Title: MDT
1MDTs EXPEDITED PROJECTDELIVERY
PROGRAMPRESENTED BYMark Wissinger, P.E.Paul
Jagoda, P.E. Mac McArthur, P.E. MONTANA
DEPARTMENT OF TRANSPORTATION
Highways and Engineering Conference
February/March 2006
2INTRODUCTION
- OPENING REMARKS (Mark Wissinger MDT
- Construction Engineer)
- PRESENTATION (Mark Wissinger, Mac McArthur and
- Paul Jagoda MDT CES Bureau)
3AGENDA
- INTRODUCTION
- WHAT IS EXPEDITED PROJECT DELIVERY?
- WHY EXPEDITE?
- CONTRACTING METHODS TO EXPEDITE
- OTHER METHODS TO EXPEDITE
- EXAMPLE PROJECTS
- Design-Build Projects
- Emergency Projects
- Milk River Bridge
- Beartooth Highway
- Non-Emergency Projects
- QUESTIONS/ANSWERS
4WHAT IS EXPEDITEDPROJECT DELIVERY?(Mac McArthur)
- CONCURRENT PRELIMINARY
- ENGINEERING EFFORTS
- SHORTENED ADVERTISE/BID TIME
- LESS TIME FROM AWARD TO NTP
- REDUCED CONSTRUCTION PERIOD
5WHY EXPEDITE?
- PUBLIC SAFETY
- ROAD USER COSTS
- IMPACTS TO BUSINESS AND COMMERCE
- WEATHER CONSRAINTS
- UTILIZE FEDERAL FUNDS
- TIMELY RESOURCE AGENCY APPROVALS
- LESS ENVIRONMENTAL IMPACTS
- REDUCE MDT COSTS
- ENCOURAGES FOCUS ON QUALITY AND
- INNOVATION
- REDUCES OVERALL PROJECT COSTS
- REDUCES CLAIM RISK
-
6CONTRACTING METHODSTO EXPEDITE
- DESIGN-BUILD
- FORCE ACCOUNT (Hybrid Design-Build)
- EMERGENCY (Design/Bid/Build)
- EMERGENCY (Design/Purchasing/Build)
- USE OF INCENTIVE/DISINCENTIVE
- USE OF A B CONTRACT
7OTHER METHODS TO EXPEDITE
- CONCURRENT PE EFFORTS
- Early Resource Agency Consensus/Permit Approval
- Use Consultant Term Contracts
- Obtain R/W Based on Corridor Concept
- Early Utility Owner Involvement/Consensus
- Utilize Existing Data (As-Builts, Soils,
Geotech, Hydraulics) - Reduce Plan Review/Approval Time
- REDUCE ADVERTISE/BID TIME
- Group Office/Site Visits With Prospective
Contractors - Coordinate With MCA
- Reduce Time - Award To NTP (Contract, Bond,
Insurance) - Delegated Award Authority
-
8OTHER METHODS TO EXPEDITE(Continued)
- CONSTRUCTION
- Pre-Order Long Lead-Time Materials
- Clearly Define Substantial Completion
- Use CPM Scheduling
- Provide Adequate Resources (Labor and Equipment)
- Focus On Quality And Innovation
9EXAMPLE PROJECTS
- DESIGN-BUILD PROJECTS
- MCS Facility Wibaux
- Lincoln Road/I-15 Interchange Safety
Improvements -
- Dupuyer SE Reconstruction
-
10MCS Facility Wibaux
- Six Months From RFQ to NTP
- No Incentive/Disincentive
- Total Change Orders lt 20,000
- Contract Completion Date August 6, 2005
- Actual Substantial Completion September 2,
2005 -
11Lincoln Road/I-15 Interchange Safety Improvements
- Four Months From RFQ to NTP
- No Incentive/Disincentive
- Total Change Orders 13,000 (Does Not Include
Replacing Cattle Guards) - Contract Completion Date August 26, 2005
(Extended to September 8, 2005) - Substantially Completed September 8, 2005
12Dupuyer SE Reconstruction
- Eight Months From RFQ to NTP
- Incentive/Disincentive 4,008 Per Calendar Day
- MDT Completion Date September 1, 2006
- D-B Firms Completion Date July 31, 2006
- Normal LDs of 2,804 After 11/15/06
- Project Status?
13- 2004 2005 EMERGENCY REPAIR PROJECTS
- (Paul Jagoda)
- 7 PROJECTS
-
-
- Montana Street Overpass - Butte
- I-94 Culvert Replacement NE of Fallon
- Beartooth Highway Repairs Red Lodge
- Sula North and South Slide
- Bozeman Bridge Repairs
- Alberton Fire Damage Repairs
- Milk River Bridge (John Pavsek MMI and Jim
Walther - MDT) -
- Temporary Repair (Incentive/Disincentive
Contract) - Permanent Repair (A B Contract)
14Montana Street Overpass - Butte
- Incentive/Disincentive 3,987 Per Calendar Day
- Completed Project 21 Calendar Days Early
(83,727) - Challenges Guardrail Required Field Retrofit
- Successful Project - Incentive Was The Key
- (2 PHOTOS FOLLOW)
15(No Transcript)
16(No Transcript)
17I-94 Culvert Replacement NE of Fallon
- No Incentive/Disincentive
- 40 Calendar Days for Completion
- Completed in 48 Days
- (3 PHOTOS FOLLOW)
18(No Transcript)
19(No Transcript)
20(No Transcript)
21Beartooth Highway Repairs Red Lodge
- Incident May 17, 2005 RFP Issued June 3, 2005
- Hybrid Design-Build Process
- Qualification Based Selection Using RFP
- Force Account Using Proposed
- Labor/Equipment/Materials Markup Rates
- 12 Days From Issue RFP to NTP
- Contract Completion Date October 15, 2005
- Incentive
- 750,138 32,275 Per Day Before October 15,
2005 - 3,379 Per Day After 10/15/05, But Before
05/26/06 - Disincentive
- 32,275 Per Day After 05/26/06 To 10/15/06
- 3,379 Per Day After 10/15/06
- Substantially Completed October 1, 2005
22Sula North and South Slide
- No Incentive/Disincentive
- 30 Calendar Days To Complete
- Normal LDs of 1,171
- Challenges
- Traffic
- Access To Top of Cut
- Dangerous Slope
- Structure At bottom Of Slide
- (3 PHOTOS FOLLOW)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26Bozeman Bridge Repairs
- No Incentive/Disincentive
- 15 Calendar Days To Complete
- Normal LDs of 618.00
- Completed Project In 8 Calendar Days
- (2 PHOTOS FOLLOW)
27(No Transcript)
28(No Transcript)
29RETURN PRESENTATION TO MARK WISSINGER
30- NON-EMERGENCY PROJECTS
- (Mark Wissinger)
- Dillon NE and Montana Street (Incentive/Disincen
tive Contract) - Woodard Absarokee (Incentive/Disincentive
Contract) - 10th Avenue South (Incentive/Disincentive
Contract) - Drummond East and West (A B Contract)
- U.S. 93 Corridor North Projects (Most Are A B
Contracts) - Minesinger Trail MT 35
- Polson East (A B Contract)
- Ashley Creek Kalispell (A B Contract)
- Bozeman Bear Canyon (A B Contract)
31Dillon NE and Montana Street (Incentive/Disincenti
ve Contract)
- Completion Date August 1, 2004
- 45 Working Days For Remaining Work
- Incentive 5,500 Per Calendar Day, Max 20
Days - Disincentive 5,500 Per Calendar Day, No Max
- LD 2,624 After 45 Working Days
- Completed 10 Calendar Days Early (55,000)
- Challenges
- Utilities
- Unstable Soils
- Incentive Produced Quality Project Ahead of
Schedule -
32Woodard Absarokee(Incentive/Disincentive
Contract)
- 140 Working Days For entire Contract
- 120 Calendar Days To Complete Woodard Avenue
- Incentive 2,270 Per Calendar Day, Max 30
Days - Disincentive 2,270 Per Calendar Day, No Max
- Normal LDs For Working Days Portion
- Completed 30 Calendar Days Early (55,000)
- Challenges
- ADA Standards
- Incentive Produced Quality Project Ahead of
Schedule
3310th Avenue South(Incentive/Disincentive
Contract)
- Completion Date of October 8, 2004
- 30 Working Days To Complete Remaining Work
- Incentive 5,400 Per Calendar Day, Max 40
Days - Disincentive 5,400 Per Calendar Day, No Max
- Normal LDs For Working Days Portion
- Completed 35 Calendar Days Early (189,000)
- Incentive Produced Quality Project Ahead of
Schedule
34 Drummond East and West(A B Contract)
- Unit One Major Work Items
- Unit Two Remaining Work
- A B Bidding
- Part A Contract Amount
- Part B Calendar Days Bid - Unit One x 6,100
- Unit One Calendar Days Bid - Max 190 Days.
- Unit Two 90 Workings Days - Start After
Completion - of Unit One.
- Incentive/ Disincentive
- Incentive Unit One 6,100 Per Calendar Day
Max 60 Days - Disincentive Unit One 6,100 Per Calendar Day
No Max - Unit Two LDs on Part A of Contract Bid
- Completed 33 Calendar Days Early (201,300)
- Incentive Produced Quality Project Ahead of
Schedule
35U.S. 93 Corridor North Projects(Most Are A B
Contracts)
- Tribal Lands
- Heavy Traffic During Construction
- Utilities
- Potential Delays Could Impact Incentive/Disincent
ive
36 Minesinger Trail MT 35NH 5-2(124)56(I/D
Contract)
- Contract Time 220 Calendar Days
- Incentive 4,800 Per Calendar Day, Maximum
30 Days - Disincentive 4,800 Per Calendar Day, No
Maximum - Designated No Work Days.
- Relied on Impacts to Critical Path for Time
Extensions
37Polson East(A B Contract)
- Part A Contract Amount
- Part B Calendar Days Bid - Unit One x 9,450
- Calendar Days Bid - Maximum 315 days.
- Incentive/ Disincentive
-
- Incentive 9,450 Per Calendar Day Max 20
Days -
- Disincentive 9,450 Per Calendar Day Plus LD
Based on - Part A (Additional - 3,379)
- Project Completed 10/17/2005. Contractor
Received - Maximum Incentive 189,000.
-
38Ashley Creek Kalispell(A B Contract)
- Unit One Major Items of Work
- Unit Two Remaining Work
- Part A Contract Amount
- Part B Calendar Days Bid - Unit One x 10,000
- Unit One Calendar Days Bid Max 200 Calendar
- Days
- Unit Two 90 Workings Days - Start After Unit
One - Completed
- Incentive/Disincentive
- Unit One 10,000 Per Calendar Day Max 20 Days
- Unit Two LDs on Part A of Contract Bid
- One Calendar Day Incentive Unit One (10,000)
- Utility Relocation Started Early No Delay to
Project
39Bozeman Bear Canyon(A B Contract)
- Unit One All Valley Center Overpass Work
- Unit Two Replace MRL Structures and Associated
Work - Unit Three Remaining Work
- Part A Contract Amount
- Part B Calendar Days Bid on Unit One x 10,000
- Unit One Calendar Days Bid Max 225 Calendar
Days. - Unit Two Completion Date - November 1, 2006.
- Unit Three 30 Working Days
- Notice To Proceed - April 4, 2005
- Incentive/ Disincentive
- Unit One Incentive 10,000 Per Calendar Day
Max 30 Days - (Based on number of calendar days bid in
Part B) - Unit One Disincentive - 10,000 Per Calendar
No Max - Unit Two Disincentive - 1,375 Per Calendar Day
- Unit Three LDs Based on Part A of Contract Bid
Amount - 200 Calendar Days Bid for Unit One.
- Received 30 Calendar Days Incentive
(300,000)
40FUTURE PROJECTS
- Victor White Coyote Road South Ravalli (AB)
- South Ravalli Medicine Tree (AB)
- U.S. 2 Havre (I/D)
- West Billings King Avenue Bridges (I/D)
- West Laurel Interchange (I/D)
- South Helena Interchange (Lane Rental)
41