Title: Cost to Comply
1Wisconsin Act 141
2Wisconsin Act 9 RPS
2001 - 2002
0.5
2003 - 2004
0.85
2005 - 2006
1.2
2007 - 2008
1.55
2009 - 2010
1.9
2011 and Beyond
2.2
3Wisconsin Act 141
- Originated from the Governors Task Force on
Energy Efficiency and Renewables - Task Force Submitted Recommendations in October
2004 - Introduced as Senate Bill 459 in November 2005
- Enacted into Law in March 2006 by Governor Doyle
- Administrative Rules for Renewables Approved in
Early 2007 - Midwest Renewable Energy Trading System (MRETS)
Currently Under Development
4Wisconsin Act 141
- Goals is to produce 10 of Wisconsin Retail Sales
with Renewable Resources - The Requirements are for each Retail Provider to
add 2 to Baseline Renewable Generation by 2010
and another 4 by 2015 - 2001, 2002 and 2003 Average Renewable Generation
is used as Baseline which Includes Hydroelectric - Any Excess Renewable Generation can be Converted
into RRCs with a 4-year Bank Life
5Requirement Comparison
1 Million MWhs per year incremental requirement
6Renewable Need In Perspective
- 1,700 to 2,000 Megawatts of Wind Power Needed in
Wisconsin (Wisconsin Currently has 50 MW) - 2,000 MW of wind capacity is..
- About 1,333 wind turbines
- About 1,263 Dairy Digesters
- About 197 landfill gas-fired generators
- About 238 million square feet (8.6 square miles)
of solar photovoltaic panels
Estimated at 30 Capacity Factor
7Why Wind?
- Why Renewable Proponents Like It
- Next to Solar, it is the most environmentally
benign - Its not Nuclear, Coal or Natural Gas
- View it as Grass Roots Economic Development
- Why Independent Power Producers Like it
- RPS Mandates have Created a Market with Limited
Alternatives - In Terms of Risk Adjusted Returns, ROE is Very
Attractive - Why WPSC has Identified Wind Power as the Best
Alternative - Most Economic of Renewable Alternatives on a
Large Scale - Even In Consideration of
- Lack of Capacity Value
- Recent Cost Run Ups
- Interconnection and Deliverability Risk
- Siting and Permitting Risk
- Demonstrates that Other Alternatives are more
risky and out of the money.
8Estimated Wind Project Costs(/Kw)
- EPRI TAG-RE 2002 997
- EPRI TAG-RE 2005 (Dec 04) 1,133
- EPRI TAG-RE 2006 (Dec 06) 1,753
- Cedar Ridge (06 Alliant CA) 1,823
- (Owner developed and constructed)
- Top of Iowa (06 MGE CA) 2,000
- (Turnkey Purchase)
- 2007 projected 2,100 to 2,400
9RISK Market Cost of Projects
Note This Represents a Snapshot in time to
Demonstrate Concept - 2002 MAIN Stack
For a 30 CF Project
10RISK - Interconnection
MISO QUEUE - WIND ONLY
Yes...that's 45,000 MW !
11RISK Locational Marginal Price
For Illustrative Purposes Only
Predicting when Transmission will be Available in
5 States is no Easy Task
12RISK Siting and Permitting
Every 1 change in capacity factor results in a
2.50/MWh change in energy price for wind
Moving the turbines on western ridge resulted in
a decrement to capacity factor
Over the period of project delay, the price of
turbines increased by over 400,000 per MW
nameplate rating
PSCW Imposed Setback
Estimated Impact of 8,000,000/year for 20 years
13- Thank You -