Title: Overview of GAOs Implementation of Earned Value Management
1Overview of GAOs Implementation of Earned Value
Management
- Karen Richey
- Jennifer Echard
- GAO Cost Analysts
- Applied Research Methods Team
- April 28, 2005
2Table of Contents
- Using EVM as an Audit Tool at GAO
- Summary of GAO Report Findings using EVM analysis
- FAA STARS (GAO-03-343)
- Missile Defense (GAO-04-409)
- Airborne Laser (GAO-04-643R)
- NASA Cost Estimating Process (GAO-04-642)
- Polar-Orbiting Environment Satellite
(GAO-04-1054) - Navy Shipbuilding (GAO-05-183)
- Next steps for GAO and EVM
3Using EVM as an Audit Tool
- GAO began using EVM analysis in 2002 for selected
audits - Since that time GAO has issued 6 reports using
EVM analysis as a basis for findings - Programs are far ranging covering major Automated
Information Systems, Shipbuilding, Missile
Defense and NASA - Results vary among programs--Examples include
- Realism of the Performance Measurement Baseline
(PMB) - Integrated Baseline Reviews (IBRs) data
validation - Number of rebaselines
- Optimistic Estimates at Completion (EACs)
- Frequency of reporting
4Summary of GAO Report Findings using EVM
analysis FAA STARS (GAO-03-343)
- Background On November 17, 2002, FAA began using
the Standard Terminal Automation Replacement
System (STARS) to control air traffic at the
Philadelphia air route traffic control center. - STARS is a joint procurement with DOD, which is
purchasing up to 199 units for its facilities. - STARS will replace controller workstations with
new color displays, processors, and computer
software at FAA and DOD terminal air traffic
control facilities. - STARS provides an automation platform that will
enable efforts to optimally configure the
terminal airspace around the country, exchange
digital information between pilots and
controllers, as well as introduce new position
and surveillance capabilities for pilots.
5FAA STARS (GAO-03-343) Website
www.gao.gov/new.items/d03343.pdf
- FAA was not using CPR data to manage its contract
because the data did not reflect current effort
and had not been validated by an IBR after
changes - Major modifications changed the Performance
Measurement Baseline (PMB) curve - PMB never updated when STARS implementations fell
from 188 to only 74 systems - PMB did not reflect 179M of new work authorized
since contract award -
-
6FAA STARS (GAO-03-343)
- Conclusions FAA was unable to effectively
manage the contract - CPR showed program to be on schedule and within 1
percent of budgeted costs - In reality, FAA was contracting to modernize
fewer than half the systems at more than twice
the original cost - Recommendations GAO recommended that FAA
- Maintain current baselines,
- Negotiate all authorized work within 3 months,
and - Conduct IBRs after any major contract
modifications within 6 months - Result FAA concurred with recommendations.
7Summary of GAO Report Findings using EVM
analysis Missile Defense (GAO-04-409)
- Background GAO has an annual congressional
mandate to assess the extent to which MDA
achieves program goals. - In 2002 two key events transformed DODs approach
to missile defense - The Secretary of Defense consolidated existing
missile defense elements into a single
acquisition program and placed them under the
management of the Missile Defense Agency (MDA) - The President directed MDA to begin fielding an
initial configuration, or block, of missile
defense capabilities in 2004.
1 Airborne Laser 2 Ground Based
Midcourse Defense
8Missile Defense (GAO-04-409) (cont) Website
www.gao.gov/new.items/d04409.pdf
- Prime contractors for 4 system elements completed
work at or near budgeted costs, but contractors
for two system elements overran budgeted costs by
a total of 380 million during fiscal year 2003 - ABL1 underestimated the complexity of integrating
subcomponents into a flight-worthy
configuration causing major cost overruns - Initial PMB was highly optimistic given the
cutting edge technology - Unrealistic schedule contributed to both cost and
schedule problems - Developmental and delivery problems with the GMD2
interceptor were the leading contributors to cost
overruns and schedule slips - CPRs for Aegis system reflected only the
interceptor portion and not the entire Aegis
element - MDA had no insight regarding the Aegis
interceptor divert system which was experiencing
development problems at the time
1 Airborne Laser 2 Ground Based
Midcourse Defense
9Missile Defense (GAO-04-409) (cont)
- Conclusions GAO found that MDAs program goals
do not serve as a reliable and complete baseline
for accountability purposes and investment
decision making because - they can vary year to year,
- do not include life cycle costs,
- are based on assumptions about performance not
explicitly stated, - does not explain some critical assumptions such
as an enemys type and number of
decoysunderlying its performance goals - As a result, decision makers in DOD and Congress
do not have a full understanding of the overall
cost of developing and fielding the Ballistic
Missile Defense System and what the systems true
capabilities will be.
1 Airborne Laser 2 Ground Based
Midcourse Defense
10Missile Defense (GAO-04-409) (cont)
- Recommendations GAO recommended that MDA
- Establish cost, schedule, and performance
measurement baselines (including full life cycle
costs) for each system being fielded - Result DoD concurred with baseline
recommendations.
1 Airborne Laser 2 Ground Based
Midcourse Defense
11Summary of GAO Report Findings using EVM
analysis Airborne Laser (GAO-04-643R)
- Background From 1996 to 2001, the ABL program
was an Air Force major defense acquisition
program. - In October 2001, the DOD transferred
responsibility for the program to the Ballistic
Missile Defense Organization (now MDA) where ABL
became one element of the Ballistic Missile
Defense System (BMDS). - ABL's mission is to destroy enemy ballistic
missiles in the boost phase as part of the
layered defense strategy. - ABL is being developed incrementally in a series
of 2-year blocks.
1 Airborne Laser
12Airborne Laser (GAO-04-643R) (cont) Website
www.gao.gov/new.items/d04643.pdf
- Prime contractors cost for developing ABL1 had
nearly doubled from Air Force original estimate
and additional cost growth expected - Costs increased from 1B in 1996 to 2B in 2003
- Unrealistic PMB at contract award prompted
numerous rebaselines - GAO forecasted an overrun between 431M - 943M
for first ABL demo - Cumulative Cost Variance at that time was -242M
with a schedule variance of -28M - Contractor reported no variance at completion
- The cost growth occurred because the program did
not adequately anticipate the complexities
involved in developing the system. - MDA continues to face significant challenges in
developing the ABL's revolutionary technologies
and in achieving cost and schedule stability.
1 Airborne Laser
13ABL Cost and Schedule Variance in FY 2003 ( in
Millions)
14ABL Actual Performance Vs. Projected Performance
15Airborne Laser (GAO-04-643R) (cont)
- Conclusions Program did not adequately plan for
or anticipate complexities involved in developing
ABLs revolutionary technologies - Rapid prototyping forced program to integrate
components before they were fully tested causing
unexpected rework - Fabrication of ABLs unique components and
developing its complex software proved more
costly and time consuming than anticipated - Bow wave of uncompleted work from prior years
competed for current resources despite an
increase in staff and additional work shifts - Recommendations GAO recommended that MDA
- complete an uncertainty analysis on the
contractors new cost estimate to quantify level
of confidence - Result DOD concurred.
1 Airborne Laser
16Summary of GAO Report Findings using EVM
analysis NASA Cost Estimating Process
(GAO-04-642)
- Background NASA's programs encompass a broad
range of complex and technical activities--from
investigating the composition and resources of
Mars to providing satellite and aircraft
observations of Earth for scientific and weather
forecasting. - Our review focused on 27 of 68 NASA programs in
the development phase as of April 2003 or that
completed development in fiscal year 2001 or
2002. - To assess NASA's cost-estimating processes and
methodologies, we conducted a more in-depth
review of 10 of the 27 programs - We chose programs using the following critieria
- The highest development cost estimate within five
of NASA's seven Enterprises.
17NASA Cost Estimating Process (GAO-04-642) (cont)
Website www.gao.gov/new.items/d04642.pdf
- We compared cost estimating documentation from 10
programs against SEI cost estimate criteria to
determine whether NASA followed good cost
estimating practices. - We found that NASA cost estimates for 8 out of
the 10 programs we reviewed in detail increased
over time - NASA attributed cost growth to technical problems
and funding shortages - Variability in cost estimates indicated that
programs lacked sufficient knowledge needed to - Establish priorities,
- Quantify risks,
- Make informed decisions, and
- Thus predict costs
18NASA Cost Estimating Process (GAO-04-642)
(cont)Overview of 10 Selected Programs
19NASA Cost Estimating Process (GAO-04-642) (cont)
- Conclusion NASAs basic cost estimating
processes lacked discipline needed to ensure that
program estimates are reasonable - None of the 10 programs GAO reviewed met all of
GAOs cost estimating criteria - Only 3 of the 10 programs provided a breakdown of
the work to be performed - Only 2 programs used EVM for measuring cost and
performance to identify risks - The other 8 programs compared planned versus
actual obligations and expenditures - NASA had no data to determine ahead of time
whether these 8 programs were at risk of cost and
schedule overruns - Recommendations GAO recommended that NASA
- develop rebaselining guidance to ensure
consistency among programs, - implement EVM as a tool for bringing cost to the
forefront, - and ensure EVM policies are enforced
- Result NASA concurred.
20Summary of GAO Report Findings using EVM
analysis Polar-Orbiting Environment Satellite
(GAO-04-1054)
- Background The United States operates
polar-orbiting meteorological satellite systems
to - Provide graphical weather images and specialized
weather products that are inputs into weather
prediction. - These images, products, and models are all used
by weather forecasters, the military, and the
public for both weather forecasting and climate
monitoring. - NPOESS1 is being developed to combine two current
satellite systems into a single state-of-the-art
environment monitoring satellite system. - NPOESS is a tri-agency endeavor involving DOD,
NASA, and the National Organic and Atmospheric
Administration
1 National Polar-Orbiting Environmental
Satellites
21Polar-Orbiting Environment Satellite
(GAO-04-1054) (cont) Website www.gao.gov/new.ite
ms/d041054.pdf
- Recently the NPOESS program office developed a
new cost and schedule baseline. - Congress asked us to identify any cost or
schedule changes as a result of the revised
baseline and determine what factors contributed
to these changes. - We found that the program office increased
NPOESS1 cost estimate by 1.2B and delayed the
availability of the first NPOESS satellite by 20
months. - Funding cuts stretched out NPOESS program causing
an increase in cost - Other cost increases were due to problems with
sensor development and additional program office
costs to mitigate risks after program rebaseline. - Lack of schedule slack increased risk for
managing development issues.
1 National Polar-Orbiting Environmental
Satellites
22Polar-Orbiting Environment Satellite
(GAO-04-1054) (cont)
- Conclusion NPOESS could experience further cost
and schedule increases - Contractors continued schedule slippage in both
cost and schedule targets indicated the NPOESS
contract would likely overrun by 500M - Program risks with developing critical sensors
could also add costs - Since contract rebaseline, cost overruns have
more than doubled and the schedule was slipping
again - We estimated an overrun between 372M and 891M
at completion compared to the contractor which
estimated an overrun of only 130M - Cumulative cost variance at that time was 55M at
only 20 percent complete - Recommendations We concluded that continued
oversight is more critical than ever.
Accordingly, GAO plans to continue the review of
this program. - Result DOD, NASA, and NOAA officials generally
agreed with the report
1 National Polar-Orbiting Environmental
Satellites
23Summary of GAO Report Findings using EVM
analysis Navy Shipbuilding (GAO-05-183)
- Background The U.S. Navy invests billions of
dollars each year to maintain technological
superiority of its warships. - Our study reviewed the top four ship classes
involved in new ship construction to determine
the reasons behind significant cost overruns.
24Navy Shipbuilding (GAO-05-183) (cont)website
www.gao.gov/new.items/d05183.pdf
- For the 8 ships assessed (2 ships in 4 classes),
we found that Congress had appropriated 2.1
billion in additional funding to cover in cost
increases through 2004 - GAO EVM analysis indicated cost increases of
3.1B or more for all 8 ships could be expected - Cost increases for CVN 77 and LPD 17 were the
most pronounced - Virginia Class submarine was expected to also
require additional costs - Increases in labor hour and material costs
together account for 77 percent of the cost
growth on the eight ships. Shipbuilders cited the
following as key causes - Design modifications
- Additional and more costly materials
- Changes in employee pay and benefits
25Navy Shipbuilding (GAO-05-183) (cont)
- Conclusion Navy practices for estimating costs,
contracting, and budgeting for ships resulted in
unrealistic funding of programs - PMB costs for CVN, SSN, and LPD 17 were all
unrealistic increasing the likelihood of
increased costs - Navy does not account for probability of cost
growth when estimating costs - No uncertainty analysis
- No management reserve
- 3 out of 4 ship classes received CPRs on a
quarterly basis - LPD 17 switched to monthly CPRs after
unprecedented cost growth - CVN 77 is switching to monthly CPRs within the
year - SSN 774 class is staying with quarterly CPRs
despite expected cost growth - Recommendation GAO recommended the Navy
- perform uncertainty analysis,
- establish realistic budgets for measuring
performance, - and include more timely and complete reporting on
program costs. - Results Navy partially concurred.
26Next steps for GAO and EVM
- Select members of GAO have been extensively
trained to use EVM for audits - These members delivered in-house training to
various GAO teams to get the word out about the
benefits of using EVM - Ability to quantify historical cost and schedule
performance - Provide a means for forecasting future costs and
schedules - Identify areas of poor performance and technical
concern - Ability to forecast potential problem areas and
report to Congress - GAO has ordered Winsight software and will be
trained in the next few months - Next area of focus includes scheduling techniques
and tools, with an emphasis on the critical path
method