Willow Glen Middle Roofing
- 9307 Willow Glen High School Roofing
- 9308 Empire Gardens Elementary New
Construction - 9309 Family Early Learning Center Measure F
Portion
3- Budget Summary
- 1. Total Budget - 2003 Projects
27,896,724 - 2.  Total Amount Currently Committed - 2003
Projects 25,091,148 - Budget Status (Over)/Under 2003 Projects (1-2)
2,805,576
42004 Project Summary
- The following projects are currently under
design - 9405 Central Kitchen
- 9421 Anne Darling Elementary
- 9423 Booksin New Classroom Facility
- (currently at DSA)
- 9425 Technology Upgrade
5- The following projects are currently on hold
- 9402 Erikson Williams Roofing
- 9422 Preschool Facilities
- 9424 Portable Replacement
- 9426 Hammer Modernization
- The following projects are currently in the bid
phase - None
6- The following projects are currently under
construction - 9410 Playgrounds
- 9413 Whiteboards
- 9417 Restroom Renovation I
- 9419 Restroom Renovation III
- 9420 Willow Glen High Restroom Building
- 9429 Synthetic Fields High Schools
- 9430 Community Day School
- 9431 Schallenberger Elementary New Classroom
Facility - 9432 Window Replacement at San Jose High
7- The following projects are currently in the
close-out phase - 9411 Underground Utilities I
- 9414 Stage Curtains
- 9415 Kitchen Renovations I
- 9416 Kitchen Renovations II
- 9418 Showers and Locker Rooms (Gunderson)
- 9427 Simonds Elementary Modernization
- 9428 Showers and Locker Rooms (Castillero and
Steinbeck) - 9433 Canoas Elementary Modernization
- 9434 Underground Utilities II
- 9490 Hoover Middle Specialized Instructional
Program
8- Budget Summary
- Â
- 1.    Total Budget - 2004 Projects 114,680,6
02 - 2.    Total Amount Currently Committed - 2004
Projects 113,985,726 - Budget Status (Over)/Under 2004 Projects
(1-2) 694,876
9Detailed Project InformationCentral Kitchen
- Project Number 9405
- Project Team
- Architect HMC
- Construction Manager Turner
- Scope Construction of a new kitchen facility at
the Districts Corp. Yard. The facility will
provide centralized food service holding and
preparation for distribution to satellite serving
kitchens at each school site. - S3.12 Kitchen and Food Services (District Wide)
- Total Budget 5,533,494
- This project is currently over budget and value
engineering is underway. - Schedule This project is currently at DSA
(Department of State Architects). Construction
is scheduled to begin in February 2005.
10(No Transcript)
11Underground Utilities I (Bachrodt, Reed Simonds
Elementary(s))
- Project Number 9411
- Project Team
- Design Pavement Engineering, Inc.
- Construction Manager PCM3
- Scope Upgrade and repair of existing
underground utilities and repair/upgrade of
ramps, sidewalks and parking lots as outlined in
the Measure F Implementation Plan. The following
scopes are included in this project - S2.2 Concrete Flatwork
- S2.8 Access Drive, Parking Lots, Bus Drop-Off
- S2.1 Underground Utility Lines
- Continued on next slide
12Underground Utilities I (Bachrodt, Reed Simonds
Elementary(s)) Continued
- Total Budget 865,017
- This project is currently being shown over
budget, however it is expected that this project
will be within budget at closeout. This
resulting from credit change orders and release
of contingency monies. - Schedule Construction was substantially
complete for the start of the 2004-2005 School
Year. Punchlist work is currently underway.
13(No Transcript)
14Kitchen Renovation I (Allen, Almaden and Carson
Elementary(s))
- Project Number 9415
- Project Team
- Architect HMC
- Construction Manager Blach
- Scope Renovation of the existing kitchen to
include speedline and upgrade finishes. The
following scopes are included in this project - S3.12 Kitchen and Food Service
- Total Budget 369,346
- This project is currently over budget. Budget
augmentation will be required on this project due
to additional scope required by the health
department. - Schedule Construction was substantially
complete for the start of the 2004-2005 School
Year. Punchlist work is currently nearing
completion.
15(No Transcript)
16Kitchen Renovation II (Bachrodt, Booksin Cory
Elementary(s))
- Project Number 9416
- Project Team
- Architect HMC
- Construction Manager Blach
- Scope Renovation of the existing kitchen to
include speedline and upgrade finishes. The
following scopes are included in this project - S3.12 Kitchen and Food Service
- Total Budget 382,026
- This project is currently over budget. Budget
augmentation will be required on this project due
to additional scope required by the health
department. - Schedule Construction was substantially
complete for the start of the 2004-2005 School
Year. Punchlist work is currently nearing
completion.
17(No Transcript)
18Restroom Renovation I (Bachrodt, Booksin,
Hacienda, Reed and Schallenberger Elementary(s))
- Project Number 9417
- Project Team
- Architect Aedis
- Construction Manager PCM3
- Scope Renovation of the existing restroom
facilities for ADA compliance and finish
upgrades. The following scopes are included in
this project - S3.5 Restrooms
- Total Budget 1,799,077
- This project is over budget. Value engineering
is being completed during construction, however
budget augmentation will be required at project
closeout. Cost overage was the result of
unfavorable bid climate.   - Continued on next slide
19Restroom Renovation I (Bachrodt, Booksin,
Hacienda, Reed and Schallenberger Elementary(s))
- Schedule This project has been approved by DSA,
however the delay in DSA approval impacted the
bid results. Due to the bid(s) received, the
project was re-bid utilizing a phased
construction schedule. Construction of Phase I
was substantially complete for the start of the
2004-2005 School Year. Phase II and Phase III
are nearing completion. Punchlist work is
scheduled to begin during the first week of
December.
20(No Transcript)
21Restroom Renovation III (Willow Glen Middle,
Lincoln and San Jose High(s))
- Project Number 9419
- Project Team
- Architect Aedis
- Construction Manager Kitchell
- Scope Renovation of the existing restroom
facilities for ADA compliance and finish
upgrades. The following scopes are included in
this project - S3.5 Restrooms
- Total Budget 1,234,145
- This project is currently over budget therefore,
budget augmentation may be required at closeout
if project contingencies are used. - Schedule This project has been approved by DSA,
however the delay in DSA approval impacted the
bid results of the Restroom Renovation III
Project therefore, the decision was made to put
this project on hold and re-bid it in October
2004. The project has been bid and is currently
underway.
22(No Transcript)
23Willow Glen High Restroom Building
- Project Number 9420
- Project Team
- Architect BFGC
- Construction Manager Kitchell
- Scope Addition of one each student restrooms for
boys and girls, one staff restroom and one
storage closet in building X. The following
scope is included in the project - S4.4 Add Restroom Building
- Total Budget 432,775
- This project is currently over budget. This
budget overage is due to under-budgeted soft
costs therefore budget augmentation may be
required at closeout if project contingencies are
used. - Schedule This project has been approved by
DSA, however the delay in DSA approval impacted
the bid results therefore, the decision was made
put this project on hold and re-bid it in October
2004. Building Abatement has been completed.
This project has been bid and is currently
underway.
24(No Transcript)
25Anne Darling Multi-Purpose and Administration
Building(s) - Site Review
- Project Number 9421
- Project Team
- Architect HMC
- Construction Manager PCM3
- Scope Renovation of the existing facilities, as
well as, construction of new buildings at the
Anne Darling Elementary site. This project
includes the following scopes - S2.2 Concrete Flatwork
- S2.6 Athletic Fields and Sport Court Safety
Issues - S2.7 Hardcourts
- S2.8 Access Drive, Parking Lots, Bus Drop-Offs
- S5.3 Building Upgrades
- S3.5 Restrooms
- S4.4 Add Restroom(s)
- S2.1 Underground Utility Lines
- Continued on next slideÂ
26Anne Darling Multi-Purpose and Administration
Building(s) - Continued
- S3.10 Roofing
- S3.11 Window Replacement
- S4.2 Portable Replacement with Portable
- S4.3 Portable Replacement with Permanent
- S4.5 Replace/Expand Multi-Purpose Room
- S5.1 Aesthetic Repairs
- S5.2 Building Protection
- S5.4 Mechanical Upgrades
- S5.5 Allowances (For multiple
- S1.2 Whiteboards
- S2.6.2 Athletic Fields and Sport Courts Program
Issues - S3.12 Kitchen and Food Service
- S3.4.1 Flooring and Interior Repainting
- S2.7.1 Hardcourts Paving Maintenance Program
- S3.14 Electrical, Lighting Upgrade
- S2.3 Front Landscaping
- S3.3 Casework in Permanent Buildings/Classrooms
- Continued on next slide
27Anne Darling Multi-Purpose and Administration
Building(s) - Continued
- Total Budget 14,885,649
- The above budget includes only Measure F monies.
Additional monies will be contributed to this
project from Scope D for new construction not
included in the original Implementation Plan. - Schedule This project is currently under
design. Anne Darling Elementary is open and
functioning in Interim Housing on the campus. A
supplementary report on this project was provided
to the CBOC on September 13, 2004. Abatement of
the Administration Building is complete. The
Demolition package has been bid and demolition is
scheduled to begin this month.
28(No Transcript)
29Synthetic Fields at High Schools (Gunderson,
Leland, Lincoln, Pioneer, San Jose and Willow
Glen High(s))
- Project Number 9429
- Project Team
- Landscape Architect Beals Alliance
- Construction Manager Kitchell
- Scope Installation of new synthetic turf fields
and track reconstruction miscellaneous paving and
fencing at all six high school sites. - Total Budget 22,333,252
- This project is under budget. Due to DSA
(Department of State Architect) ADA requirements,
stadium restrooms are being completed with budget
savings on this project. 750,000 will be
applied toward this scope. - Schedule Bids were received on this project on
March 24. The project bids received were below
the project estimate and budget. This project is
currently underway. The Pioneer, Lincoln and
Willow Glen fields are currently in use by the
sites. The first game at Leland is scheduled
for November 5. Gunderson and San Jose High are
currently underway.
30(No Transcript)
31Community Day School
- Project Number 9430
- Project Team
- Architect Bill Gould Design
- Construction Manager English Management
Consulting - Scope Construction of the new Community Day
School as necessitated by the Synthetic Field
Project at San Jose High. The new campus is
currently being sited behind the Family Early
Learning Center. - Total Budget 5,000,001
- Project is currently reflected over budget,
however it is anticipated that the project will
be completed within budget. No budget
augmentation is suggested. - Schedule Construction on this project is
currently underway and although scope is still
being completed, the facility opened as planned
for the start of the 2004-2005 School Year. It
is anticipated that this project will be complete
by December 31, 2004.
32(No Transcript)
33Canoas Modernization
- Project Number 9433
- Project Team
- Architect BFGC
- Construction Manager TBI
- Scope Modernization of Canoas Elementary School
included the following scopes - S5.3 Building Upgrades
- S3.5 Restrooms
- S3.11 Window Replacement
- S5.1 Aesthetic Repairs
- S5.4 Mechanical Upgrades
- S5.5 Allowances (For multiple
- S1.2 Whiteboards
- S1.3 Stage Curtains
- S3.12 Kitchen and Food Service
- S3.2 Counters and Sinks
- Continued on next slide
34Canoas Modernization, Continued
- S3.14 Electrical, Lighting Upgrade
- S3.4 Classroom Modernization
- S3.3 Casework in Permanent Buildings/Classrooms
- Total Budget 2,042,142
- This project is currently reflected over budget,
however there is scope that is currently being
charged against this budget that was completed on
an emergency basis, but is outlined in the IP as
scope included in project 9602 (Underground
Utilities). Therefore, an expense transfer will
take place from this project to project 9602.
This transfer will bring the project within
budget. - Schedule Construction of this project was
substantially complete for the start of the
2004-2005 School Year. Punchlist work is
currently underway and expected to be complete by
November 30, 2004.
35(No Transcript)
362005 Project Summary
- The following projects are currently under
design - 9501 Underground Utilities I
- Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
- 9502 Underground Utilities II
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9503 Underground Utilities III
- Design Contract Approved by BOE
- Construction Management Contract Pending Approval
37- 9504 Whiteboards (Middle High Schools)
- Design Contract Not Applicable
- Construction Management Contract Approved by BOE
- 9505 Stage Curtains
- Design Contract Not Applicable
- Construction Management Contract Not Applicable
- 9506 Kitchen Renovation I
- Design Contract Pending Approval
- Construction Management Contract Pending Approval
38- 9507 Restroom Renovation I
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9508 Restroom Renovation II
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9509 Restroom Renovation III
- Design Contract Pending Approval
- Construction Management Contract Pending Approval
39- 9510 Grant Elementary Multi-Use Building
Underground Utilities - Design Contract Pending Approval
- Construction Management Contract Pending
Approval - 9512 Booksin Elementary Modernization
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9514 Portable Replacement
- Design Contract Approved by BOE
- Construction Management Contract Pending Approval
40- 9515 Elementary School Athletics
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - Â
- 9516 Middle School Athletics
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9517 High School Athletics I
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval
41- 9518 Reed Modernization and New Restroom
Building - Design Contract Pending Approval
- Construction Management Contract Pending
Approval - 9519 Schallenberger Modernization
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9521 Pioneer Modernization
- Design Contract Approved by BOE
- Construction Management Contract Pending Approval
42- 9522 Restroom Buildings 2005
- Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
- 9523 New Classroom Facility - Lowell
- Design Contract Pending Approval
- Construction Management Contract Pending
Approval - 9524 New Classroom Facility Willow Glen
Elementary - Design Contract Approved by BOE
- Construction Management Contract Pending Approval
43- 9525 New Classroom Facility Gunderson
- Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
- 9527 Specialized Instructional Program Pioneer
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9530 Specialized Instructional Program
Gunderson - Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
44- 9531 Showers and Locker Rooms I
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9532 Showers and Locker Rooms II
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9535 High School Athletics II
- Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
45- 9536 Multi-Purpose Fire Project (Pioneer)
- Design Contract Approved by BOE
- Construction Management Contract Pending
Approval - 9537 Multi-Purpose Buildings I
- Design Contract Pending Approval
- Construction Management Contract Pending
Approval - Â
- 9540 Window Replacement at Willow Glen Middle
- Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
46- 9541 Window Replacement at Willow Glen High
- Design Contract Approved by BOE
- Construction Management Contract Approved by BOE
- Â
- 9542 Specialized Instructional Program New
Restroom -Lincoln - Design Contract Pending Approval
- Construction Management Contract Approved by BOE
- Â
- 9546 Downtown College Prep at Hester
- Design Contract Approved by BOE
- Construction Management Contract Pending Approval
47- The following projects are currently on hold
- 9513 Preschool Facilities
- Â
- The following projects are currently in the bid
phase - None
- The following projects are currently under
construction - None
- The following projects are currently in the
close-out phase - None
48- Budget Summary
- 1.    Total Budget - 2004 Projects 102,304,3
73 - 2.    Total Amount Currently Committed - 2004
Projects 101,812,129 - Budget Status (Over)/Under 2004 Projects
(1-2) 492,245