Lessons Learned and Earned Value Management System Assessment - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

Lessons Learned and Earned Value Management System Assessment

Description:

GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner_at_slac.stanford.edu 650-926-2726 Gamma-ray Large Area Space ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 7
Provided by: Lowe2
Category:

less

Transcript and Presenter's Notes

Title: Lessons Learned and Earned Value Management System Assessment


1
Lessons Learned and Earned Value Management
System Assessment
GLAST Large Area Telescope Lowell A.
Klaisner Stanford Linear Accelerator
Center Project Manager Klaisner_at_slac.stanford.edu
650-926-2726
2
Background
  • Pathfinder project
  • First flight instrument integrated at SLAC
  • Most of the staff at SLAC were unfamiliar with
    the effort required to meet space instrumentation
    requirements
  • Challenging project
  • Largest silicon detector, 800K channels
  • Limited bandwidth to ground
  • Event processing on board
  • Space qualifying state of the art instrumentation
  • Rigorous requirements of space instrumentation
  • Low power
  • Withstand launch loads
  • Vacuum
  • Challenging thermal environment
  • Reliability

3
EVMS Assessment
  • The EVMS system could not anticipate problems
    that arose from insufficient engineering in
    critical areas early in the project and showed up
    in environmental testing as the project moved
    into the flight hardware fabrication phase
  • The EVMS system did not track earned value for
    work being done by foreign partners on
    independent budgets (eg the work in Italy
    supported by INFN and ASI)
  • The GLAST mission office exercised rigorous
    control of the requirements while the Office of
    Science exercised rigorous control of the funding
    which limited ability to respond to cost growth
    and schedule stretch out

4
Tracker example of anomaly response
Technical Issue Tracker (Past Year) Root Cause Incurred Delay
(months)
Bias circuit design error and coupon plating problems. Design Problem 0
MCM and cable termination resistors. Design Problem 0
MCM-sidewall clearance issues. Design Problem 1
Pitch-adapter flex circuit trace cracking. Process Problem 1
Cable-closeout short circuit. Design Problem 0
Encapsulation of wire bonds on heavy trays. Process Problem 1
Bonding of Kapton bias circuits to tungsten. Process Problem 3
Tracker-Grid interface fastener failure and alignment issues. Design and Process Problem 9
MCM encapsulation delamination. Process Problem 1
PWB short circuits. Process Problem 0
ASI funding problems. Funding Problem 3
Conformal coating workmanship. Process Problem 0
Flex-circuit cable via problems. Process Problem 0
Flex-circuit cable workmanship problems. Process Problem 0
5
Lessons Learned
  • The Joint Oversight Group is too removed to
    resolve schedule and funding issues for the
    project
  • When a DOE laboratory takes on a project in a new
    discipline such as GLAST, extra effort is
    required at the beginning to assure that the
    scope of the project is well understood.
  • Also, the new infrastructure that is required
    needs to be identified and adequately planned
  • Facilities
  • Staffing particularly special expertise
    required
  • Management staffing, systems and procedures
  • The DOE does not have the technical staff, QA
    support, management support, and funding
    flexibility that are available from the GLAST
    Mission Office
  • In particular, lack of funding flexibility
    limited the DOEs ability to assist in
    identifying the issues and provide adequate
    response
  • The DOE TEC was defined before the project was
    adequately engineered
  • GLAST predates PED funds

6
Path Forward
  • SLAC now has the facilities in place to integrate
    a space instrument
  • Key staff are in place to execute future
    space-based instrumentation projects
  • In particular, a strong data acquisition system
    staff is in place with experience with space
    hardware and software
  • The Kavli institute is attracting renown
    astro-physicists
  • Executing key science with GLAST
  • Planning and executing future astro-physics
    projects.
Write a Comment
User Comments (0)
About PowerShow.com