Title: Ethiopian Roads Authority Design Review and Approval
1Ethiopian Roads Authority Design Review
and Approval
-
- Focused On Design Management
-
2Outline
Design Management Theory The Process of Feasibility and Engineering Design Responsibility for Design-Contractual and legal aspects Case Studies
3Time and Cost Over Runs
4(No Transcript)
5(No Transcript)
6Description Unit 2003 EFY (Base year) 2004 EFY 2005 EFY 2006 EFY 2007 EFY
Projects completed within contract time 15 28 6 22 16 36
Projects completed within contract Budget5 26 31 32 40 50
7Targets the Design Performance
Customers' Needs and Expectations Customers' Needs and Expectations Customers' Needs and Expectations Current Performance Current Performance Stretched Objective
Criterion Measurement Importance (H, L, M) As-Is Process TO BE Performance Stretched Objective
1. Project Design Sub Process 1. Project Design Sub Process 1. Project Design Sub Process 1. Project Design Sub Process 1. Project Design Sub Process 1. Project Design Sub Process 1. Project Design Sub Process
1 Quality Incr. to the original works contract price (( per project) H 18.05 or (40 mill) N/A 5
1 Quality Time extension to the original works contract ( per project) H 54. or (580 days) N/A 5
1 Quality Env., Socio-economic and Safety Considerations Detailed and that satisfy customers demand (H, M, L) M L M H
1 Quality Project Design Duration - not longer than 365 days (100km) M 384 398 365
2 Time Time taken to review design documents (working days/document) H ?? 17.0 6 - 13
3 Cost Incr. in construction cost due to delay in design duration Zero (age incr. in construction cost /project OR ETB/Km/project) M 1 OR 29,000 ETB/Km/project N/A Zero
8The Need for Design Management
- Failures during design have significantly
contributed to cost and time overruns, - Cost and time overruns can reduce significantly
if the quality of design deliverables is
enhanced, - Clients (ERA in particular) expecting better
performance from both designers and contractors
and their need to be certain of the final outcome
of their projects
9The Need for Design Managementcont
- Clients have also sought greater control over
their projects and an increased involvement in
decision-making, - Design is a complex process that continues to
grow in complexity because of the dramatic
increase in specialist knowledge. There are now
many contributors to the design of a project from
a wide variety of organizations
10Definition
- Design Management is best seen as an
information processing system driven by
innovative and/or creative solution to problems
of the client organization.
11Design ManagementCont.
- Two important aspects of Design Management
- The need to produce information that fully
interconnects the inputs of all the contributors
into one coherent and complete piece without
ambiguity, - Ensuring that all contributors are working to a
co-ordinated schedule to achieve a timing of the
information flow that allows the development of
the co-ordinated information.
12Management and Organization in design and
construction
- Separating responsibility for managing from the
responsibility for doing work is firmly
entrenched in the management literature, - The management of industrial production
processes, and can be traced back to Adam Smith
and Charles Babbage, as shown by Hawk (1996).
13Management and Organization in design and
construction
- OrganisationTo organize something is to arrange
the elements into a co-ordinated whole. This
shows that complex things can only be understood
when orderly structure is imposed upon them. In
other words, dealing with complex issues often
requires the whole to be split into pieces, - ManagementThe definition of manage is to
conduct things and people in order to achieve
some end. Management involves co-ordination,
motivation, leadership and many aspects of
getting things done through other people
14Management and Organization in design and
construction
- Complexity Common in construction projects
(Bennett 1992). Not due to technological
complexity (mostly) but due to the following
causes - The need for different discipline to come
together during design, - Specialization
- Economic reasons to belong to different firms
15- Differentiation
- The simple idea is people working on a particular
thing differed in a number of respects, - Fragmentation and specialization may refer to an
increased division of labor within the
construction industry
16Fragmentation and specialization
17- Differentiation is more than a mere division
of labor the difference in attitude and behavior
of the managers concerned - orientation towards certain goals (e.g. economy
is more important in cost control than it is in
structural design, where safety and stability are
more important) - time orientation (construction site planning is
likely to have a shorter term than the
development of a design brief).
18- Lawrence and Lorsch
- people differ because of their own learnings and
predilections, - The key thing is that these differences exist
because they are needed, - They identified that greater levels of
differentiation required greater levels of
integration, - The amount of differentiation required is
dependent on the complexity of the organizations
environment, so simply eliminating
differentiation is of no help.
19- Integration
- Unifying the diverse contributions into a
cohesive team effort, - Co-ordination is concerned with ensuring that the
output from each team member is directed towards
the clients objectives, - In order to achieve these, information must flow
from one team member to another,
20Integration-Traditional/ Hierarchical and Team
work
21Relative increase in the number of communication
links for different Style of Organization
Number of People Central Control Central Control Team Work Team Work
Number of People No. of Links Increase () No. of Links Increase ()
2 1 1
3 2 100 3 200
4 3 50 6 100
5 4 33 10 66
6 5 25 15 50
7 6 20 21 40
8 7 17 28 33
22- Techniques for co-ordinating work and
achieving integration - 1. Standardize and control internal operations
in order to facilitate interaction between
inputs, outputs and boundary transactions - Procedures
- Hierarchy
- Planning
- 2. Reduce the amount of information required
- Creation of self-contained units
- Slack resources
- Environmental control
23- Techniques for co-ordinating work and
achieving integration - Increase the information processing
characteristics of the firm - Task autonomy
- Information systems
- Lateral relations
24Management and Organization Cont.
- Contingency theories of organization show that
the best way to organize a complex task is to
ensure that the skill diversity (differentiation
of technology) is appropriate to the complexity
of the task, and then to match the level of
integration and co-ordination (management
functions) to the level of differentiation.
25Management and Organizationcont
- The task of the design manager is to make sure
that the organization of the design process is
structured appropriately for the task at hand,
and to ensure that there are sufficient
integrative and coordinating mechanisms for the
work to progress meaningfully, - The collaboration between individuals is part of
the wider collaboration between firms in the
construction sector. The construction industry is
thus characterized as networks of transactions, a
phenomenon that exacerbates discontinuities in
the process, but an inevitable feature, given the
nature of the tasks and the market.
26(No Transcript)
272. The process of Feasibility and Engineering
Design
28Terms of Reference(ToR)/ Statement of
Requirement(SoR)
- Older Version
- Requirements stated vaguely
- No code of ethics
- No quality manuals
- Limited requirements
-
- New Revised Version
- States clear comprehensive requirements and
process - Includes ERA Code of Professional Conduct and
Ethics - Instructs to use latest ERA design manuals and
quality manuals
29Feasibility and Preliminary Design
- Feasibility Study and Preliminary Design
- The client and the designers must agree on the
complete scope of the work, - The process involves identifying the real problem
as well as solving it, - Designers work in a complex and interactive way
this requires the additional focus
of prioritization to the project delivery
objectives
30Feasibility Study and Preliminary Design
- The design manager must achieve the following
during Feasibility Stage - Allow designers time for reflection,
- Establish a framework within which the tasks and
objectives are kept in focus as the design moves
through its stages of development, (How?) - Help the designer understand the full
implications of a new definition of the design
problem and the possible need to re-enter the
design cycle, - Maintain Continuous liaison with the Client.
31The Four Part of the Design Process (From
Hickling)
The Choice The Product
Interpretation What is the Shape of the Problem A definition of the problem
Generation What are the alternative solutions A range of alternative solutions
Comparison What Makes them Different A set of comparison and preferences
Choice Where do we go from here A decision regarding policy and action
32Contd
- the proposition that design is a linear sequence
can be questioned, - the designer thinks freely across and around the
boundaries of a problem, -
- a complex cyclic model is more realistic and
representative of the process
33(No Transcript)
34Components of Phase I Design
- Study of Maps, Aerial Photography and Literature
- Proposed Corridors
- Site Visit and Survey
- Towns Passed Through by Project Road
- Orographic and Morphological Characteristics
- Socio-Environmental Impact of the Project on the
Area - Recommendation
- Consultation Process
- Traffic Data and Analysis
- Highway Engineering
- Economic Data
- Economic Evaluation
35- Base Case (do minimum Case)
- shall be used as the basis for evaluation
- Not the do noting criteria
- and the do minimum shall only be the work
necessary to keep the road open
- project case represents one or perhaps two or
more feasible solutions to solving the problem or
issue at hand - of the most important features of effective
project analysis
36Criteria for Acceptance
- The expected present value of the project's net
benefits must not be negative and - The expected present value of the project's net
benefits must be higher than or equal to the
expected net present value of mutually exclusive
project alternatives, - The project must pass stringent environmental
screening criteria
37Value Management
- Value management is a strategy of examining every
aspect of the whole project to ensure that all of
the expectations can be delivered in the most
economical way, - A problem with traditional briefing documents is
that few contain any judgment as to the relative
priorities in the requirements
38Value Hierarch/Tree
Life time cost
39Decision Matrix/ Multi criteria
40- Detailed Engineering Design
- The engineering design process deals with the
creation of the production information necessary
for site operations - Design Management must obviously make sure that
all the information transfers occur at the right
time, which can only be achieved if the required
knowledge and its availability has been organized
and contracted
41- Topographic Survey Report
- Identification of national grid points and
benchmarks - Purpose of topographic survey what the data is
to be used for, e.g. for detailed design of road
or structures, for hydraulic modelling of
watercourses, for ROW and land acquisition
(recording property boundaries and physical
assets), etc
- Based on the findings of the Feasibility Study
- Geometric Standards and Design Speeds
(carriageway width) - Road safety features
- Design criteria and standards for pavements
42- Materials and Site Investigation Report
- Engineering Design Report
- Environmental Impact Assessment Report
- Hydrology Report
- Structural Report
- Land Acquisition Report
43Engineering Drawings and Detail drawings
- In UK the Practice is for the Engineer a lot of
Design Information (1 drawing 9 m2, contractor 1
drawing 17m2) - US and other European Practice-follow
standardized approach (Contractor 4x as many
drawings)
- Costly practice,
- Gives way to mistake
- Originality/ innovativeness of the design
- Standard design
- Not appropriate for detail designing
- Requires competent contractor to make use of the
design
44Topographic Surveying
- Route Selection using desk study and field
reconnaissance survey - Feasibility Study use route selection data, plus
partial topographic survey - Detail design uses full topographic survey
- Route Selection using maps, aerial photographs
and satellite imagery - Feasibility Study use route selection data, plus
full topographic survey - Detail Engineering Design use Feasibility Study
data, plus Supplementary survey where required
45Concept of Optimization
- Minimizes cost and time overrun during
construction. - Adds value to the detail design
- Optimize the initial design to reduce volumes of
earthworks and rock excavation, improve drainage
design, improve road safety design, and minimize
land acquisition, without compromising the
quality of the road services.
46Planning, Monitoring and Controlling
- Iterative process and partial completion not
indicated, - Simple, link, interconnectivity not addressed,
- Suited for construction phase,
- ADePT-Activity as well as information
interdependency - 7-30 loops, 350-400 design tasks, 2400
information dependencies
- Network Analysis
- Bar Chart
- Information required schedule
- Information transfer schedule
473. Stages, Roles and Responsibilities
48Stages, Roles and Responsibilities
- Change in responsibility with each
phase-additional burden on management - Ensure that designers, in attempting to limit
design liability, do not confuse their
co-ordination and management responsibility with
liability for the content of their design and so
limit their co-operation
49(No Transcript)
504.Design Liability
- There are two types of liability
- professional liability, imposing an obligation on
a consultant to act with skill and care,and - absolute liability, requiring fitness for
purpose. This may be attached to an agreement to
provide a finished building - PI policies
51Art. 2636. - Required care and responsibility.
- (1) Whoever hires out his work shall undertake to
carry it out in the best interest of his client,
conscientiously and in conformity with the
practice and rules of his profession, -
- (2) He shall not be liable to his client, unless
he commits an error, having regard to the
rules of his profession, - (3) The error may consist in an omission or an
act detrimental to his the client
52ERA Code of Professional Conduct and Ethics
- ERA seeks to ensure that all professional firms
and individuals, who provide services and works
on its behalf, abide by a Code of Professional
Conduct and Ethics that supports the aim of
providing a high quality, safe and efficient road
network in the interest of the public. - Consists of Five set of rules (1)Responsibility
to Public, Society and Profession,
(2)Responsibility to Client/Employer, (3)
Responsibility for Environment, (4)
Responsibility to Professionals, (5) Adherence
and Disclosure
53- 5. Case Studies Variation Order during
Management
VO No. Short Description of Variation Orders Issued Date of Issue of Variation Order
1 Widening of Urban Section 22/Dec/08
2 Provision of Walkways in Urban Sections 4/Feb/09
3 Change of wearing course from DBST to AC 17/Aug/09
4 provision of Additional Slab Culverts 30/Jan/10
5 Design Modification of Assasa Town 27/Apr/10
6 Construction of safe structures in flood prone areas of Kubsa and Assasa Town 5/Oct/10
7 Removing and Relaying of existing pipes 28/Nov/10
8 provision of vehicular access 7/Feb/11
9 Change of SST to AC at towns for parking lanes 6th May 2011
- Could have been done at one times
54S.No. Project Problems Possible Causes
1 Project A Increase in overall cut volume from 239,960.00m3 to 2,108,572.76 m3 (an increase by about 778.72 over the design provisions for same) Error in quantity estimation-escarpment section located at the middle of the project had not been properly quantified-related to improper surveying. Improper desk study and site investigation survey
Increase in cut/ borrow to fill volume from 421,493.00 m3 to 557,791.08 m3 (an increase by about 32.34 over the design provisions for same) Improper estimation of borrow to fill material
Pavement type change from DBST to AC has brought about additional cost of about 65 million birr Traffic study has not been properly investigated in terms of considering potential generated traffic, diverted following improvement of the existing road type Improper economic analysis of project area
2. Project B Pavement type change from DBST to AC has brought about additional cost of about 57 million birr Ditto as above
3. Project C Increase in quantity of minor drainage structures by 46 Increase in major drainage structures by 40.09 Slope instability and land slide problems and increase in quantity of ditches Improper sub-surface investigation Improper estimation of the quantity of abutment Improper sub-surface investigation
55Contd
4. Project D Increase in quantity of AC surfacing by about 42.47 Improper computation of AC quantity
5. Project E Land slide problem Inappropriate route selection Inadequate sub-surface investigation
- Missing of Geotechnical Investigation
56Conclusion
- Client demands improvement in Quality of Design
- Enhanced Design can be achieved by applying the
principles of design management, - Design management, can be considered as a
framework for managing interconnectivity, quality
and timely delivery of design information, - Liability is being enforced through code of
conducts and design accountability.
57