Title: Lessons Learned and Earned Value Management System Assessment
1Lessons Learned and Earned Value Management
System Assessment
GLAST Large Area Telescope Lowell A.
Klaisner Stanford Linear Accelerator
Center Project Manager Klaisner_at_slac.stanford.edu
650-926-2726
2Background
- Pathfinder project
- First flight instrument integrated at SLAC
- Most of the staff at SLAC were unfamiliar with
the effort required to meet space instrumentation
requirements - Challenging project
- Largest silicon detector, 800K channels
- Limited bandwidth to ground
- Event processing on board
- Space qualifying state of the art instrumentation
- Rigorous requirements of space instrumentation
- Low power
- Withstand launch loads
- Vacuum
- Challenging thermal environment
- Reliability
3EVMS Assessment
- The EVMS system could not anticipate problems
that arose from insufficient engineering in
critical areas early in the project and showed up
in environmental testing as the project moved
into the flight hardware fabrication phase - The EVMS system did not track earned value for
work being done by foreign partners on
independent budgets (eg the work in Italy
supported by INFN and ASI) - The GLAST mission office exercised rigorous
control of the requirements while the Office of
Science exercised rigorous control of the funding
which limited ability to respond to cost growth
and schedule stretch out
4Tracker example of anomaly response
Technical Issue Tracker (Past Year) Root Cause Incurred Delay
(months)
Bias circuit design error and coupon plating problems. Design Problem 0
MCM and cable termination resistors. Design Problem 0
MCM-sidewall clearance issues. Design Problem 1
Pitch-adapter flex circuit trace cracking. Process Problem 1
Cable-closeout short circuit. Design Problem 0
Encapsulation of wire bonds on heavy trays. Process Problem 1
Bonding of Kapton bias circuits to tungsten. Process Problem 3
Tracker-Grid interface fastener failure and alignment issues. Design and Process Problem 9
MCM encapsulation delamination. Process Problem 1
PWB short circuits. Process Problem 0
ASI funding problems. Funding Problem 3
Conformal coating workmanship. Process Problem 0
Flex-circuit cable via problems. Process Problem 0
Flex-circuit cable workmanship problems. Process Problem 0
5Lessons Learned
- The Joint Oversight Group is too removed to
resolve schedule and funding issues for the
project - When a DOE laboratory takes on a project in a new
discipline such as GLAST, extra effort is
required at the beginning to assure that the
scope of the project is well understood. - Also, the new infrastructure that is required
needs to be identified and adequately planned - Facilities
- Staffing particularly special expertise
required - Management staffing, systems and procedures
- The DOE does not have the technical staff, QA
support, management support, and funding
flexibility that are available from the GLAST
Mission Office - In particular, lack of funding flexibility
limited the DOEs ability to assist in
identifying the issues and provide adequate
response - The DOE TEC was defined before the project was
adequately engineered - GLAST predates PED funds
6Path Forward
- SLAC now has the facilities in place to integrate
a space instrument - Key staff are in place to execute future
space-based instrumentation projects - In particular, a strong data acquisition system
staff is in place with experience with space
hardware and software - The Kavli institute is attracting renown
astro-physicists - Executing key science with GLAST
- Planning and executing future astro-physics
projects.