Title: INDONESIA ELECTRICITY SUPPLY CHALLENGES: TEN-YEAR ELECTRICITY DEVELOPMENT PLAN 2010-2019
1 INDONESIA ELECTRICITYSUPPLY
CHALLENGESTEN-YEAR ELECTRICITY DEVELOPMENT PLAN
2010-2019
PT PLN (PERSERO)
1
2ELECTRICITY DEMAND FORECAST 2010-2019
- The electricity demand growth estimated average
9.3 per year (Jawa-Bali 8.97, West Indonesia
10.2 and East Indonesia 10.6) - The electricity sales from year 2010 onwards is
forecasted by assuming an average economic growth
of 6.2 and an average population growth of
1.17. - It is anticipated that the sales for those years
would not be constrained, as all of the power
plants of the fast track program would have been
already in operation. - Electrification ratio increase from 65 in 2009
to 91 by the end of 2019. - DSM program to shave and shift peak load has not
been taken into account.
2
3DEMAND FORECAST 2010-2019
JAVA-BALI SYSTEM
Electricity Demand growth average 9.3/year
3
4INDONESIA ELECTRICITY RATIO 2009 sekita63
NAD 72,7
Sumut 75,5
Kaltim 53,9
Kalselteng 56,3
Riau Kepri 44,7
Sulutenggo 51,2
Kalbar 49,5
Sumbar 67,6
Sulteng 47,64
Babel 48,4
Sulselrabar 55,8
SumselJambiBengkulu 50,3
Maluku 53,5
Bali 76,2
Lampung 47,1
JabarBanten 64,95
Jatim 61,6
JatengYogya 70,2
NTT 21,7
NTB 29,9
Papua Irjabar 27,8
5POLICY IN GENERATION EXPANSION PLANNING
- Some ageing and inefficient oil-fired power
plants are retired as soon as more effcient
plants are available. - Generation expansion planning is made on
least-cost principle, by looking for generation
configuration that have minimum system costs. - However, development of renewables (especially
geothermal and some hydro) is encouraged, by
treating these as fixed plants prior to
optimisation process. - Loss of Load Probability (LOLP) of lt1 day/year is
used as reliability criteria during planning
process. - The reserve margin is restricted within 35-50
range based on net dependable capacity. Rental
power plants and excess power are not taken into
account.
5
6POLICY IN GENERATION EXPANSION PLANNING
- Gas supply is assumed to be available for Java
Bali system, yet for outside Java Bali system
gas-fired power plants are considered only if
there is a definite gas supply. LNG receiving
terminal is also considered as one option of gas
supply. - Development of small scale coal-fired powerplants
is used to substitute oil-fired powerplants for
smaller systems, if there is no local primary
energy resource available. - Coal-fired power plants with unit size of 1,000
MW supercritical would be introduced into the
Java-Bali system. - PLN expects a bigger role from private sector in
IPP development.
6
7GENERATION CAPACITY EXPANSION PLAN
Additional Capacity 53,219MW up to 2019 PLN
Generation 32,636MW and IPP 20,583MW, Average
4800MW/year
8Fast Track Program Phase 1 (Jawa)
- PLTU 1 Jateng-Rembang, 2x315MW, Cons.
ZelanTronohPriamanaya, Contract Signed
21March2007 - PLTU 2 Banten-Labuan, 2x300MW, Cons.
ChengdaTruba Jurong, Contract Signed 21March2007 - PLTU 1 Jabar-Indramayu, 3x330MW, Cons.
SinomachCNEECPT Penta Adi Samudra, Contract
Signed 21March2007 - 4. PLTU 2 Jatim-Paiton, 1x660MW, Cons. Harbin
PEMitra SelarasHutama Energi, Contract Signed
7August2007 - 5. PLTU 1 Banten-Suralaya, 1x625MW, Cons.
CNTICRekayasa Industri, Contract Signed
12March2007 - 6. PLTU 1 Jatim-Pacitan 2x315MW, Cons. Dongfang
ElectricDalle Energy, Contract Signed 7Augus2007 - 7. PLTU 2 Jabar-Pelabuhan Ratu, 3x350MW, Cons.
Shanghai ElectricMaxima Infrastructure, Contract
Signed 7August2007 - 8. PLTU 3 Banten-Teluk Naga, 3x315MW, Cons.
Dongfang ElectricDalle Energy, Contract Signed
7August2007 - 9. PLTU 3 Jatim-Tg. Awar Awar, 2x350MW,
SinomachCNEECPenta Adi Samudra, Contract Signed
25April2008 - 10. PLTU 2 Jateng-Adipala Cilacap, 1x660MW,
Contract 22December2008, COD 2012
9Fast Track Program Phase 1 (Outside Jawa)
- PLTU 2 Sumut-Pangkalan Susu, 2x220MW, Cons.
GuangdongNintecBagus Karya - PLTU Kepri-Tg. Balai Karimun, 2x7MW, Cons.
ShangdongRekadaya Elektrika - PLTU NAD-Meulaboh, 2x110MW, Synohydro
- PLTU 1 Riau-Bengkalis, 2x10MW, Cons. Guandong
MachineryModacoKelsriAngkasa Buana - 5. PLTU 2 Riau-Selat Panjang, 2x7MW, Bouwstead
Maxitherm - 6. PLTU Sumbar-Teluk Sirih, 2x212MW, Cons.
CNTICRekayasa Industri - PLTU Lampung-Tarahan Baru, 2x100MW, Jiangxi
Electric Power Design InstituteAdhi Karya - 8. PLTU 3 Babel-Bangka Baru, 2x30MW, Cons.
Truba,China Shanghai Group - 9. PLTU 4 Babel-Belitung 2x16,5MW, Cons. Shandong
MachineryPoeser Indonesia - 10. PLTU 1 Kalbar-Parit Baru, 2x50MW, Cons. Bumi
Rama NusantaraAltons - 11. PLTU 2 Kalbar-Bengkayang, 2x27,5MW, Cons.
Guangdong MachineryWijaya Karya - PLTU Kalsel-Asam Asam, 2x65MW, Cons.
ChengdaWijaya Karya - 13. PLTU 1 Kalteng, Pulang Pisau, 2x60MW
- 14. PLTU 1 NTB-Bima, 2x10MW, GuandongModaco
EnersysAngkasa Buana Cipta - 15. PLTU 2 NTB-Lombok,2x25MW, Barata Indonesia
- 16. PLTU 1 NTT-Ende 2x7MW, Cons. Shandong
MachineryRekadaya Elektrika
10Fast Track Program Phase 1 (Outside Jawa)
18. PLTU Gorontalo, 2x25MW, Meta Epsi 19. PLTU 2
Sulut-Amurang, 2x25MW, Wijaya Karya 20. PLTU
Sultra-Kendari, 2x10MW, Cons. Shangdong
MachineryRekadaya Elektrika 21. PLTU
Sulsel-Barru, 2x50MW, Cons. Hubei Hongyuan
EngineeringBagus Karya 22. PLTU Maluku
Utara-Tidore, 2x7MW, Cons. Shandong
MachineryRekadaya Elektrika 23. PLTU 3
Papua-Jayapura, 2x10MW, Cons. Modern Widya
TechnicalBoustead Maxitherm
11Fast Track Program Phase 2
- More geothermal projects will be developed, and
large coal fired power plant in Java to be
excluded from Fast Track Program Phase 2. In
addition to that, Upper Cisokan Pumped Storage
Project will be included in the program. - The composition of project will consist of
geothermal 48, hydro 12, gas combined cycle
14 and coal fired outside Java-Bali 26. - The capacity of the projects will be as follows
- Java-Bali geothermal 2,137 MW, hydro 1,000 MW
and gas combined cycle 1,200 MW. - Outside Java-Bali coal plant 2,616 MW, hydro 174
MW, geothermal 2,596 MW, and gas combined cycle
240 MW. - Total Indonesia coal plant 2,616 MW, hydro 1,174
MW, geothermal 4,733 MW and gas combined cycle
1,440 MW, totalling 9,963 MW.
12 Fast Track Program Phase 2
- The second phase of fast track program will
consist of 3,649 MW of PLNs project and 6,314 MW
of IPP project. - The 1,200 MW gas combined cycle in Java-Bali is
Muara Tawar Add-On 2,3,4 project. This project is
very strategic in that it will meet the future
demand by the year 2011-2012, however the
feasibility of the project will subject to gas
supply availability. - The 1,000 MW hydro project in Java-Bali is Upper
Cisokan Pumped Storage. This project is very
strategic as it will serve as peaking unit to
replace the role of oil fired plants. - Most geothermal projects will be IPP. To ensure
the success of the projects within the time frame
of the program (up to 2014), geothermal
developers must take immediate project
preparation and PLN must make immediate
geothermal IPP procurement.
13Summary of Fast Track Program Phase 2
REGION Steam Coal PP (MW) Combined Cycle PP (MW) Geo PP (MW) Hydro PP (MW) Total (MW)
JAVA-BALI - 1.200 2.137 1.000 4.337
OUTSIDE JAVA-BALI 2.616 240 2.596 174 5.626
TOTAL 2.616 (26) 1.440 (14) 4.733 (48) 1.174 (12) 9.963 (100)
14Map of Fast Track Program Phase 2
- SUMATERA
- PLTA 174 MW
- PLTP 2285 MW
- PLTU 1100 MW
- PLTGU 120 MW
- KALIMANTAN
- PLTU 840 MW
- PLTGU 120 MW
- SULAWESI
- PLTP 195 MW
- PLTU 418 MW
- MALUKU
- PLTP 40 MW
- PLTU 44 MW
- NTT
- PLTP 46 MW
- PLTU 30 MW
- TOTAL
- PLTA 1174 MW
- PLTP 4733 MW
- PLTU 2616 MW
- PLTGU 1440 MW
- TOTAL 9963 MW
- JAMALI
- PLTP 2.137 MW
- PLTU 0 MW
- PLTGU 1.200 MW
- PLTA 1.000 MW
- NTB
- PLTP 30 MW
- PLTU 70 MW
15Investment of Fast Track Program Phase 2
16TRANSMISSION EXPANSION PLANNINGJAVA-BALI
2008-2018
16
17 Project Name COD Financing Plan
Transmisi 275 kV Sumatera (Payakumbuh Padangsidempuan) 2012 Loan JICA
Transmisi 275 kV Rengat Garuda Sakti (220 km) 2014 unallocated
Transmisi Sumatera-Jawa 500 kV HVDC 2016 USD 2,3 milyar, Loan JICA
Jawa-Bali Crossing 500 kV HVAC 2015 USD 328 juta, akan diusulkan ke ADB
Interkoneksi Kalbar-Serawak 275 kV HVAC 2012 USD 101 juta, akan diusulkan ke ADB
Interkoneksi Sumatera-Malaysia 250 kV HVDC 2015 USD 353 juta, akan diusulkan ke ADB/JICA
Perkuatan Transmisi Sistem Jakarta dan Bali 2011 2012 USD 420 juta, KE
Perkuatan Transmisi Kota-Kota Besar di Jawa 2012 USD 250 juta, IBRD
Transmisi 500 kV AC Tj Jati - Ungaran Pemalang Mandirancan Indramayu (500 km) 2015 USD 300 juta, unallocated
18DISTRIBUTION EXPANSION PLAN
- ADDIONAL DISTRIBUTION FACILITY UP TO 2019
- MV 181,000KMS ? 16,500 KMS/YEAR
- LV 249,500KMS ? 22,700 KMS/YEAR
- DISTRIBUTION TRANSFORMER 35,000 MVA ?
3,200 MVA/YEAR - ADDITIONAL COSTUMER 27,4 MILION? 2,5
MIO/YEAR
19PLN INVESTMENT
INVESTMENT PROJECTION UP TO 2019 USD 64,7
BILLION, INCLUDING INVESTMENT FOR LIFE
EXTENSION/REFURBISHMENT EXISTING GENERATION,
SPARE IBT
20PLN IPP INVESTMENT
INVESTMENT PROJECTION UP TO 2019 USD 83,0
BILLION OR USD 7,6 BILLION PER YEAR, INCLUDING
INVESTMENT FOR LIFE EXTENSION/REFURBIS MENT
EXISTING GENERATION, SPARE IBT
21PLN PROJECT JAWA-BALI SYSTEM
22IPP PROJECT JAWA-BALI SYSTEM
23SUMMARY
- For the next 10 years
- The average electricity demand would grow at
9.3/year (Jawa-Bali 8.97, West Indonesia 10.2
and East Indonesia 10.6) - Total additional generation capacity for
Indonesia is 53,219 MW, consists of 32,636 MW of
PLN projects and 20,583 MW of IPP projects - Development of renewable energy, especially
geothermal, is encouraged, by additional 5,006 MW
by 2018 - Total additional transmission network would reach
44,257 kms for all voltage levels, and total
additional of transformers would be 103,000 MVA
for all voltage levels. - Total additional distribution network is 175,013
kms for MV, 222,018 kms for LV, 30,877 MVA for
distribution transformers and 25 million new
customer connections.
24SUMMARY
- Total investment needed for Gen Trans Dis is
US 64,69 billion (PLN only) or US 82,99 billion
(PLNIPP). - Investment needed for PLN power plant projects
alone is US 38,581 billion, and for IPP projects
is US 18,31 billion.
25Some strategic generation projects
SUMMARY
- CCGT Muara Tawar Add-on 2, 3, 4, 1,200 MW,
commissioned in 2011-2012. - Fast Track Generation Project 10,000 MW Phase 2
with total capacity of 11,355 MW year 2011-2014
(this figure might change due to recent
governments will to promote more geothernal). - Upper Cisokan Pumped Storage of 4x250 MW in 2014
(WB) - CFPP Jawa Tengah Infrastruktur (IFC) 2x1,000 MW
in 2014-2015. - CFPP mine mouth in Sumatera 6x600 MW in 2016-2017
(transferred to Java Bali system) - CCGT LNG Bojanegara 3x750 MW in 2015-2017.
25
26Some strategic transmission projects
SUMMARY
- HVDC transmission between Sumatera and Java in
2016. - Sub-sea 150 kV Java-Bali circuit 3,4, 2010
- Batam Bintan interconnected system using
sub-sea 150 kV, 2010 - 275 kV transmission connecting West Kalimantan
Serawak in 2011 - 500 kV Java-Bali Crossing from Paiton to
Kapal/near Denpasar in 2015
26
27PT PLN (PERSERO)
Thank You