Title: A'Gianolio LISA status 1
1LISA Status LISA France College de
France January 20-21, 2005 A. Gianolio LISA
Project Manager
2- Following a year of discussion, a programmatic
agreement for the LISA project has been reached
between ESA and NASA in August 2004 - WHY WAS SUCH AN AGREEMENT NECESSARY ?
- The interface between experiment and spacecraft
in LISA is such that the experiment drives the
mission design. - System Engineering needs to extend deep into the
definition of the mission elements. - The mission reference architecture has to be
defined during Mission Formulation in order to
finalize the share of responsibility. - Consequently, all major system engineering
decisions have to be agreed by both ESA and NASA. - The way this is implemented requires to be
formalized within an inter-agency agreement.
3Decisions
- ESA considers it essential that during the whole
mission and in particular during mission
formulation - no decision affecting overall mission performance
- no decision affecting technical design, early
technological investment, cost and schedule of
the other partner - can be taken by one partner without explicit and
well informed consensus by the other partner.
4Organization principles
- Single project with parallel organizational
structures in each agency. - Each agency is responsible for discharging its
obligations. - Each agencys project team responds to his own
management. - A high degree of interaction is required of the
two agencies.
5Mission phases
- Two mission phases can be identified
- FORMULATION
- Definition of mission and system requirements
and of mission architecture - IMPLEMENTATION
- Procurement of deliverables that fulfil the
above requirements - Additionally ESA will introduce the
- DEFINITION
- Industrial competitive phase to perform the
preliminary design of the ESA deliverables and
select the prime contractor for Implementation
6ESA-NASA Agreement
- The main elements of the agreement are
- Project description
- Project organisation
- System Engineering functions
- Mission elements share
- The Project description defines the general terms
to be adopted throughout the project
7Definitions
- LISA Scientific Complement it includes the LISA
Optomechanical Core Systems (LOCS), the LISA
Instrument Metrology and Avionics System (LIMAS),
the associated control software, microthrusters
(TBC) - Sciencecraft one spacecraft bus with its LISA
Scientific Complement - Constellation the three LISA sciencecraft
operating together. - Joint Project Managers Office (JPMO) LISA
project management office composed of the ESA and
the NASA project managers and their management
support, chaired jointly by the ESA and the NASA
project managers.
8Definitions
- Mission System Engineering (MSE) system
engineering team co-chaired by the ESA, the GSFC
and the JPL Mission System Engineering Managers,
who have equal authority and report to the JPMO.
MSE merges the system engineering teams of ESA,
GSFC and JPL. - Mission System Engineering Advisory Team (MSEAT)
small advisory body to the Mission System
Engineering. - Integrated Technical Advisory Teams (ITAT)
technical teams commissioned ad hoc by MSE to
provide inputs in specific areas.
9MF Project Organisation
The ESA and the NASA project managers share equal
responsibility in the management of the project
The JPMO, led by the ESA and the NASA project
managers, is in charge of the overall project
The JPMO has to approve, inter alia, the mission
reference design and the requirements
The project will adopt, as far as possible, a
single set of procedures, documentation and
reviews
10Programmatic
- The description of the System Engineering
functions constitutes a fundamental step forward
in the cooperation - it identifies the functions in Formulation and in
Implementation - it sanctions the principle that the mission
design has to be done jointly, to the level
required to clearly define the responsibility of
each agency - It establishes that decisions affecting the
project cannot be taken unilaterally by one
Agency - The implementing structure foresees three SE
managers working together to define mission
requirements and reference architecture, to be
submitted to the approval of the two project
managers
11ITATs
- ITATs are created by the SE Mgrs upon need and
they can be dissolved once the task is completed. - Their charter is defined by the SE Mgrs
- The ITATs composition is defined by the SE Mgrs
and can be modified during the existence of the
ITAT. - Each ITAT has have a chair appointed by the SE
Mgrs - The ITATs can call upon the support of experts
for the fulfilment of their charter. - The ITAT chair can, if necessary, advise the SE
Mgrs on the need to create a subgroup to address
specific issues. - Currently three ITATs are active the DRS, the
IMS and the Constellation
12DRS ITAT
- The DRS/GRS ITAT is chartered to provide the SE
office the following inputs - GRS reference architecture and options
- DRS reference architecture and options
- Overall acceleration noise error budget
- DRS requirements flowdown
- GRS Risk List
- GRS test (validation and verification) plan
- DRS test (simulation) plan
- Composition S. Vitale (chair), M. Sallusti, S.
Buchman, S. Merkowitz, T. Hyde
13IMS ITAT
- The IMS ITAT is chartered by the SE office to
perform the following tasks - Initially define the IMS architecture including
options - Define interface between the IMS subsystems
- Develop an error budget
- Identify areas that require technology
development - Develop a prioritized IMS risk list
- Develop an IMS test plan
- Define a constellation frequency plan for the
space-space segment - Composition O.Jennrich (chair), K.Danzmann, P.
McNamara, G.Heinzel, D.Shaddock, T.Stebbins,
P.Bender, D.Robertson, T.Hyde (obs)
14Constellation ITAT
- The Constellation ITAT is chartered by the SE
office to perform the following tasks - Define constellation concept (functions, system)
- Identify DF interfaces to IMS and GRS
- Define control requirements on micropropulsion
subsystem - Define constellation acquisition strategy and
relative requirements on DRS and IMS subsystems - Composition M.Sallusti (co-chair), S.Merkowitz
(co-chair), T.Hyde, D.Bortoluzzi, J.Zeimer
15Programmatic - SW
- The agreement for SW includes the following
- Software algorithms and the corresponding code to
the level of e.g. MatLab routines will be defined
and maintained by MSE throughout the mission
lifetime. - Each Agency will independently verify and
validate all mission software developed by the
other Agency. - Each Agency will exchange models required to
support design, verification, validation and
operations with the other Agency. - If any of the points above requires specific
clearances, NASA will promptly start the required
process.
16 ESA Contribution
- Under the current agreement, ESA is responsible
to deliver the LISA Opto-mechanical Core System
(LOCS) - The LOCS includes the following
- Gravitational Reference System (GRS)
- Structures
- Optics
- Laser Subsystem
- Additionally ESA may deliver three Propulsion
Modules (PM).
17 GRS
- ESA supplies
- Charge Management System
- Vacuum Enclosure
- GRS Analog Electronics
- JPL supplies
- Test Mass
- Caging Mechanism
- Electrode Housing
- GRS Digital Electronics (TBC)
- ESA integrates the GRS
18 Structures
- ESA supplies
- GRS OB Telescope Alignment Structure
- Y- Tube
- Instrument Thermal Insulation/Control
19 Optics
- ESA supplies
- Optical Bench (OB)
- JPL supplies
- Photodiodes
- CCDs
- Star Trackers
20 Laser Subsystem
- ESA supplies
- Laser
- Modulator
- Laser Stabilisation
21 ESA Contribution AIV
- ESA integrates, verifies and delivers three LOCS
to JPL. - ESA supports NASA during all system level LOCS
integration and testing activities. - ESA supports the end to end system verification
at GSFC and at the launch site.
22 ESA Contribution Ops SW
- ESA supports in-orbit commissioning activities
and nominal operations. - ESA performs the Software Independent
Verification and Validation for all flight
software.
23 JPL Contribution
- JPL will be responsible to deliver the LISA
Instrument Metrology and Avionics System (LIMAS). - The LIMAS includes the following
- Frequency Distribution Subsystem
- Phase Measurement Subsystem
- Metrology System CDH
- Metrology System Flight Software
-
24 JPL Contribution - AIV
- JPL develops, integrates and verifies three LIMAS
assemblies. - JPL integrates the three ESA-delivered LOCS onto
the three LIMAS and verifies them. - JPL verifies Operation and Performance of the
three LOCS/LIMAS assemblies with the support of
ESA.
25 GSFC Contribution
- GSFC will be responsible to deliver the
following - Spacecraft Bus including subsystems
- Constellation Software (drag-free and
acquisition) - Microthrusters (TBC)
-
26 GSFC Contribution - AIV
- GSFC integrates and verifies three Spacecraft
Buses. - GSFC integrates and verifies the three LISA
Scientific Complements (LOCS LIMAS Control
Software Microthrusters) onto the three Buses. - GSFC integrates and verifies the three Propulsion
Modules.
27 NASA Contribution
- NASA procures the launch vehicle (Delta IV)
- NASA performs operations via the DSN
28Mission Formulation
- ESA has started an industrial contract with
Astrium GmbH for the LISA Mission Formulation on
January 17, 2005 - The activity will last two years and is divided
into two phases, lasting respectively 9 and 15
months - Regular Milestones have been set to ensure
consistent system design and to phase work with
NASA - Each phase is concluded with a review (Mission
Architecture and Mission Definition Review
respectively) - Additionally, a Mid-term Review will take place
in the middle of phase 2
29MF tasks
- Astrium will support ESA in the consolidation of
- Mission constituents and their interfaces
- Model philosophy
- Error budget apportionment and allocation to the
constituents - Risk assessment and risk management plans
- Mission Requirements in order to allow entering
the Definition Phase - All the other elements required to support
discussions with NASA on the share of
responsibility
30MF Phase 1
- The objective of this phase is to consolidate the
LISA mission architecture and design. - Main end products will be a complete set of
draft Specs for the LISA mission elements, the
DDVP, Budgets, Tech Plan - Among others, the following specific points will
be addressed in phase 1 - OB re-design and interfaces with IS
- telescope and structure
- Telescope pointing system
- P/L Avionic and I/F with S/C
- Error budget
- Constellation acquisition
- point ahead
- Critical review and analysis of the S/C and
Propulsion Module design - Mission scenario and Operations
31MF Phase 2
- A reference design (mechanical, optical,
electrical) for the mission elements will be
produced. - Product Tree, IRDs, Functional diagrams, Budgets
will be consolidated - Risk assessment and margin policy will be
reviewed - Environmental constraints will be reviewed
- Key technology identified and technology plan
proposed - MRD will be finalized and draft requirements
documents for the mission elements will be
prepared - The requirements verification logic and methods
will be established
32MF Short term
- Short term (3 months scale) activities will
concentrate on the following major architectural
issues that have relevance in the definition of a
set a requirements for the design - Use of Telescope/CCD as a Star Tracker
- Acquisition and attitude control
- Alignment
- Point ahead angle
- Telescope design
33Mission Formulation
- Mission Formulation has a different meaning at
ESA and at NASA and care has to be exercised to
avoid confusion
34(No Transcript)
35Data Processing
- European plan of activities
- Request Letter of Intent from interested parties.
- Plan to have algorithm in prototype form at the
end of 4 yrs period. - Need to the define the e2e data processing cycle
with responsibilities and products at the various
stages.
36Data processing
1. Create ad-hoc data processing structure with
ESA chair 2. Define goals, plan of work,
schedule 3. ESA request sci community
LoI 4. Selection of scientists for participation
to data processing structure 5. SPC info paper
6. Mtg with selected parties to define plan of
work and required funding 7. Selected parties to
obtain national funding 8. ESA to place a
contract to study and define the LISA data
processing architecture
37LISA Logo