Title: CACILM


1
CACILM
  • MULTICOUNTRY CAPACITY BUILDING (MCB) PROJECT

SUMMARY AND THE WAY FORWARD
2
TASKS
  • (based on the mandatory ProDoc template)
  • 1. Situation Analysis
  • Contest and global significance
  • Threats, root causes and barriers
  • Stakeholder analysis and involvement plan
  • Baseline analysis

3
TASKS
  • (continued)
  • 2. Project Strategy
  • Institutional, sectors and policy analysis
  • Rationale and policy conformity
  • Goal, Objective, Outcomes and Outputs
  • Indicators, Risks, Assumptions
  • Incremental reasoning
  • Ownership, Eligibility, Drivenness
  • Sustainability
  • Replicability

4
TASKS
  • (continued)
  • 3. Management Arrangements
  • 4. Monitoring and Evaluation
  • 5. Strategic Results Framework (LogFrame)
  • 6. Budget

5
WORKPLAN
  • The Work Plan will combine the above Tasks with
    the Milestones below and indicate who does what.
  • It is currently being developed and will be
    communicated to all parties by next week

6
NATIONAL EXPERTS
  • Preliminary ToRs produced
  • Positions advertised (WWW) 06 May
  • Deadline for applications 20 May
  • Earliest start-up 26 May
  • Engaged for about 8 weeks
  • Last reporting by 14 July
  • But need to be available for any follow-up

7
MILESTONES
  • (tentative, yet to be confirmed with the Work
    Plan)
  • 02 June Situation Analysis completed
  • 10 June SRF Workshop
  • 30 June Project Strategy completed
  • 14 July Final reporting from National Experts
  • 20 July Final Draft (English Russian)
  • 05 August Deadline for feedback
  • 22 August Final endorsements
  • 31 August Final delivery

8
REPORTING LINES AND COORDINATION
  • Coordinators at Country level
  • Through National CACILM Secretariats
  • Data and information to go to appropriate
    international consultant
  • According to guidance provided by Team
    Coordinator (Robert Crowley)
  • All correspondence to be copied to Robert

9
(No Transcript)
10
COMMUNICATION
  • By email
  • In English
  • Data and information to be transmitted as soon as
    it is available
  • Final Country Report to be collated by
    Coordinators to be used as annex