MDT - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

MDT

Description:

MDTs EXPEDITED PROJECT DELIVERY PROGRAM PRESENTED BY: Mark Wissinger, P'E' Paul Jagoda, P'E' Mac McA – PowerPoint PPT presentation

Number of Views:236
Avg rating:3.0/5.0
Slides: 42
Provided by: mdt2
Learn more at: https://www.mdt.mt.gov
Category:
Tags: mdt

less

Transcript and Presenter's Notes

Title: MDT


1
MDTs EXPEDITED PROJECTDELIVERY
PROGRAMPRESENTED BYMark Wissinger, P.E.Paul
Jagoda, P.E. Mac McArthur, P.E. MONTANA
DEPARTMENT OF TRANSPORTATION
Highways and Engineering Conference
February/March 2006
2
INTRODUCTION
  • OPENING REMARKS (Mark Wissinger MDT
  • Construction Engineer)
  • PRESENTATION (Mark Wissinger, Mac McArthur and
  • Paul Jagoda MDT CES Bureau)

3
AGENDA
  • INTRODUCTION
  • WHAT IS EXPEDITED PROJECT DELIVERY?
  • WHY EXPEDITE?
  • CONTRACTING METHODS TO EXPEDITE
  • OTHER METHODS TO EXPEDITE
  • EXAMPLE PROJECTS
  • Design-Build Projects
  • Emergency Projects
  • Milk River Bridge
  • Beartooth Highway
  • Non-Emergency Projects
  • QUESTIONS/ANSWERS

4
WHAT IS EXPEDITEDPROJECT DELIVERY?(Mac McArthur)
  • CONCURRENT PRELIMINARY
  • ENGINEERING EFFORTS
  • SHORTENED ADVERTISE/BID TIME
  • LESS TIME FROM AWARD TO NTP
  • REDUCED CONSTRUCTION PERIOD

5
WHY EXPEDITE?
  • PUBLIC SAFETY
  • ROAD USER COSTS
  • IMPACTS TO BUSINESS AND COMMERCE
  • WEATHER CONSRAINTS
  • UTILIZE FEDERAL FUNDS
  • TIMELY RESOURCE AGENCY APPROVALS
  • LESS ENVIRONMENTAL IMPACTS
  • REDUCE MDT COSTS
  • ENCOURAGES FOCUS ON QUALITY AND
  • INNOVATION
  • REDUCES OVERALL PROJECT COSTS
  • REDUCES CLAIM RISK

6
CONTRACTING METHODSTO EXPEDITE
  • DESIGN-BUILD
  • FORCE ACCOUNT (Hybrid Design-Build)
  • EMERGENCY (Design/Bid/Build)
  • EMERGENCY (Design/Purchasing/Build)
  • USE OF INCENTIVE/DISINCENTIVE
  • USE OF A B CONTRACT

7
OTHER METHODS TO EXPEDITE
  • CONCURRENT PE EFFORTS
  • Early Resource Agency Consensus/Permit Approval
  • Use Consultant Term Contracts
  • Obtain R/W Based on Corridor Concept
  • Early Utility Owner Involvement/Consensus
  • Utilize Existing Data (As-Builts, Soils,
    Geotech, Hydraulics)
  • Reduce Plan Review/Approval Time
  • REDUCE ADVERTISE/BID TIME
  • Group Office/Site Visits With Prospective
    Contractors
  • Coordinate With MCA
  • Reduce Time - Award To NTP (Contract, Bond,
    Insurance)
  • Delegated Award Authority

8
OTHER METHODS TO EXPEDITE(Continued)
  • CONSTRUCTION
  • Pre-Order Long Lead-Time Materials
  • Clearly Define Substantial Completion
  • Use CPM Scheduling
  • Provide Adequate Resources (Labor and Equipment)
  • Focus On Quality And Innovation

9
EXAMPLE PROJECTS
  • DESIGN-BUILD PROJECTS
  • MCS Facility Wibaux
  • Lincoln Road/I-15 Interchange Safety
    Improvements
  • Dupuyer SE Reconstruction

10
MCS Facility Wibaux
  • Six Months From RFQ to NTP
  • No Incentive/Disincentive
  • Total Change Orders lt 20,000
  • Contract Completion Date August 6, 2005
  • Actual Substantial Completion September 2,
    2005

11
Lincoln Road/I-15 Interchange Safety Improvements
  • Four Months From RFQ to NTP
  • No Incentive/Disincentive
  • Total Change Orders 13,000 (Does Not Include
    Replacing Cattle Guards)
  • Contract Completion Date August 26, 2005
    (Extended to September 8, 2005)
  • Substantially Completed September 8, 2005

12
Dupuyer SE Reconstruction
  • Eight Months From RFQ to NTP
  • Incentive/Disincentive 4,008 Per Calendar Day
  • MDT Completion Date September 1, 2006
  • D-B Firms Completion Date July 31, 2006
  • Normal LDs of 2,804 After 11/15/06
  • Project Status?

13
  • 2004 2005 EMERGENCY REPAIR PROJECTS
  • (Paul Jagoda)
  • 7 PROJECTS
  • Montana Street Overpass - Butte
  • I-94 Culvert Replacement NE of Fallon
  • Beartooth Highway Repairs Red Lodge
  • Sula North and South Slide
  • Bozeman Bridge Repairs
  • Alberton Fire Damage Repairs
  • Milk River Bridge (John Pavsek MMI and Jim
    Walther - MDT)
  • Temporary Repair (Incentive/Disincentive
    Contract)
  • Permanent Repair (A B Contract)

14
Montana Street Overpass - Butte
  • Incentive/Disincentive 3,987 Per Calendar Day
  • Completed Project 21 Calendar Days Early
    (83,727)
  • Challenges Guardrail Required Field Retrofit
  • Successful Project - Incentive Was The Key
  • (2 PHOTOS FOLLOW)

15
(No Transcript)
16
(No Transcript)
17
I-94 Culvert Replacement NE of Fallon
  • No Incentive/Disincentive
  • 40 Calendar Days for Completion
  • Completed in 48 Days
  • (3 PHOTOS FOLLOW)

18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
Beartooth Highway Repairs Red Lodge
  • Incident May 17, 2005 RFP Issued June 3, 2005
  • Hybrid Design-Build Process
  • Qualification Based Selection Using RFP
  • Force Account Using Proposed
  • Labor/Equipment/Materials Markup Rates
  • 12 Days From Issue RFP to NTP
  • Contract Completion Date October 15, 2005
  • Incentive
  • 750,138 32,275 Per Day Before October 15,
    2005
  • 3,379 Per Day After 10/15/05, But Before
    05/26/06
  • Disincentive
  • 32,275 Per Day After 05/26/06 To 10/15/06
  • 3,379 Per Day After 10/15/06
  • Substantially Completed October 1, 2005

22
Sula North and South Slide
  • No Incentive/Disincentive
  • 30 Calendar Days To Complete
  • Normal LDs of 1,171
  • Challenges
  • Traffic
  • Access To Top of Cut
  • Dangerous Slope
  • Structure At bottom Of Slide
  • (3 PHOTOS FOLLOW)

23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
Bozeman Bridge Repairs
  • No Incentive/Disincentive
  • 15 Calendar Days To Complete
  • Normal LDs of 618.00
  • Completed Project In 8 Calendar Days
  • (2 PHOTOS FOLLOW)

27
(No Transcript)
28
(No Transcript)
29
RETURN PRESENTATION TO MARK WISSINGER
30
  • NON-EMERGENCY PROJECTS
  • (Mark Wissinger)
  • Dillon NE and Montana Street (Incentive/Disincen
    tive Contract)
  • Woodard Absarokee (Incentive/Disincentive
    Contract)
  • 10th Avenue South (Incentive/Disincentive
    Contract)
  • Drummond East and West (A B Contract)
  • U.S. 93 Corridor North Projects (Most Are A B
    Contracts)
  • Minesinger Trail MT 35
  • Polson East (A B Contract)
  • Ashley Creek Kalispell (A B Contract)
  • Bozeman Bear Canyon (A B Contract)

31
Dillon NE and Montana Street (Incentive/Disincenti
ve Contract)
  • Completion Date August 1, 2004
  • 45 Working Days For Remaining Work
  • Incentive 5,500 Per Calendar Day, Max 20
    Days
  • Disincentive 5,500 Per Calendar Day, No Max
  • LD 2,624 After 45 Working Days
  • Completed 10 Calendar Days Early (55,000)
  • Challenges
  • Utilities
  • Unstable Soils
  • Incentive Produced Quality Project Ahead of
    Schedule

32
Woodard Absarokee(Incentive/Disincentive
Contract)
  • 140 Working Days For entire Contract
  • 120 Calendar Days To Complete Woodard Avenue
  • Incentive 2,270 Per Calendar Day, Max 30
    Days
  • Disincentive 2,270 Per Calendar Day, No Max
  • Normal LDs For Working Days Portion
  • Completed 30 Calendar Days Early (55,000)
  • Challenges
  • ADA Standards
  • Incentive Produced Quality Project Ahead of
    Schedule

33
10th Avenue South(Incentive/Disincentive
Contract)
  • Completion Date of October 8, 2004
  • 30 Working Days To Complete Remaining Work
  • Incentive 5,400 Per Calendar Day, Max 40
    Days
  • Disincentive 5,400 Per Calendar Day, No Max
  • Normal LDs For Working Days Portion
  • Completed 35 Calendar Days Early (189,000)
  • Incentive Produced Quality Project Ahead of
    Schedule

34
Drummond East and West(A B Contract)
  • Unit One Major Work Items
  • Unit Two Remaining Work
  • A B Bidding
  • Part A Contract Amount
  • Part B Calendar Days Bid - Unit One x 6,100
  • Unit One Calendar Days Bid - Max 190 Days.
  • Unit Two 90 Workings Days - Start After
    Completion
  • of Unit One.
  • Incentive/ Disincentive
  • Incentive Unit One 6,100 Per Calendar Day
    Max 60 Days
  • Disincentive Unit One 6,100 Per Calendar Day
    No Max
  • Unit Two LDs on Part A of Contract Bid
  • Completed 33 Calendar Days Early (201,300)
  • Incentive Produced Quality Project Ahead of
    Schedule

35
U.S. 93 Corridor North Projects(Most Are A B
Contracts)
  • Tribal Lands
  • Heavy Traffic During Construction
  • Utilities
  • Potential Delays Could Impact Incentive/Disincent
    ive

36
Minesinger Trail MT 35NH 5-2(124)56(I/D
Contract)
  • Contract Time 220 Calendar Days
  • Incentive 4,800 Per Calendar Day, Maximum
    30 Days
  • Disincentive 4,800 Per Calendar Day, No
    Maximum
  • Designated No Work Days.
  • Relied on Impacts to Critical Path for Time
    Extensions

37
Polson East(A B Contract)
  • Part A Contract Amount
  • Part B Calendar Days Bid - Unit One x 9,450
  • Calendar Days Bid - Maximum 315 days.
  • Incentive/ Disincentive
  • Incentive 9,450 Per Calendar Day Max 20
    Days
  • Disincentive 9,450 Per Calendar Day Plus LD
    Based on
  • Part A (Additional - 3,379)
  • Project Completed 10/17/2005. Contractor
    Received
  • Maximum Incentive 189,000. 

38
Ashley Creek Kalispell(A B Contract)
  • Unit One Major Items of Work
  • Unit Two Remaining Work
  • Part A Contract Amount
  • Part B Calendar Days Bid - Unit One x 10,000
  • Unit One Calendar Days Bid Max 200 Calendar
  • Days
  • Unit Two 90 Workings Days - Start After Unit
    One
  • Completed
  • Incentive/Disincentive
  • Unit One 10,000 Per Calendar Day Max 20 Days
  • Unit Two LDs on Part A of Contract Bid
  • One Calendar Day Incentive Unit One (10,000)
  • Utility Relocation Started Early No Delay to
    Project

39
Bozeman Bear Canyon(A B Contract)
  • Unit One All Valley Center Overpass Work 
  • Unit Two Replace MRL Structures and Associated
    Work
  • Unit Three Remaining Work 
  • Part A Contract Amount
  • Part B Calendar Days Bid on Unit One x 10,000
  • Unit One Calendar Days Bid Max 225 Calendar
    Days.
  • Unit Two Completion Date - November 1, 2006.
  • Unit Three 30 Working Days
  • Notice To Proceed - April 4, 2005 
  • Incentive/ Disincentive
  • Unit One Incentive 10,000 Per Calendar Day
    Max 30 Days
  • (Based on number of calendar days bid in
    Part B)
  • Unit One Disincentive - 10,000 Per Calendar
    No Max
  • Unit Two Disincentive - 1,375 Per Calendar Day
  • Unit Three LDs Based on Part A of Contract Bid
    Amount  
  • 200 Calendar Days Bid for Unit One.
  • Received 30 Calendar Days Incentive
    (300,000) 

40
FUTURE PROJECTS
  • Victor White Coyote Road South Ravalli (AB)
  • South Ravalli Medicine Tree (AB)
  • U.S. 2 Havre (I/D)
  • West Billings King Avenue Bridges (I/D)
  • West Laurel Interchange (I/D)
  • South Helena Interchange (Lane Rental)

41
  • QUESTIONS/ANSWERS
Write a Comment
User Comments (0)
About PowerShow.com