A'Gianolio LISA status 1 - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

A'Gianolio LISA status 1

Description:

Jan 20, 2005 LISA France. A.Gianolio LISA status - 2. LISA ... JPL will be responsible to deliver the LISA Instrument Metrology and Avionics System (LIMAS) ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 38
Provided by: csargarcam
Category:

less

Transcript and Presenter's Notes

Title: A'Gianolio LISA status 1


1
LISA Status LISA France College de
France January 20-21, 2005 A. Gianolio LISA
Project Manager
2
  • Following a year of discussion, a programmatic
    agreement for the LISA project has been reached
    between ESA and NASA in August 2004
  • WHY WAS SUCH AN AGREEMENT NECESSARY ?
  • The interface between experiment and spacecraft
    in LISA is such that the experiment drives the
    mission design.
  • System Engineering needs to extend deep into the
    definition of the mission elements.
  • The mission reference architecture has to be
    defined during Mission Formulation in order to
    finalize the share of responsibility.
  • Consequently, all major system engineering
    decisions have to be agreed by both ESA and NASA.
  • The way this is implemented requires to be
    formalized within an inter-agency agreement.

3
Decisions
  • ESA considers it essential that during the whole
    mission and in particular during mission
    formulation
  • no decision affecting overall mission performance
  • no decision affecting technical design, early
    technological investment, cost and schedule of
    the other partner
  • can be taken by one partner without explicit and
    well informed consensus by the other partner.

4
Organization principles
  • Single project with parallel organizational
    structures in each agency.
  • Each agency is responsible for discharging its
    obligations.
  • Each agencys project team responds to his own
    management.
  • A high degree of interaction is required of the
    two agencies.

5
Mission phases
  • Two mission phases can be identified
  • FORMULATION
  • Definition of mission and system requirements
    and of mission architecture
  • IMPLEMENTATION
  • Procurement of deliverables that fulfil the
    above requirements
  • Additionally ESA will introduce the
  • DEFINITION
  • Industrial competitive phase to perform the
    preliminary design of the ESA deliverables and
    select the prime contractor for Implementation

6
ESA-NASA Agreement
  • The main elements of the agreement are
  • Project description
  • Project organisation
  • System Engineering functions
  • Mission elements share
  • The Project description defines the general terms
    to be adopted throughout the project

7
Definitions
  • LISA Scientific Complement it includes the LISA
    Optomechanical Core Systems (LOCS), the LISA
    Instrument Metrology and Avionics System (LIMAS),
    the associated control software, microthrusters
    (TBC)
  • Sciencecraft one spacecraft bus with its LISA
    Scientific Complement
  • Constellation the three LISA sciencecraft
    operating together.
  • Joint Project Managers Office (JPMO) LISA
    project management office composed of the ESA and
    the NASA project managers and their management
    support, chaired jointly by the ESA and the NASA
    project managers.

8
Definitions
  • Mission System Engineering (MSE) system
    engineering team co-chaired by the ESA, the GSFC
    and the JPL Mission System Engineering Managers,
    who have equal authority and report to the JPMO.
    MSE merges the system engineering teams of ESA,
    GSFC and JPL.
  • Mission System Engineering Advisory Team (MSEAT)
    small advisory body to the Mission System
    Engineering.
  • Integrated Technical Advisory Teams (ITAT)
    technical teams commissioned ad hoc by MSE to
    provide inputs in specific areas.

9
MF Project Organisation
The ESA and the NASA project managers share equal
responsibility in the management of the project
The JPMO, led by the ESA and the NASA project
managers, is in charge of the overall project
The JPMO has to approve, inter alia, the mission
reference design and the requirements
The project will adopt, as far as possible, a
single set of procedures, documentation and
reviews
10
Programmatic
  • The description of the System Engineering
    functions constitutes a fundamental step forward
    in the cooperation
  • it identifies the functions in Formulation and in
    Implementation
  • it sanctions the principle that the mission
    design has to be done jointly, to the level
    required to clearly define the responsibility of
    each agency
  • It establishes that decisions affecting the
    project cannot be taken unilaterally by one
    Agency
  • The implementing structure foresees three SE
    managers working together to define mission
    requirements and reference architecture, to be
    submitted to the approval of the two project
    managers

11
ITATs
  • ITATs are created by the SE Mgrs upon need and
    they can be dissolved once the task is completed.
  • Their charter is defined by the SE Mgrs
  • The ITATs composition is defined by the SE Mgrs
    and can be modified during the existence of the
    ITAT.
  • Each ITAT has have a chair appointed by the SE
    Mgrs
  • The ITATs can call upon the support of experts
    for the fulfilment of their charter.
  • The ITAT chair can, if necessary, advise the SE
    Mgrs on the need to create a subgroup to address
    specific issues.
  • Currently three ITATs are active the DRS, the
    IMS and the Constellation

12
DRS ITAT
  • The DRS/GRS ITAT is chartered to provide the SE
    office the following inputs
  • GRS reference architecture and options
  • DRS reference architecture and options
  • Overall acceleration noise error budget
  • DRS requirements flowdown
  • GRS Risk List
  • GRS test (validation and verification) plan
  • DRS test (simulation) plan
  • Composition S. Vitale (chair), M. Sallusti, S.
    Buchman, S. Merkowitz, T. Hyde

13
IMS ITAT
  • The IMS ITAT is chartered by the SE office to
    perform the following tasks
  • Initially define the IMS architecture including
    options
  • Define interface between the IMS subsystems
  • Develop an error budget
  • Identify areas that require technology
    development
  • Develop a prioritized IMS risk list
  • Develop an IMS test plan
  • Define a constellation frequency plan for the
    space-space segment
  • Composition O.Jennrich (chair), K.Danzmann, P.
    McNamara, G.Heinzel, D.Shaddock, T.Stebbins,
    P.Bender, D.Robertson, T.Hyde (obs)

14
Constellation ITAT
  • The Constellation ITAT is chartered by the SE
    office to perform the following tasks
  • Define constellation concept (functions, system)
  • Identify DF interfaces to IMS and GRS
  • Define control requirements on micropropulsion
    subsystem
  • Define constellation acquisition strategy and
    relative requirements on DRS and IMS subsystems
  • Composition M.Sallusti (co-chair), S.Merkowitz
    (co-chair), T.Hyde, D.Bortoluzzi, J.Zeimer

15
Programmatic - SW
  • The agreement for SW includes the following
  • Software algorithms and the corresponding code to
    the level of e.g. MatLab routines will be defined
    and maintained by MSE throughout the mission
    lifetime.
  • Each Agency will independently verify and
    validate all mission software developed by the
    other Agency.
  • Each Agency will exchange models required to
    support design, verification, validation and
    operations with the other Agency.
  • If any of the points above requires specific
    clearances, NASA will promptly start the required
    process.

16
ESA Contribution
  • Under the current agreement, ESA is responsible
    to deliver the LISA Opto-mechanical Core System
    (LOCS)
  • The LOCS includes the following
  • Gravitational Reference System (GRS)
  • Structures
  • Optics
  • Laser Subsystem
  • Additionally ESA may deliver three Propulsion
    Modules (PM).

17
GRS
  • ESA supplies
  • Charge Management System
  • Vacuum Enclosure
  • GRS Analog Electronics
  • JPL supplies
  • Test Mass
  • Caging Mechanism
  • Electrode Housing
  • GRS Digital Electronics (TBC)
  • ESA integrates the GRS

18
Structures
  • ESA supplies
  • GRS OB Telescope Alignment Structure
  • Y- Tube
  • Instrument Thermal Insulation/Control

19
Optics
  • ESA supplies
  • Optical Bench (OB)
  • JPL supplies
  • Photodiodes
  • CCDs
  • Star Trackers

20
Laser Subsystem
  • ESA supplies
  • Laser
  • Modulator
  • Laser Stabilisation

21
ESA Contribution AIV
  • ESA integrates, verifies and delivers three LOCS
    to JPL.
  • ESA supports NASA during all system level LOCS
    integration and testing activities.
  • ESA supports the end to end system verification
    at GSFC and at the launch site.

22
ESA Contribution Ops SW
  • ESA supports in-orbit commissioning activities
    and nominal operations.
  • ESA performs the Software Independent
    Verification and Validation for all flight
    software.

23
JPL Contribution
  • JPL will be responsible to deliver the LISA
    Instrument Metrology and Avionics System (LIMAS).
  • The LIMAS includes the following
  • Frequency Distribution Subsystem
  • Phase Measurement Subsystem
  • Metrology System CDH
  • Metrology System Flight Software

24
JPL Contribution - AIV
  • JPL develops, integrates and verifies three LIMAS
    assemblies.
  • JPL integrates the three ESA-delivered LOCS onto
    the three LIMAS and verifies them.
  • JPL verifies Operation and Performance of the
    three LOCS/LIMAS assemblies with the support of
    ESA.

25
GSFC Contribution
  • GSFC will be responsible to deliver the
    following
  • Spacecraft Bus including subsystems
  • Constellation Software (drag-free and
    acquisition)
  • Microthrusters (TBC)

26
GSFC Contribution - AIV
  • GSFC integrates and verifies three Spacecraft
    Buses.
  • GSFC integrates and verifies the three LISA
    Scientific Complements (LOCS LIMAS Control
    Software Microthrusters) onto the three Buses.
  • GSFC integrates and verifies the three Propulsion
    Modules.

27
NASA Contribution
  • NASA procures the launch vehicle (Delta IV)
  • NASA performs operations via the DSN

28
Mission Formulation
  • ESA has started an industrial contract with
    Astrium GmbH for the LISA Mission Formulation on
    January 17, 2005
  • The activity will last two years and is divided
    into two phases, lasting respectively 9 and 15
    months
  • Regular Milestones have been set to ensure
    consistent system design and to phase work with
    NASA
  • Each phase is concluded with a review (Mission
    Architecture and Mission Definition Review
    respectively)
  • Additionally, a Mid-term Review will take place
    in the middle of phase 2

29
MF tasks
  • Astrium will support ESA in the consolidation of
  • Mission constituents and their interfaces
  • Model philosophy
  • Error budget apportionment and allocation to the
    constituents
  • Risk assessment and risk management plans
  • Mission Requirements in order to allow entering
    the Definition Phase
  • All the other elements required to support
    discussions with NASA on the share of
    responsibility

30
MF Phase 1
  • The objective of this phase is to consolidate the
    LISA mission architecture and design.
  • Main end products will be a complete set of
    draft Specs for the LISA mission elements, the
    DDVP, Budgets, Tech Plan
  • Among others, the following specific points will
    be addressed in phase 1
  • OB re-design and interfaces with IS
  • telescope and structure
  • Telescope pointing system
  • P/L Avionic and I/F with S/C
  • Error budget
  • Constellation acquisition
  • point ahead
  • Critical review and analysis of the S/C and
    Propulsion Module design
  • Mission scenario and Operations

31
MF Phase 2
  • A reference design (mechanical, optical,
    electrical) for the mission elements will be
    produced.
  • Product Tree, IRDs, Functional diagrams, Budgets
    will be consolidated
  • Risk assessment and margin policy will be
    reviewed
  • Environmental constraints will be reviewed
  • Key technology identified and technology plan
    proposed
  • MRD will be finalized and draft requirements
    documents for the mission elements will be
    prepared
  • The requirements verification logic and methods
    will be established

32
MF Short term
  • Short term (3 months scale) activities will
    concentrate on the following major architectural
    issues that have relevance in the definition of a
    set a requirements for the design
  • Use of Telescope/CCD as a Star Tracker
  • Acquisition and attitude control
  • Alignment
  • Point ahead angle
  • Telescope design

33
Mission Formulation
  • Mission Formulation has a different meaning at
    ESA and at NASA and care has to be exercised to
    avoid confusion

34
(No Transcript)
35
Data Processing
  • European plan of activities
  • Request Letter of Intent from interested parties.
  • Plan to have algorithm in prototype form at the
    end of 4 yrs period.
  • Need to the define the e2e data processing cycle
    with responsibilities and products at the various
    stages.

36
Data processing
1. Create ad-hoc data processing structure with
ESA chair 2. Define goals, plan of work,
schedule 3. ESA request sci community
LoI 4. Selection of scientists for participation
to data processing structure 5. SPC info paper
6. Mtg with selected parties to define plan of
work and required funding 7. Selected parties to
obtain national funding 8. ESA to place a
contract to study and define the LISA data
processing architecture
37
LISA Logo
Write a Comment
User Comments (0)
About PowerShow.com