Title: Contract Management and Administration
1URRAP-Training of Trainers for Contractors and
Coordinators
Ministry of Transport Ethiopian Roads Authority
- Contract Management and Administration
- Tsegaye Borse(ERA)
- (BSc. CoTM)
- DAY 4- Tuesday August 06, 2013
2Outline of the Presentation
- Introduction
- Results of Neglected Contract Management
- Learning Objectives
- Contract and its Legal Framework
- Definition of Contract and its nature
- Primary Ingredients of Contract
- So why do we need a written contract??
- Project Delivery System, Contract Types and
Construction Risk - Types of Project Delivery System
- Contract Types
3Outline of the Presentation.contd
- Types of Risk in Construction Contracting
- Contract Management and Administration
- What do you mean by Contract Management and
Administration - Main tasks of Contract Management
- What effective contract Management accomplishes??
- Primary Roles and obligations of the Parties to
the Construction Contract - Types of Standard Conditions of Contract
- Communications
4Outline of the Presentation.contd
- Claims Management and Dispute Resolution
- Typical Claims Against the Owner
- Typical Claims Against the Contractor
- Likely source of construction Delay and
Disruption - Claims Analysis
- Claims Prevention Suggestions
- Dispute Resolution Mechanisms
- Discussion Points and Feedbacks
- Selected Contractual Issues
5Introduction
- Results of Neglected Contract Management
- Learning Objectives
6Introduction..contd
- Results of Neglected Contract Management
- End user frustration because of poor contract
performance in timeliness quality - Lack of contractor accountability
- Implementing Agency acceptance of poor quality
- Increased costs and
- Under or overpayment to a contractor
- Keep the End in Mind at the Beginning!!!
7Introduction..contd
- Learning O bjectives
- Understand about Contract and contract
management - Understand roles and responsibilities of parties
under General Conditions of Contract - Role, Relationships, expectations and
communications between the owner, design,
contractor and supplier teams - Understand Contract types and Delivery systems
- Construction Risk
- Brain storming about claims and Dispute
8Contract and its Legal Framework
- Definition of Contract and its nature
- Primary Ingredients of Contract
- So why do we need written contract??
9Contract and its Legal Frameworkcontd
- Definition of Contract and its nature
- A contract is a legally binding agreement between
the parties(t w o or more) identified in the
agreement to fulfil all the terms and conditions
outlined in the agreement. - All construction is done within a contract except
that is done by a person for himself. - A contract determines the actions of the parties
in their dealings with each other. The parties to
a contract are bound to each other for a certain
period of time by a unique and exclusive
relationship (pri vity of contract) they have
created for their mutual benefit.
10Contract and its Legal Frameworkcontd
- This contractual relationship persists until the
contract is discharged or terminated (because of
impossibility, agreement, bankruptcy, or breach
of contract). - It is important that the construction contract,
whatever form it may take, accurately documents a
meeting of the minds states clearly the roles
and responsibilities of the parties without
overlaps or voids and aims squarely at achieving
a quality project.
11Contract and its Legal Frameworkcontd
- Primary Ingredients of Contract
- Mutual Agreement and Genuine Intention
- Offer and Acceptance
- Capacity to Contract
- Consideration in a Contract
- Lawful Object of a Contract
- Contract Time
12Contract and its Legal Frameworkcontd
- Mutual Agreement and Genuine Intention
- Mutual agreement is the fundamental and mutual
consent which is normally expressed by the
parties to a contract in the offer originally
made by one, which then is accepted by other. - Sometimes the acceptance of an offer may be
unspoken and indicated or accepted by an action,
rather than by actual words. - A contract may be defined as a promise enforcea
ble by la w, and there must be genuine intention
on the parties to take on obligations agreed in
the contract.
13Contract and its Legal Frameworkcontd
- Offer and Acceptance
- Offer and acceptance of the offer are natural
expressions of mutual agreement. As such, both
the offer and the acceptance must be identical to
their sub stance. - When an offer is made it should be accepted
without qualification. No change to an offer
should be made in the acceptance, and what is
offered should be accepted as it is offered.
Otherwise, the offer should be refused, and, if
required, notice may then be given that a
different kind of offer is sought.
14Contract and its Legal Frameworkcontd
- An offer may be withdrawn at any time prior to
its acceptance. - Mutual agreement must be based on free assent
without duress or undue influence, so that there
is a real meeting of the minds of the parties.
Anything less than this may result in an invalid
contract. - Once an offer is accepted, however, the offer
cannot be withdrawn because it has been changed
by its acceptance into a contract. - The primary purpose of a bid bond/security is to
guarantee the owner that the bidder whose bid he
accepts will enter into and perform the contract.
15Contract and its Legal Frameworkcontd
- Capacity to Contract
- Capacity refers to the competency to make valid
and enforcea b le contracts. - A citizen who is
- Not under the age of majority
- Sane, and not a drunkard
- Not under legal restraint
- Not restricted by his or her occupation or
profession - has the greatest possible freedom to enter into
and make contracts
16Contract and its Legal Frameworkcontd
- Considerations in a Contract
- Consideration is something of value given by one
party in a contract to the second party in
exchange for something else. - A contract is an agreement with consideration.
- In contract law, consideration can be anything of
value and the law usually is not concerned with
the amount of value. Its sufficiency is a matter
for the parties to bar gain over and agree to. - Consideration can be a promise not to do
something such that the result will be of value
to the other party.
17Contract and its Legal Frameworkcontd
- Lawful object of a Contract
- The object of a contract must be lawful, for the
law will not enforce a contract for an illicit
purpose. - It is more probable to see illegal work done
under a contracts change order, because changes
are not always subjected to the same official
scrutiny as the work originally proposed and
shown in the contract documents, and it is
possible that a change could be made to do
construction work that would be illegal (e.g.
increase rooms seating capacity beyond its legal
limit).
18Contract and its Legal Frameworkcontd
- Contract Time
- Time is the scarcest of all construction
resources (capital, labor, material, equipment,
etc.). - Contract time affects contract sum since most
costs depend on time (e.g. costs of labor,
equipment use, and overhead costs).
19Contract and its Legal Frameworkcontd
- So why do we need a written contract??
- Basic lack of trust
- Clearly establishes the risks and obligations of
each party - Provides means by which performance can be
assessed and measured - Provides means by which breaches can be
identified - Provides means by which default can be
established - Establishes the owners means of control
- Establishes the contractors scope of work
20Contract and its Legal Frameworkcontd
- Discharge of a Contract
- Contracts are said to be discharged when the
contracting parties are released form their
contractual obligations. - Once the contract is discharged, the parties are
no longer bounded by its terms although the
discharge itself may result in enforceable
rights. - In general, there are four ways in which a
contract may be discharged
21Contract and its Legal Frameworkcontd
- Performance
- parties have performed all their respective
obligations, as for example, when the contractor
has carried out the work fully in accordance with
the contract and when the employer has paid all
amounts due to the contractor. - Frustration
- where the parties are unable to perform their
obligations owing to events outside their
control, force majeure but contracts are not
frustrated if there become too difficult or too
expensive to perform.
22Contract and its Legal Frameworkcontd
- Breach
- where one party fails to perform his contractual
obligations. - Agreement
- where both parties agree to terminate the
contract before complete performance.
23Project Delivery System, Contract Types and Risk
- Types of Project Delivery System
- Contract Types
- Types of Risk in Construction Contracting
24Project Delivery System, Contract Types and
Risk.Contd
- Types of Project Delivery System
- Owner-provided delivery
- Traditional Design Bid-Build
- Construction Management
- Design-Build
- Design-Build variations
- Fast Tracking
25Project Delivery System, Contract Types and
Risk.Contd
- Owners, designers, and contractors make the
decisions, provide the services, and perform the
work to deliver constructed projects. These
activities are known collectively as project
delivery. - The generic term project delivery system
describes how the participants are organized to
interact, transforming the owners project goals
and objectives into a finished facility.
26Project Delivery System, Contract Types and
Risk.Contd
- Types of Project Delivery System
- Owner-provided delivery/Force Account
- Mostly applicable to projects where the scope of
the work is within the owners range of skills,
experience, and resources. - Owners perform some or all of the design services
and construction work themselves. - E.g. simple modifications to an existing
facility, projects with limited cost or
complexity, repetitive projects.
27Project Delivery System, Contract Types and
Risk.Contd
- Traditional Design Bid Build
- For many years, DBB has been the most common
method of project delivery for public projects,
and for many private projects as well. - Design Bid-Build is effective on projects
- where the owner needs both professional design
services and construction services - where the designer does not require detailed
knowledge of the means and methods of
construction. - DBB provides the owner with a high degree of
control and the most preferred project delivery
system.
28Project Delivery System, Contract Types and
Risk.Contd
- Construction Management
- Many owners engage construction managers (CMs) to
assist in developing bid documents and overseeing
project construction. - CM
- Is a professional or a firm trained in the
management of construction processes. - Is generally interposed between the owner and
some or all of the other participants.
29Project Delivery System, Contract Types and
Risk.Contd
- Design Build
- Design-build provides the owner with a single
point of contact for project responsibilities,
eliminating the need to assist in resolving
designer-contractor disputes. - With the contractor playing a major role in
design, costs are typically defined and
maintained to a greater degree, and the
coordination of fast-track management to achieve
early completion is greatly simplified. - The design-builder makes many decisions that
owner would make under DBB, due to delegation of
greatly increased authority
30Project Delivery System, Contract Types and
Risk.Contd
- Design Build variations
- Funding Option variations
- Turnkey
- Developer Financed Projects
- Turnkey V ariations
31Project Delivery System, Contract Types and
Risk.Contd
- Funding Option variations
- Private capital and developer participation offer
private owners several variations on
design-build. - Lease-develop-operate arrangement The owner
gives a private operator a long-term lease to
use, operate, and expand an existing facility. - Public-private partnership or wrap around
Ownership of or fiduciary responsibility for a
project is assigned to a private party. That
party designs, builds, and may even own, operate
and maintain the new facility.
32Project Delivery System, Contract Types and
Risk.Contd
- Turnkey
- Turnkey adds to the design-builders
responsibilities the operation and/or maintenance
of the completed project. - Turnkey delivery has the potential for bringing a
new project on line more quickly. - Three forms of turnkey project delivery
- Design-build-operate-transfer
- Design-build-operate-maintain
- Design-build-own-operate-transfer
33Project Delivery System, Contract Types and
Risk.Contd
- Developer Financed Projects
- For highly specialized projects and
circumstances, financing from a private or public
developer or other third parties can offer
additional variations on design-build and turnkey
project delivery, each with new roles for owners,
designers, and contractors.
34Project Delivery System, Contract Types and
Risk.Contd
- Turnkey V ariations
- V ariations on turnkey add financing as a key
component. While financing arrangements are
unique for each project, developer financed
projects generally resemble one of the turnkey
delivery methods - FDBT (Finance, design, build, transfer)
- FDBOT (Finance, design, build, operate, transfer)
- FDBOOT (Finance, design, build ,own, operate,
transfer) - In each case, the transfer of the project occurs
only after the developers interests and
financial obligations have been satisfied.
35Project Delivery System, Contract Types and
Risk.Contd
- Fast Tracking
- Fast-track approach compresses the schedule by se
quencing the start of construction on underlying
project elements (e.g. foundation, basic
supporting structures) before final design is
complete for interior or adjacent elements. - Fast-tracking is not a method of delivery,
rather, its a management strategy within
delivery methods. - While often successful in achieving schedule
reductions, problems on fast-track contracts can
create a domino effect on follow-on contracts for
the project. - Fast-track is more successful on projects that
are straightforward and have a high level of
predictability
36Project Delivery System, Contract Types and
Risk.Contd
- The owner usually considers the following factors
to decide how project resources are to be
organized - Past practices, traditions, and experience
- The advice of consultants
- Funding sources and constraints
- The effective use of staff and working capital
- The interests of other project stakeholders.
37Project Delivery System, Contract Types and
Risk.Contd
- Contract Types
- Competitive Bidding(Lump Sum, Unit Price)
- Negotiated Cost-Plus(Various Types)
- Combination(CM administered)
38Project Delivery System, Contract Types and
Risk.Contd
39Project Delivery System, Contract Types and
Risk.Contd
- Lump-sum
- One price for the whole contract
- Lump sum includes costs plus overheads and
profits - Higher risk to contractor
- Price quoted is a guaranteed price as per
contract documents. - Payment based on a scheduled percentage scheme
(monthly progress claims) - The contractor is free to use means and methods
to complete the work and responsible for proper
performance - Work must be well defined at bid time.
- Low risk on the owner, Higher risk to the
contractor - Cost known at outset
40Project Delivery System, Contract Types and
Risk.Contd
- Unit Price
- Quote Rates / Prices by units
- No total final price
- Re-negotiate for rates if the quantity or work
considerably exceeds the initial target - Payment to contractor is based on the measure.
- Unbalanced bids
- Higher risk to owner
- Ideal for work where quantities can not be
accurately established before construction starts
41Project Delivery System, Contract Types and
Risk.Contd
- Require sufficient design definition to estimate
quantities of units - Contractors bid based on units of works
- Time cost risk (shared)
- Owner at risk for total quantities
- Contractor at risk for fixed unit price.
- Large quantities changes (gt15-25) can lead to
increase or decrease of unit price.
42Project Delivery System, Contract Types and
Risk.Contd
- Cost plus
- Actual cost plus a negotiated reimbursement to
cover overheads and profit. - Compromise guaranteed maximum price (GMP)
reduces risk to owner while maintain advantage of
cost plus contract. - By using this type of contract the contractor can
start work without a clearly defined project
scope, since all costs will be reimbursed and a
profit guaranteed. - In this type of contract the contractor is
reimbursed at cost with an agreed-upon fee up to
the GMP, which is essentially a cap beyond this
point the contractor is responsible for covering
any additional costs within the original project
scope
43Project Delivery System, Contract Types and
Risk.Contd
- Types of Construction Risks
Legal Risk Associated with drafting of the construction contract and documentation
Dispute Risk Without a detailed understanding of the terms and conditions of contract
Design Risk Defective and deficient drawing and specifications. Design risk is proportional to the time which is made available to produce the design documentation and sufficient time to establish the client need
44Project Delivery System, Contract Types and
Risk.Contd
Buildability Risk Ease of convertibility of the drawings and specification into a built form
Procurement risk Related with the project delivery system chosen
Biddability risk The risk associated with bidders misinterpreting what is often directly related to the quality of the tender documentation and the time which has been made available to prepare it. Were there are omissions from the specifications and drawings there is likely to be higher degree of uncertainty as to the quality and quantity of work to be undertaken, the bidder needs to make suitable allowance in his contract price
45Project Delivery System, Contract Types and
Risk.Contd
- Primary source of risk
- By those who have construction obligations
- By circumstances outside the control of
controlling parties - By compliance with statutory obligations
46Contract Management and Administration
- What do you mean by Contract Management and
Administration - Main tasks of Contract Management
- What effective contract Management accomplishes??
-
- Primary Roles and obligations of the Parties to
the Construction Contract - Types of Standard Conditions of Contract(Emphasis
on MoWUD 1994)
47Contract Management and Administration.contd
- What do you mean by Contract Management and
Administration - Contract Management
- The art and science of managing a contractual
agreement throughout the contracting process. - All activity that occurs in the contracting
process - Using procurement tools in the contract formation
process to develop specifications a contract that
effectively addresses the established contract
objectives - Within contract management there are two key
components - (Contract administration Contract compliance)
48Contract Management and Administration.contd
- Contract Administration
- Manages the contractual relationship with the
contractor in accordance with the contract
specifications, scope of work and performance
requirements. - The management of all actions, after the award of
a contract, that must be taken to assure
compliance with contract
49Contract Management and Administration.contd
- Main tasks of Contract Management
- Obtains commitments from subcontractors
- Establishes a contract administration plan
- Plans and conducts a pre performance conference
- Monitors, measure and reports progress
- Read and analyze the contract
- Evaluate organizations ability to comply
- Function as focal point for internal
support/team-members - Protect the financial interests of the
organization - Manages contract changes
- Resolves disputes
- Ensures timely delivery
50Contract Management and Administration.contd
- Manages the invoice and payment process
- Documents decisions and events
- Closes out or terminates the contract
- What effective contract Management accomplishes??
- Serves customers by providing them with a
controlled effective job and good communications - Establishes clear expectations of both parties
- Anticipates and handles disputes as they arise
- Ensures compensation for the deliverables
achieved.
51Contract Management and Administration.contd
- Primary Roles and obligations of the Parties to
the - Construction Contract
STAKEHOLDER MAJOR ROLES/OBLIGATIONS
Employer/Client/Owner Make Payment Give Possession of Site Ensure Construction information is available timely
Contractor Perform Work in a workable manner Deliver the Work on time Abide by the Contract Conditions
Engineer/Designer/Supervisor Responsible for the project design administers the contract and supervises the works
52Contract Management and Administration.contd
General Rule General Rule
Contractor is Not Liable for Contractor is Liable for
Design Workmanship
Ensuring that works are fit for the purpose for which they were intended Ensuring that materials are fit for purpose and free of defects
Ensuring that specifications, instructions and design are appropriate for the purpose for which the works are intended Ensuring that all materials and workmanship fulfill the specification, instructions and design
53Contract Management and Administration.contd
- Types of Standard Conditions of Contract(Emphasis
on MoWUD 1994) - Widely used general conditions of the
contracts include - FIDIC, General Conditions of the Contract for
Construction - Institute Of Civil Engineers (ICE), General
Conditions of the Contract for Construction - American Institute of Architects (AIA), A201-
General Conditions of the Contract for
Construction. - The Engineers Joint Contract Documents Committee
(EJCDC), C-700 - Standard General Conditions of
the Construction Contract. - NEC
- PPPAA for domestic contracts- 2006
- MoWUD 1994
54Contract Management and Administration.contd
- Ministry of Works and Urban Development (MoWUD)
- DECEMBER 1994
55Contract Management and Administration.contd
- MoWUD GCC Categorizations
- Definitions and Interpretations Clause 1
- Engineer and Engineers Representative Cl 2
- Assignment and Subletting Cl 3-4
- Contract Documents Cl 5-7
- General Obligations Cl 8-33
- Labour Cl 34-35
- Materials and Workmanship and Tests Cl 36-40
- Commencement Time and Delays Cl 41-48
- Maintenance and Defects Cl 49-50
56Contract Management and Administration.contd
- Alterations, Additions, and Omissions Cl 51-54
- Measurement Cl 55-57
- Provisional Sums Cl 58
- Nominated Subcontractor Cl 59
- Certificates and Payments Cl 60-62
- Remedies and Powers Cl 63-64
- Special Risks Cl 65
- Frustration Cl 66
- Settlement of Disputes Cl 67
- Notices Cl 68
- Default of Employer Cl 69
57Contract Management and Administration.contd
- Changes in Costs and Legislation Cl 70
- Other Matters Cl 71-75
58Contract Management and Administration.contd
- CoPA, Sub-Clause 5 Priority of Contract
Document - The Contract Agreement
- Appendix to contract and Addendum (if any)
- Condition of particular Application part II
- Standard condition of contract for construction
of Civil Works projects. (MoWUD Dec, 1994 part) - Technical Specification special provision
- The standard specification (if any)
- Other documents, as listed in the Appendix to
contract.
59Contract Management and Administration.contd
- Sub-Clause 8 Contractor General Obligations
- Contractor to execute and maintain the Works and
provide all labour (including the supervision),
materials, Plant/machineries, etc subject to
the provision of the contract the necessity of
which is specified in the contract or reasonably
inferred from the contract (c25) - Full Responsibility for the adequacy, stability,
and safety of all site operations and methods of
construction - Contractor Shall inform the employer/engineer of
any error, omission, fault, other defects in
the design of or specification which are
discovered when reviewing the contract documents
or in the process of execution of the Works
60Contract Management and Administration.contd
- Sub-Clause 10 Performance Bond
- Letter of acceptance ? within 30 days performance
bond in the sum of 10 of CP - Reduced to 5 at the completion of works
- for the due proper performance of the contract
and observance of all provisions, conditions,
stipulations - Bond shall not be released until the employer has
given a certificate in writing that all
outstanding matters in dispute b/n the employer
the contractor have been settled - CoPA Without limitation to the provisions of the
preceding paragraph, whenever the Engineer
determines an addition to the Contract Price as a
result of a change in cost and /or legislation or
as a result of a variation amounting to not more
than 25 percent of the portion of the Contract
Price payable, the Contractor, at the Engineer's
written request, shall promptly increase the
value of the performance security by an equal
percentage
61Contract Management and Administration.contd
- Sub-Clause 11 Site Inspection
- Contractor deemed to inspected examined the
site its surroundings to have satisfied
himself as to all - matters necessary for the due performance of the
contract including, risks, contingencies, all
other circumstances which may influence his
tender - Form nature of the site
- Geological, hydrological subsurface climatic
conditions - Details, locations levels of all existing
projected utilities services / above and below
ground/ - Nature carrying capacities of existing
projected roads - The extent nature of the work, materials,
labour, and all things necessary for the
completion of the works, etc
62Contract Management and Administration.contd
- CoPA Whenever an Opinion is made available to
the Contractor in respect of any data provided to
the Contractor by Employer, the Contractor shall
be solely responsible for ascertaining the
correctness of such Opinion and the Employer
shall in no manner be liable in this regard. - In particular and without limiting the generality
of the aforesaid, the Contractor shall not rely
upon such opinion or interpretation for any claim
with respect to additional time or cost under the
Contract
63Contract Management and Administration.contd
- Sub-Clause 12 Sufficiency of Tender
- Contractor deemed to have satisfied himself as
to - the correctness sufficiency of his tenders for
the works, of the rates prices stated in the
priced BoQ - Rates prices shall cover all the obligations
under the contract, all matters and things
necessary for the proper execution maintenance
of the works - but if the contractor encounters,
- Physical conditions other than climatic
conditions - Artificial obstructions
- which conditions and obstructions could not have
been reasonably foreseen by an experienced
contractor (in the opinion of the eng)
64Contract Management and Administration.contd
- Engineer to certify and employer to pay the
additional cost to which the contractor incurred
by the reason of such conditions including the
proper reasonable cost of complying with any
instruction of the engineer proper reasonable
measures to be taken - Sub-Clause 13 Work to be to the satisfaction of
the Engineer - save in so far as it is legally physically
impossible - Contractor to execute maintain the works in
strict accordance with the contract to the
satisfaction of the engineer - Contractor to take instructions only from the
engineer (channels of communication) Core of
contract management
65Contract Management and Administration.contd
- Contractor to comply with adhere strictly to
the engineers instructions directions on any
matters whether mentioned in the contract or not,
touching or concerning the works - Sub-Clause 14 Program to be Furnished
- Within 15 days of letter of acceptance
- To be revised at intervals of three months
??clause 46, engineer to notify the contractor if
rate of progress is to slow to ensure timely
completion of the works - i.e. to expedite progress so as to complete the
works
66Contract Management and Administration.contd
- Sub-Clause 20 Care of the Works
- Contractor responsibility for care of works
from commencement of works till completion of
works - Responsibility passed to the employer from
completion of works till issue of maintenance
certificate - save and except the EXEMPTED Risks defined
- Any damage/loss or injury from excepted risks ?
cont may repair make good at the expense of the
employer - Exempted risks war, hostilities, invasion, act
of foreign enemies, rebellion, revolution,
military power, civil war, riot, disorder (not
contractors), use or occupation by the employer,
cause due to engineers design, ionizing
radiations, pressure waves --- or other forces of
nature which an experienced cont could not
foresee
67Contract Management and Administration.contd
- Sub-Clause 40 Suspension of works
- Instruction to suspend any work/part of it
?contractor to suspend the progress of the work - Such suspension will be contractors risk if
- provided in the contract or by the default of the
contractor - for the proper execution of the works/ safety
reasons (not arisen from any act/default of the
Eng/Emp not exempted risks) - Suspension lasting gt90 days (no order to resume
works) if not contractors risk ?contractor to
require permission within 28days
68Contract Management and Administration.contd
- no permission ?contractor may treat the
suspension as - Omission of the work variation as per clause 51
- abandonment of the contract by employer if it
affects the whole of the works (clause 69) ? 28
days notice mandatory
69Contract Management and Administration.contd
- Sub-Clause 44 Extension of Time for Completion
- (amount of) extra or additional work of any kind
- any cause of delay referred to in the conditions
- exceptional adverse climatic conditions
- other special circumstances of any kind
whatsoever which may occur other than through a
default of the contractor - fairly entitle cont an EOT for completion of
works - NB (a) and (d) require notification within 28
days or as soon as practicable plus full
detailed particulars - any cause of delay ? if contractor suffers
delay and/or incurs cost ... ?Ex Sub clause
6(4) delays of drawings, 42(1) possession of
the site, etc
70Contract Management and Administration.contd
-
- CoPA 44 "Neither rains falling within the rainy
seasons as occurs in the country, nor floods
caused by such rains shall be deemed exceptional
weather conditions such as may fairly entitle the
Contractor to an extension of time for the
completion of the Work. - Similarly in respect of the provision of Clause
12 of these Conditions, neither such rains nor
such floods shall be deemed to be adverse
physical conditions"
71Contract Management and Administration.contd
- Sub-Clause 48 Certification of Completion of
Works - Substantially completed project (passing
satisfactory tests)? notice by Contractor to
Engineer (accompanied by an undertaking to finish
any outstanding works) ? Engineer to issue the
certificate or to give instructions specifying
works to be done (within 21 days) - If Engineer fails to certify within 21 days,
default of the Employer sub clause 69(1)b
?Employer refusing any required approval to issue
any such certificate
72Contract Management and Administration.contd
- Sub-Clause 51 Alterations, additions and
omission of works - Increase/ decrease in qty of any work included in
the contract - Omissions of any such work
- Changes in the character/quantity/kind of any
such work - Change the levels, positions, lines dimensions
of any part of the works - Execution of additional works of any kind
necessary for the completion of works - No such variations shall invalidate/vitiate the
contract - Value of variations to be taken into account in
ascertaining the amount of the contract price - Order to be in writing if verbally, to be
confirmed in writing
73Contract Management and Administration.contd
- Art. 3031 of the Civil Code Alterations
required by - Client. - 1. Rights of client
- The client may demand that alterations be made in
the work as originally planned where such
alternations can technically be made and are not
such as to impair the solidity of the work. -
- Art. 3032. 2. Effect
- The client may require a reduction in the price
as originally agreed where the alterations
required by him reduce the expenses of the
contractor. - The contractor may require an increase in the
price and his remuneration as originally agreed,
where the alterations required by the client
increase his expenses, work or liability.
74Contract Management and Administration.contd
- Art. 3033. 3. Contractor refusing alteration
- The contractor may refuse the alterations
required by the client where such alterations
affect plans, schemes or other documents on which
the parties had agreed. - The contractor may also refuse the alterations
where they are of such a nature or importance
that they constitute a work absolutely different
to the agreed work. - The work shall be deemed to be absolutely
different to the agreed work where it implies an
alteration exceeding by twenty per cent of the
value at which the original work was or could
have been estimated.
75Contract Management and Administration.contd
- Sub-Clause 52 Valuation of variation
- Rates prices contained in the contract to be
used - if not appropriate, new rate to be agreed upon
b/n the cont and the eng ?failing to agree, by
the eng (reasonable proper rates/prices having
regard to circumstances) - notice to be delivered ASAP by cont to claim
extra payment or a varied rate/price ?otherwise
no inc/dec or adjustment be - notice of intention to vary a rate/price ? by the
eng -
76Contract Management and Administration.contd
- Intention by the
- engineer of the
- variation
Cont to give a varied rate to the engineer
Engineer to give his comments on the varied rate
lt30days
lt15days
Engineer may forward the rate for approval by
MoWUD CoPAEmployer
77Contract Management and Administration.contd
- Sub-Clause 52(3) (5) CP Adjustment/Claims
- Variations exceeding 10 of CP
- On certified completion of the whole of the works
? if the reduction/increase of the CP is greater
that 10 of CP ? the amount of the CP shall be
adjusted considering all material related
factors including the contractors site/general
overhead cost of the contract!! - Arising from the aggregate effect of all
variation orders all adjustments upon
remeasurement of estimated quantities - Claims
- Contractor to submit all claims for additional
payment of all extra/additional order once
every month with particulars - Engineer to authorize payments notwithstanding
the conts failure to comply with condition.
78Contract Management and Administration.contd
- Sub-Clause 60 Monthly Payment
- Every month to be submitted, comprising of
- quantities value of executed permanent works
- value of materials on site intended to form part
of the permanent work together with supporting
invoices - value of temporary works (if included in the
BoQ) - amounts reflecting any changes in cost (pursuant
to clause 70) - amounts approved in respect of day works
- Employer to pay within 30 days of the date of
eng certificate - Subject to 10 (5) retention to all the above
payments
79Contract Management and Administration.contd
- Eng may correct/modify/withhold any approved
payments from latter PCs for mistakes made on
PCs, works not carried out to his satisfaction,
damages on materials/plants etc
80Contract Management and Administration.contd
- Sub-Clause 63 Default of the Contractor
- If the contractor becomes bankrupt, assigns the
contract without the consent of the employer,
goes into liquidation, etc OR - If the engineer certifies to the employer that
the cont (in his opinion) - Abandoned the contract
- Failed to commence works without reasonable
excuse or suspended the progress of works for 28
days (after notice) - Failed to remove condemned materials for 28 days
(after notice) - Is not executing the works in accordance with the
contract or is persistently flagrantly
neglecting to carryout his obligations under the
contract -
81Contract Management and Administration.contd
- Has sublet any part of the contract to the
detriment of good workmanship or in defiance of
the engineers instruction ??? default of the
contractor ? breach of the contract..SEE
PORCEDUR FOR DECLARING DEFAULT
82Contract Management and Administration.contd
-
- enter upon the site works
- expels contractor from site
- may himself complete or employ other cont
- may use temporary works, plants to complete
- May sell any of materials, plants, temporary
- works ? applying proceedings of sale, to the
- satisfaction of any such sums due to him
- Employer to give 14 days
- written notice
Employer
- Eng to fix, determine certify
- Amounts reasonably earned or
- accrue to the cont
- value of unused or partially used
- materials, plants, or temporary works
- If the amount exceeds the sum payable
- to the cont ? cont to pay to the employer or
- a debt by the cont to the employer shall be
- recoverable accordingly!!
- If not ?? contractor entitled for the balance!!
- Eng to ascertain certify payment
- cost of execution maintenance
- Damage for delay in completion
- all expenses incurred by the employer
83Contract Management and Administration.contd
- Employer entry expulsion ? contractor not
entitled/employer not liable to payment (any
Money) on account of the contract, until the
expiration of the period of Maintenance!! ?
withholding the money due to the con if any!
84Contract Management and Administration.contd
- Sub-Clause 69 Default of the Employer
- Contractor entitled to terminate his employment
under the contract in the events of the employer
(giving 30 days prior notice) - Fails to pay the contractor the amount due under
any certificate of the engineer within 30 days
after the same shall have become due. - Interferes with or obstructing or refuses any
required approval to issue payment certificate,
completion certificate, work certificate,
maintenance certificate - Becomes bankrupt or goes in to liquidation
- Gives a formal notice to the contractor that for
unforeseen reasons due to economic dislocation,
it is impossible to continue to meet his
contractual obligations and for convenience???
85Contract Management and Administration.contd
- Sub-Clause 71 Warranties in Respect of Defects
- Unless otherwise provided, the Contractor shall
be LIABLE to the Employer for any defects of the
construction of the works DURING TEN YEARS FROM
THE DAY ON WHICH THE EMPLOYER HAS ENTERED INTO
THE POSSESSION OF THE WORKS
86Contract Management and Administration.contd
- Communications(Meetings in Construction)
- Pre-construction Meetings
- Procedural Meeting
- Site Mobilization Meeting
- Utility Coordination Meeting
- Authorities Having Jurisdiction (AHJs)
- Progress Meetings
- Contractor/Subcontractor Meetings
- Pre installation Meetings
- SAFETY Meetings
- Other Meetings
87Contract Management and Administration.contd
- Closeout Meeting
- Pre default meeting
- Preconstruction meetings are important for-
- Introducing the project team,
- Establishing the ground rules for communication,
and explaining the administrative process. In
many cases, a single meeting is all that is
required however, large, complex, or multiprime
contractor projects may require more than one
meeting. - A procedural meeting
- may cover administrative procedures, such as
communication, submittals, testing, and
inspection. A second mobilization meeting may
address use of the site
88Contract Management and Administration.contd
- Site Mobilization Meeting
- Access to the site, such as construction entrance
and egress locations, including access roads,
parking restrictions, and security. - Environmental controls such as silt fences,
biobags, inlet protection, temporary seeding and
mulching, and oil booms and containment systems
when working over or near water. - Use of site and existing facilities by contractor
and owner, including access to buildings or
areas, use of elevators, and maintenance of fire
exits. For public infrastructure projects, this
might involve traffic control, detours, and
barriers.
89Contract Management and Administration.contd
- Identification of benchmarks and data, including
survey and layout of work. - Occupancy and use by owner, tenants, and public
during the construction stage, including partial
use and occupancy of completed work, and the
related coordination of insurance requirements - Site mobilization meeting is a tool for laying
effective management of site by addressing pre
construction activities required by participants
of the project. Typically held at the site, this
meeting concerns issues about site use.
90Contract Management and Administration.contd
- Utility Coordination Meeting
- On a projects where significant utility
relocation work is required, it is prudent to
have a utility coordination meeting. - This meeting is usually held shortly after the
preconstruction meeting. Participants may include
representatives from the utility providers
serving the project. - Identifying the best time for each utility
provider to perform their work - Identifying the interface with other utility
providers for work that must occur concurrently - Establishing how long each utility providers
work will take -
91Contract Management and Administration.contd
- Identifying the primary contact person
- Establishing how much notification (lead time)
each utility provider will require to mobilize - Identifying whether there are related costs that
have not been identified - Determining or confirming who will do the
locating work for each utility provider - Identifying special inspection requirements.
- Regardless of the project extent, a utility
coordination meeting might be required by utility
providers as a precondition of future connection
to utilities.
92Contract Management and Administration.contd
- Pre-installation Meeting
- Ascertain access to the work
- Review conditions of proper installation and
environmental conditions - Identify conditions detrimental to the
installation - Review preparation procedures, including
protection of adjacent work - Review coordination with other work such as
substrates, connections, transitions, and
existing and surrounding conditions - Evaluate delivery schedule and progress schedule
93Contract Management and Administration.contd
- Safety Meeting
- Several different types of safety meetings may
occur on a project. Contractors hold weekly
safety meetings, at which the supervisors and
workers gather before start of shift and discuss
a selected safety topic. - Sometimes a contractor invites OSHA Consultative
Services to visit the project and do a safety
consultation.
94Contract Management and Administration.contd
- Closeout Meeting
- The closeout meeting is used to review
requirements for the completion of the contract
and to obtain submittal of the necessary final
documents. Separate meetings may be required for
substantial completion, final completion, and
warranty reviews. - Many of the closeout documents are prepared
during construction, even though their submission
is not required until the project is nearing
completion. These documents might include record
documents, OM data, manufacturer certification
of installations, and interim inspections and
testing.
95Contract Management and Administration.contd
- Completion time for correcting defective work
- Inspections by AHJs
- Certificate of use or occupancy and transfer of
insurance responsibilities - Partial release of retainage
- Final cleaning
- Preparation for final inspection
- Closeout submittals
- Record documents
96Contract Management and Administration.contd
- Pre-default Meeting
- The performance bond provides the most important
protection for the owner by guaranteeing that if
the contractor defaults, the surety will either
complete the contract in accordance with its
terms or provide sufficient funds, up to the
penal amount of the bond, to fund such completion.
97Claims Management and Dispute Resolution
- Typical Claims Against the Owner
- Typical Claims Against the Contractor
- Likely source of construction Delay and
Disruption - Claims Analysis
- Claims Prevention Suggestions
- Dispute Resolution Mechanisms
98Claims and Dispute Resolution.contd
- Typical Claims Against the Owner
- Poor project planning
- Scope changes
- Constructive change orders
- Errors and omissions
- Contract accelerations and stoppages
- Site access or availability
- Other construction interference and delays
- Strikes and acts of God
99Claims and Dispute Resolution.contd
- Typical Claims Against the Contractor
- Late completion - liquidated damages
- Out of specification materials
- Defective work
- Property damage
100Claims and Dispute Resolution.contd
- Likely Sources of Construction Delay and
Disruption
Excusable/Neutral Delay Non-Excusable Delay
Delay or deferment in granting Possession of Site Late Mobilization Commencement
Unforeseeable ground conditions Shortage of Resources
Instructions (e.g. additional work, opening up for inspection and testing) Delayed Contractor s design (e.g. temporary works)
Variations or changes to work scope Poor site co-ordination
Increase in Quantities Price Fluctuation
Inaccurate quantities in contract BOQ Delayed Geo-technical investigation by the Contractor
101Claims and Dispute Resolution.contd
Excusable/Neutral Delay Non-Excusable Delay
Late/Poor design information by the Engineer Re-work and maintenance works
Suspension of Works by the Engineer/Employer Provision of Engineers Facilities
Delay caused by statutory bodies stakeholders Improper Mgt. of Statutory obligations Traffic Safety Mgt
Exceptionally adverse weather conditions Lack of Early Warning for delaying events
Delay caused by Employer or his representatives Re-work and maintenance works
Civil commotion Industrial action(e.g. lock outs)
102Claims and Dispute Resolution.contd
- Claims Analysis
- Brief of the case
- Owners position
- Contractors position
- Analysis and evaluation
- Recomm