Title: CIPULARANG II TOLL ROAD PROJECT


1
CIPULARANG IITOLL ROAD PROJECT
  • C. Willy Hartono
  • Sales Manager
  • West Java
  • Admixture System

2
  1. Section I Purwakarta
  2. Section II South Purwakarta Plered
  3. Section III. 1 Plered Cikalong Wetan
  4. Section III. 2 Darangdan Cikalong Wetan
  5. Section III. 3 Cisomang Bridge
  6. Section IV. 1 Cikalong Wetan Cikubang
  7. Section IV. 2 Cikubang Bridge
  8. Section IV. 3 Cikalong Wetan Cikamuning
  9. Section IV. 4 Cipada Cikamuning
  10. Summarize

3
1. General Overview
  1. Total Length is 40 km
  2. Divided by 9 Sections
  3. Starting in March 2004 done before April 25,
    2005 (The 50th Anniversary of Asia Africa
    Conference in Bandung, West Java)
  4. Starting with earthworks in March 2004
    continuing with concrete works in July 2004
  5. Girder produce insitu by precaster (Adhi
    Precast, Wika Beton, Saeti)

4
2. Section I Purwakarta
  1. Main Contractor is Mawatindo
  2. Supervision Consultant is Virama Karya
  3. Total Length is 9 km
  4. Concrete supplied by Farika Duta Agung (2 BP).
  5. Concrete Volume 100,000 m3
  6. We supplied 100 (Pozzolith 101 Ri Rheobuild
    1100) to Farika Duta Agung
  7. Wet Mix for Rigid Pavement

5
2. Section I Purwakarta
6
3. Section II South Purwakarta - Plered
  1. Main Contractor is Adhi Karya Division III
  2. Supervision Consultants are Cipta Strada, Saka
    Adhi Prada Amythas Expert
  3. Total Length is 8 km
  4. Concrete supplied by Adhimix
  5. Concrete Volume 80,000 m3 for Rigid Pavement only
  6. We supplied 100 (Pozzolith 100 Ri Rheobuild
    1100)
  7. Wet Mix low slump for Rigid Pavement concrete
    barrier
  8. Girder Supplied by Adhi Precast

7
3. Section II South Purwakarta - Plered
8
4. Section III. 1 Plered Cikalong Wetan
  1. Main Contractor is Waskita Yasa J.O.
  2. Supervision Consultants are Delta Tama Waja,
    Buana Archicon Prosys
  3. Total Length is 6.3 km include 500 m long bridge
  4. Concrete supplied by Yasa Readymix Multi
    Structure
  5. Total Concrete Volume is 40,000 m3
  6. Admixture supplied by Fosroc (SP 337 RP 264 M)
    to Yasa Readymix Grace to Multi Structure
  7. Girder produced in situ with total 153 pieces
    using Yasa Readymix

9
4. Section III. 1 Plered Cikalong Wetan
10
5. Section III. 2 Darangdan - Cikalong Wetan
  1. Main Contractor is Nindya Karya
  2. Supervision Consultants are Multi Phi Beta, Tata
    Guna Patria Indra Karya
  3. Total Length is 4 km
  4. Concrete supplied by Dwi Dinamika
  5. Concrete Volume 40,000 m3
  6. Admixture supplied by Fosroc (SP 337 RP 264 M)
  7. Girder Supplied by Wika Beton (Glenium 317 from
    BASF M 21N from KAO)

11
5. Section III. 2 Darangdan - Cikalong Wetan
12
6. Section III. 3 Cisomang Bridge
  1. Main Contractor is L M System
  2. Supervision Consultant is Global Profex Synergy
  3. Concrete supplied by Pionir Beton
  4. Concrete Volume 25,000 m3
  5. Admixture supplied by Sika (Plastiment RMC)
  6. Girder produced insitu (Sikament NN) supplied
    by Saeti Concretindo Wahana (Rheobuild 893)

13
6. Section III. 3 Cisomang Bridge
14
7. Section IV. 1 Cikalong Wetan - Cikubang
  1. Main Contractor is Daya Mulya Turangga
  2. Supervision Consultants are Bina Karya,
    Eskapindo Matra Hasfarm Dian Consultant
  3. Total Length is 5 km
  4. Concrete supplied by Focon Indo Beton
  5. Total Concrete Volume is 30,000 m3
  6. Admixture supplied by BASF (Pozz. 101 Ri
    Rheobuild 1100) Sika (Plastiment R Sikament
    NN )
  7. Girder supplied by Wika Beton ( Glenium 317 from
    BASF M 21 N from KAO)

15
7. Section IV. 1 Cikalong Wetan - Cikubang
16
8. Section IV. 2 Cikubang Bridge
  1. Main Contractor is Propelat Wika J.O.
  2. Supervision Consultant is Yodya Karya
  3. Total Length is 4 km including 400 m long bridge
  4. Concrete supplied by Focon Indo Beton
  5. Total Concrete Volume is 30,000 m3
  6. Admixture supplied by BASF (Pozz. 101 Ri
    Rheobuild 1100) Sika (Plastiment R Sikament
    NN)
  7. Girder supplied by Wika Beton ( Glenium 317 from
    BASF M21N from KAO)

17
8. Section IV. 2 Cikubang Bridge
18
9. Section IV. 3 Cikalong Wetan -
Cikamuning
  1. Main Contractor is Hutama Karya
  2. Supervision Consultant is Indec Ass Ltd.
  3. Bridge with 750 m long (The longest bridge in
    Cipularang II project)
  4. Concrete supplied by Farika Duta Agung
  5. Total Concrete Volume is 50,000 m3
  6. We supplied 100 (Pozzolith 101 Ri Rheobuild
    1100)
  7. Girder produced in situ with total 183 pieces

19
9. Section IV. 3 Cikalong Wetan
Cikamuning
20
10. Section IV. 4 Cipada - Cikamuning
  1. Main Contractor is Sumber Mitra Jaya Ircon Int.
    J.O.
  2. Supervision Consultants are Indah Karya, Widya
    Graha Angsana Tribina
  3. Total Length is 4 km
  4. Concrete supplied by Beton Indotama Surya
  5. Total Concrete Volume is 30,000 m3
  6. Admixture supplied by Sika (Plastiment R
    Sikament NN
  7. Girder supplied by Wika Beton ( Glenium 317 from
    BASF M 21 N from KAO)

21
10. Section IV. 4 Cipada - Cikamuning
22
11. Summarize
  1. We got about 50 share of the project
  2. We supply to Adhimix Citapen (1 BP), Focon Indo
    Beton (1 BP) Farika Duta Agung (2 BP in
    Purwakarta 1 BP in Padalarang)
  3. Sales value more than 500 million in 6 months
    (July to December 2004)
  4. Farika Duta Agung Padalarang gave the biggest
    contribution for our sales value

23
THANK YOU