Title: US CMS
1US CMS
- US CMS Project
- Dan Green
- US CMS Project Manager
- DOE/NSF JOG Meeting, June 13, 2002
2Outline
- Detector Status
- Completion Strategy
- Detector MO - Revised
- Status of SWC
- SWC Revised Proposal
- Issues
3Detector Financial Summary
4Financial Overview - I
- BCWS 109.0 AYM
- BCWP 98.54
- Obligations 103.37
- Paid Actuals 85.43
- Obligations/BCWS 95
- BCWP/BCWS 90
- Paid Actuals/BCWP 87
We are getting the funds out to groups and we are
getting the jobs under contract. There is some
lag in schedule/reporting and in invoicing.
5Financial Overview - II
- TPC Constant 167.25 (AYM)
- EAC 143.39
- Contingency TPC - BAC 23.86
- ETC BAC - BCWP 44.85
- BCWP/EAC 69
- Contingency/ETC 53
We have a fixed total cost. We are 69 complete
and retain 53 contingency on the estimated cost
to complete.
6ME - Fermilab Site
- Panel Production
- All chambers (410)
- Started June 1999
- gt 85 done
- ahead of schedule
- Finish Aug 2002
- CSC Assembly
- Large chambers (148)
- Started June 2000
- 55 done
- On schedule with the recent production rate 6
CSC/month - Finish March 2003
7ME Electronics
First CSC completed by FAST site
8HB-1 Assembly in SX5
1000 T of machined brass assembled good to 1 mm.
On time and on budget. The HCAL subsystem will
now move into an installation and commissioning
phase.
9Six channel FE Proto
The FE electronics is in advanced prototype
phase. ASICs are in production.
10HCAL ASICs on WH14
Replace with scintsource with QIEHPD.
First 1 channel slice test recently
completed at FNAL. Next is 100 ch in test beam in
July-August.
11Cal Trigger Status/Plans
- Preparing second generation prototype tests
- Crate, Backplane, Clock Control, ASICs done
- Receiver Card Electron Isolation Card ready.
- Serial Link Mezzanine Card Receiver done,Tester
Card at vendor, Transmitter Tester in design - Goals for 2002
- Complete of prototype tests, validate ASICs
- Integrate Serial Links w/ECAL,HCAL front-ends
- Prototype Jet/Summary card manufacture
- Ready for manufacture -- waiting for other board
tests - Finalize Jet Cluster crate design
12Second Gen. Crate Backplane
VME
48V DC Power
Std. VME Slots
Custom Point-to-point Dataflow
Rear
Front
- 160 MHz with 0.4 Tbit/sec dataflow
- Initial tests indicate good signal quality
- Designed to incorporate algorithm changes
- New Non-Isolated Electron, Tau Jet Triggers
13CSC Trigger Status/Plans
- Prototype 1 tests now complete
- Prototype 2 and production follow EMU components
to optimize technology - MPC, SP, CCC modules, backplane milestones
- Apr-02 Prototype 2 designs done
- Freeze CSC-DT interface
- Determine DDU compatibility with OSU module for
EMU - Nov-02 Prototype 2 construction done
- Apr-03 Prototype 2 testing done
- Sep-03 Final designs done
- Oct-04 Production done
- Apr-05 Installation done
- (backplane schedule 3 months ahead of above
dates to provide platform for testing and
integration) - Muon Sorter module only 1, design by Jan-04
Slice tests with portable Trigger using
prototype 2 boards -gt then full Trigger
14Evolution of CMS DAQ
New modular design of Event Builder - Break into
a number of functionally identical, parallel,
smaller DAQ systems A 64x64 system is feasible
today Submit DAQ TDR end-02
US CMS will build first 1/8 of DAQ and
prototype DAQ in slice tests. US CMS then
responsible for slice tests
15EVB Demonstrator
EVB demonstrator in Lab 32 323211 PCs
(RUBUEVMRCS) Myrinet 2000 128 port Clos
switch GB Ethernet 64 port FastIron 8000
16ECAL Electronics
CMS and LHCC Reviews in 2001 revealed major cost
overruns in electronics Last RRB Double speed of
optical links half cost of links BUT
insufficient Action - Mar 02 Alter electronics
architecture to contain costs generate L1
trigger primitive (S25 xtals) on-detector rather
than off-detector reduce links and off detector
electronics by factor 10. FPPA Final
submission May02 Electronics team reorganised,
synergy between ECAL, Tracker Preshower
electronics
TDR
TP
91000 Data and Control Links 800 Off-detector
Trig/DAQ Boards
12000 Data and Control Links 120 Off-detector
Trig/DAQ Boards
17FPPA plans
- Second FPPA review late May.
- If all OK then
- Submission late June Full wafer run.
- Wafers back early October (13 weeks)
- Test small quantity at LBL in ceramic package.
- Package 2000 in plastic package and test at Lyon.
Help from US group needed for this. - If all OK then (2/03)
- Proceed to production.
FNAL will get involved in FPPA tests and design
of alternatives - Yarema
18FPIX - FE Overview
- US CMS
- Token Bit Manager (TBM)
- Very High Density Interconnect (VHDI)
- High Density Interconnect (HDI)
- Port Card
- Front End Controller (FEC)
- European Groups
- Readout Chip (ROC) PSI
- Optical Links CERN
- Front End Driver (FED) Vienna
19TBM Implementation
- Dual TBM Chip
- Twin TBMs
- two analog readouts per blade side
- Control Network Hub
- port addressing for control commands
- 4-fold fanout (clock, trigger, reset)
- LVDS drivers
- Located on porch of each side of blade
DMILL run with ROC and TBM is a success. Now we
need to change to 0.25 ?m. First submission back
end of CY02
20TOB - Rods
1.2 m
21Robotic Assembly at FNAL
SiTrkr ready to assemble at FNAL and UCSB. Start
at end of CY02
- FNAL pick and place gantry
- Fully qualified for production
- Presently building modules as part of CMS M200
program - These will be used in the May test beam study.
22Detector Project Summary
- Recent reviews Detector June 5-6, FNAL
Technical Review April 29-May1, MO Review April
11. - MS cost experience has been good.
- The labor for CSC and HCAL absorber/optics has
been fairly well estimated. Chambers and
absorber/optics are done. - We are in the midst of FE electronics production
no cost or technical surprises (yet). - Contingency use has been good enough to allow for
modest scope increases SiTrkr, HE, HF, ME1/1,
ME VME (US CMS management) - It is logical to define the end of the Project to
be completion of deliverables prior to slice
tests in SX5 for commissioning.
23CMS SX5 Schedule V33
24Critical Path Analysis -V33
25 Extended Surface Phase
Additional costs part of C I
Objectives channel test of HV/LV burn-in of
electronics flushing gas readout test of ?10
of sub-detector (HB, HE, HO, HF,MB,ME, RB etc)
vertical slice tests with test-beam DAQ
prototype final DAQ
Convert the delay into UX into an opportunity for
commissioning with access. Get to Physics earlier.
26Project Complete -gt MO
27Project Completion
- It is logical, given the discontinuity between
SX5 and UX5 installation, to define Project
complete as SX5 installation. This can be done by
FY06 end. - MO begins with commissioning and preops in SX5
in FY03. - Final installation, costing 8 M, could be a
distinct effort.
28US CMS Resources
Note the rolloff of construction to MO by FY05.
The major category for MO is physicists -gt base
program.
BaBar Reality check
29US CMS Commitments
Total MO ramps up slowly as the detector
construction is completed. The ramp is the sum of
L2 handoffs.
30L2 Commitments
Each L2 has a different schedule to complete the
detector and handoff to MO
31L2 - Scrubbing
In scrubbing the costs engineering was released,
reducing scope, on the assumption that FNAL
personnel can be recaptured. In other cases,
knowledge transfer and consolidation was assumed.
This procedure carries serious risk. Tasks were
also somewhat delayed, which reduces schedule
float and risks discontinuity with the
construction team. Some costs on a fuzzy boundary
were shifted onto the construction project, which
reduces the project contingency.
32CO (Cat A) PO Costs
WBS 18 CO is 69 CatA bills. The Ops Office
is comparable to the PO, with a new CERN branch.
PO is extended to ease MO costs (but NSF FY04).
33Handoff to VCR, PAC
The estimated costs have been scrubbed. For
example, beyond paying the bills, there are few
costs prior to FY05. Then the VCR and PAC ramp up
to pace the detector slice tests and the data
challenges.
34Management Scrub
CO is Cat A, OM delay (use PO), RD delayed, MR
10 in FY02-FY05. This reduction means management
is rather less agile and detector is taxed.
35MORD Cost Estimates
36SWC Tier 1,2 in the US
CERN financial problems are an opportunity for
the US to step forward and lead.
37Preparing for First Beam
Need to keep in synch with CERN, LHC, and CMS
schedules
38Status and Progress
Common PO economy of scale
39User Facilities Status
UF needs to be augmented
40Prototype Operation
41Bare Bones SWC
- There has been a top down re-estimate of FY03 and
FY04 needs. - Basically, CCS is constant and UF is ramped up
very little. This puts the mock data challenge at
risk. - Revised planning at SWC status meeting June 21.
42Research Program Costs
Having scrubbed hard, and perhaps having
overshot, US CMS remains 2 M above guidance
for FY03-FY05.
43Research Program Scrub
- We have scrubbed the estimates
- RD is delayed gt FY05, Reserve is only 10
- PO is stretched to delay OM
- L2 costs are pushed onto Construction or are
delayed, as possible - SWC, UF ramp up is minimal in FY03, FY04
- The reduced costs are still 7 M above guidance.
We cannot cut harder without serious risk.
44Issues
- We need help in defining the end of detector
construction. Declare victory upon receipt of
MOU deliverables? - We need help in more rapidly starting up the
Research Program which is now back loaded. After
vigorous scrubbing, the needs are still above
guidance. - We need a commitment by NSF in support of the US
CMS Research Program at least at the 1/3 level
assumed in our planning.
45Summary
- The physics at the LHC is compelling.
- The transition of the detector project to the
Research Program begins in FY02. - The SWC , MO, and Upgrade RD components of the
Research Program all have resource loaded
schedules which are being scrubbed. - The Research Program will enable US physicists to
make a major impact on CMS, if it is properly
funded.
46Contingency Usage and Performance
We have 47 months of monthly reporting. CR can be
followed at any level of detail needed.
Contingency continues to be earned.
47FE/DAQ Electronics
48EMU Integration Status
- Cooling
- All valves, fittings, hoses purchased
- Manifold design finished - ready for production
- Gas
- CERN contract out for bid - covers piping gas
racks - Bulkheads - in production
- On-chamber integration
- 3 CSC styles finished (ME23/2, ME1/2, ME2/1),
only 2 styles remain (ME1/3, ME3/1) - Almost all parts procured for 1st 3 styles,
delivered to FAST sites
49RBX Readout Module
- The readout module (RM) integrates the HPD, front
end electronics, and digital optical drivers. PRR
passed March 1-2. - HB Production begun mechanics only. HE in
design. -
50Endcap Yoke Finished
51HB RBX Assembly
Full RBX with 19 ch RMs
RBX Interior -- HV distributor and backplane
52CSC Trigger Slice Test
- Requirements for 3-station 20 degree slice test
(9 chambers) - Need 3 MPC, 1 SP/SR, 1 CCB module, 1 backplane
- Integrate w/3 partially populated peripheral
crates 1 DDU - Schedule
- Apr-02 Prototype 2 designs done
- Nov-02 Prototype 2 construction done
- Apr-03 Prototype 2 testing done
- Sep-03 Final designs done
- CSC Sorter module only 1, design by Jan-04
- Not needed for Slice Test Itrigger out from CCB
- Oct-04 Production done
- Mar-05 Installation begins in USC55
- Slice Test Phase I
- Oct-03 to Oct-04
- Use Prototype 2 modules
- Slice Test Phase II
- Oct-04 to Mar-05
- Use Production Modules ( Proto. Sorter)
53New EMU Trigger Design
Track
-
Finder crate (1.6
Gbits/s optical links)
SP 2002 Card
(3 Sector Receivers
Clock and Control Board
Sector Processor)
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
CCB
/
/
/
/
/
/
/
/
/
/
/
/
(60
sector)
MS
SP
SP
SP
SP
SP
SP
SP
SP
SP
SP
SP
SP
BIT3 Controller
From MPC
(chamber 4)
Muon Sorter
From MPC
(chamber 3)
From MPC
(chamber 2)
From
Trigger Timing Control
From MPC
(chamber 1B)
From MPC
(chamber 1A)
To
To DAQ
Global
Trigger
Power consumption
1000W per crate
16 optical connections per SP
Custom backplane for SP ? CCB and MS connections
54WBS 19 Ops Office
There is an NSF branch which opens in FY04, and
a CERN branch which is integral to MO.
55MO RD at L2
The major cost drivers for US CMS are HCAL, EMU
and Common Ops, totaling 2/3. Common Ops
Operations Management are 1/3 of the total.
56Scrubbing Results
Both the scope has been reduced and the tasks
have been delayed. Both effects have risks to
the US CMS institutional memory
57US CMS MO Resources
Estimated D0 engineers techs as a reality
check
58MO Upg RD SWC
59FNAL Technical Review
- There was a Directors Review on US CMS, April
30. - External Committee looked at ME, HCAL and Trigger
electronics production. In addition review
covered FPIX and SiTrkr status and progress, both
Si itself and the associated electronics. - There was general agreement about the areas of
concern.