A Presentation by: - PowerPoint PPT Presentation

About This Presentation
Title:

A Presentation by:

Description:

* PPP Projects in Energy Sector No. Plant Capacity (MW) Type FCOD /Status Procurement Method 1. IberAfrica 106 Thermal 1997 Open competition on first 56MW, ... – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 35
Provided by: kpl13
Category:

less

Transcript and Presenter's Notes

Title: A Presentation by:


1
PUBLIC PRIVATE PARTNERSHIPS IN THE POWER SECTOR
IN KENYA
  • A Presentation by
  • Laurencia K. Njagi,
  • Company Secretary
  • Kenya Power Lighting
  • Company Ltd
  • To the Law, Justice and Development Week 2012

2
INTRODUCTION
  • Comprehensive reforms implemented between 1993
    and 2000 in accordance with the Energy Sector
    Policy Framework Papers 1993-1995 and 1996-1998 .
  • Objectives of the reforms were to enhance
    operational efficiency and attract private sector
    investment in power generation.

3
INTRODUCTION
  • The private sector participation would
  • (i) Create competition in the generation
    function
  • (ii) Improve operational efficiency and
  • (iii) Complement GoKs investment which could be
    used in other sectors not attractive to private
    sector.

4
SUMMARY OF IMPLEMENTED REFORMS
  • Separation of commercial functions from policy
    setting, and regulatory functions.
  • This involved transfer of power assets owned by
    government and two regional development
    authorities to two main public companies i.e. the
    Kenya Power Lighting Company Ltd. (transmission
    assets) and Kenya Power Company Ltd., now KenGen
    (generation assets).

5
SUMMARY OF IMPLEMENTED REFORMS
  • Unbundling of generation function from
    transmission and distribution functions.
  • KenGen undertaking generation function and KPLC
    undertaking transmission and distribution
    functions.
  • KPLC and KenGen were required to operate on a
    commercial basis under a Power Purchase Agreement
    which was first entered into in 1999.

6
SUMMARY OF IMPLEMENTED REFORMS
  • Legislative reform through the enactment of the
    Electric Power Act, 1997.
  • Establishment of a power sector regulator in
    1997 the Electricity Regulatory Board with the
    mandate to set retail tariffs, approve negotiated
    PPAs between KPLC and generating companies and
    overall regulation of the sector.

7
SUMMARY OF IMPLEMENTED REFORMS
  • The Electric Power Act, 1997 was repealed in 2006
    and replaced with Energy Act -to consolidate
    electricity and petroleum regulation into one
    regulator.
  • Development of power generation projects on the
    basis of approved national least cost investment
    plan.
  • Cost reflective electricity tariffs.

8
PPP Projects in Energy Sector
No. Plant Capacity (MW) Type FCOD /Status Procurement Method
1. IberAfrica 106 Thermal 1997 Open competition on first 56MW, then extension in 2007
2. Tsavo Kipevu II 74 Thermal 2001 Open Competition
3. OrPower 4 100 Geothermal 2000 Open Competition for phase 1 later expansion
9
PPP Projects in Energy Sector
No Plant Contracted Capacity (MW) Technology Full Commercial Operation Date/Status Procurement Method
4 Rabai 90 Thermal 2009 Open Competition
5 Mumias 25 Bagasse 2008 Co-Generation
6 Thika 87 Thermal 2013 Open Competition
7 Triumph 83 Thermal 2013 Open Competition
10
PPP Projects in Energy Sector
No. Plant Contracted Capacity (MW) Technology Full Commercial Operation Date/Status Procurement Method
8 Gulf Athi River 80 Thermal 2014 Open Competition
9 Aerolus Kinangop 60 Wind 2014 Feed In Tariffs
10 AGIL Longonot 140 Geothermal 2014 Unsolicited Proposal
11
PPP Projects in Energy Sector
  • Other 4 mini hydro projects under feed in tariff.

12
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(i) Least Cost Power Development Plan
  • Kenya has a 20 year Least Cost Power Development
    Plan for transmission and generation systems that
    is updated annually.
  • The Government and KenGen agree on the projects
    to be developed by KenGen based on its financial
    and technical capacity.

13
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(i) Least Cost Power Development Plan
  • KPLC procures private investors to develop plants
    not being developed by KenGen.
  • Most of the geothermal and hydro projects are
    implemented by KenGen due to low IPP bidders
    interest.

14
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(i) Least Cost Power Development Plan
  • In order to remove the risk of geothermal steam,
    a fully state-owned geothermal company has been
    established to carry out geothermal exploration
    and development and to sell steam to private
    developers and KenGen for conversion to
    electricity.

15
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(ii) Bridging Capacity Gap
  • In the event of delays in the implementation of a
    committed project in the LCPDP, a decision is
    made to procure development of a power plant of a
    technology which can be implemented in a short
    period by private investors to bridge the
    capacity gap.

16
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(ii) Bridging Capacity Gap
  • This has been the case for a number of thermal
    projects.

17
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(iii) Feed In Tariffs For Renewable Energy
  • Kenya has a Feed In Tariff with set energy charge
    rates for various renewable energy sources to
    encourage their development.
  • Proposals from interested developers are analyzed
    and approved if found adequate by a Standing
    Committee under the Ministry of Energy.

18
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(iii) Feed In Tariffs For Renewable Energy
  • PPA negotiations are carried out between the
    private investors and KPLC.

19
CRITERIA FOR PROJECT DEVELOPMENT ON A PPP
BASIS(iv) Unsolicited Proposals
  • Some projects have been awarded for development
    as PPPs following unsolicited proposals.
  • Mostly in technologies like geothermal and wind
    which are difficult to subject to competitive
    bidding without investing first to ascertain the
    natural resource potential.

20
LOCATION OF THE PLANT
  • A decision on the siting of the project is made
    based on the location of the natural resource
    (hydro, geothermal and wind), the proximity to
    the load centre and transmission and distribution
    connection facilities.

21
PROCUREMENT PROCESS AND APPROVAL
  • Kenya has a Public Procurement and Disposal Act,
    2006, that governs procurement by government and
    state corporations.
  • Competitive bidding is the normal method of
    procurement.
  • The Act provides for a review mechanism of
    appeals from bidders who are dissatisfied with
    the procurement/evaluation outcome.

22
PROCUREMENT PROCESS AND APPROVAL
  • The Public Private Partnerships Regulations made
    under the Act provide specialized procedures for
    procurement and approvals of PPP projects and
    sets out a PPP Secretariat under the Ministry of
    Finance.
  • A PPP Bill is before parliament as a stand alone
    legislation for PPPs.

23
PROCUREMENT PROCESS AND APPROVAL
  • The negotiated PPAs are subject to approval by
    the sector regulator, the Energy Regulatory
    Commission.

24
IPP PRICES
  • The prices payable to IPPs in the PPAs are
    derived from competitive bidding process.
  • For the Feed In Tariff Policy projects, the rates
    are set by Feed In Tariff Policy.

25
IPP PRICES
  • The prices for unsolicited proposals are
    negotiated i.e. project costs, cost of funding
    are screened including the rate of return to be
    allowed and are, where applicable, compared with
    those of existing projects.

26
IPP PRICES
  • The rate of return is guided by ERCs Tariff
    Policy which had followed a study.

27
RISKS THAT KPLC AND GOK HAVE TAKEN
  • KPLC has taken the market/demand risk -PPAs are
    on a take or pay basis this arrangement will be
    reviewed as the market becomes competitive.
  • The forex risk is borne by electricity consumers.
    Payments are denominated in either dollars or
    Euros. The variations are passed through to
    customers.

28
RISKS THAT KPLC AND GOK HAVE TAKEN
  • Political risks are borne by GOK through a
    legally binding letter of support issued to the
    projects.

29
PAYMENT SECURITIES PROVIDED
  • The payment security provided to IPPs by KPLC has
    usually been stand by letters of credit from
    commercial banks in Kenya covering 3 4 months
    of payments
  • In view of planned increased IPP participation,
    KPLC requested GOK to support the sector by
    providing sovereign guarantees to IPPs.

30
PAYMENT SECURITIES PROVIDED
  • In order to manage contingent liability, GOK
    requested IDA to provide partial risk guarantee
    to four projects (87MW Thika), (83MW Triumph),
    80MW Gulf) and 52MW geothermal extension) thus
    dispensing with sovereign guarantees.

31
FACTORS THAT HAVE CONTRIBUTED TO SUCCESSFUL PPPS
IN POWER SECTOR
  • An enabling environment -National Energy Policy
    and Energy Act, 2006.
  • Both recognise need for cost reflective retail
    tariffs and IPP charges that should, among
    others, enable the investors to attract capital
    and compensate them for the risks assumed.

32
FACTORS THAT HAVE CONTRIBUTED TO SUCCESSFUL PPPS
IN POWER SECTOR
  • A mature regulatory framework ERC was created
    in 1997 and has been approving PPAs and setting
    retail tariffs.
  • Capacity of KPLC to procure, negotiate, and
    monitor IPPs.

33
FACTORS THAT HAVE CONTRIBUTED TO SUCCESSFUL PPPs
IN POWER SECTOR
  • Financial stability of KPLC as the off-taker.
  • Sound governance of KPLC and energy sector
    leadership.
  • Structured competitive procurement process of
    PPPs.

34

THE END THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com