ILC Baseline Schedule, Milestones, and Decision points - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

ILC Baseline Schedule, Milestones, and Decision points

Description:

ILC Baseline Schedule, Milestones, and Decision points Tom Himel Preface There is a large amount of ongoing R&D. I will concentrate on those aspects which have major ... – PowerPoint PPT presentation

Number of Views:101
Avg rating:3.0/5.0
Slides: 34
Provided by: Geral81
Category:

less

Transcript and Presenter's Notes

Title: ILC Baseline Schedule, Milestones, and Decision points


1
ILC Baseline Schedule, Milestones, and Decision
points
  • Tom Himel

2
Preface
  • There is a large amount of ongoing RD.
  • I will concentrate on those aspects which have
    major effects on the ILC design.
  • Note that ILC RD, engineering, and
    industrialization are all going on in parallel.
  • Ill describe each RD project with its goals,
    explain why it is useful, give its schedule, and
    some results.
  • We know many pieces of the schedule, but the
    fully integrated schedule will be developed
    during the EDR.

3
Contents
  • Preview of Overall Schedule
  • Major risk mitigation RD efforts
  • Cavity gradient
  • Cryomodule at full gradient
  • Linac string test
  • E cloud, DR kicker
  • BDS system test
  • Design for High Availability
  • Cost reduction RD
  • High power RF
  • Construction Schedule and overview

4
Technically Driven Timeline
2006
2010
2014
2018
Engineer Design
Construction ? Startup
BCD
Begin Const
End Const
RDR
EDR
Detector Install
Detector Construct
Siting Plan being Developed
Site Select
Site Prep
Pre-Operations
All regions 5 yrs
R D -- Industrialization
System Tests XFEL
Gradient
Cryomodule Full Production
August
e-Cloud
5
Cavity Gradient Goal
  • Current status Nine 9 cell cavities have been
    produced with gradients gt 35 MeV/m. Not
    reproducible and needs several attempts at final
    processing.
  • Goal After a viable cavity process has been
    determined through a series of preparations and
    vertical tests on a significant number of
    cavities, achieve 35 MV/m at Q0 1010 in a
    sufficiently large final sample (greater than 30)
    of nine-cell cavities in the low power vertical
    dewar testing in a production-like operation e.g.
    all cavities get the same treatment.
  • The yield for the number of successful cavities
    of the final production batch should be larger
    than 80 in the first test. After re-processing
    the 20 underperforming cavities the yield
    should go up to 95. This is consistent with the
    assumption in the RDR costing exercise.

6
Cavity Gradient Plan
  • There are three main activities which are closely
    coupled and partially progressing in parallel
  • This is needed to separate cavity preparation and
    production issues
  • 1. Single-cell RD
  • Establishing more reliable final preparation
    parameters.
  • Focus on the final rinse after EP before HPR.
  • E.g. Ultrasound, Short EP (or HF rinse), H2O2
  • 2. Tight-loop (Finish in 2008)
  • International multi-cell cavity exchange
  • 1st round
  • Comparison of regional differences in preparation
    and testing
  • 2nd round
  • Use single-cell results and implement on 9-cell
    cavities.
  • 3. Production-like effort (Continues into 2010)
  • Monitor ongoing productions
  • Esp. XFEL preparation
  • Use qualified and new vendors
  • Use improved preparation process for an ultimate
    batch of cavities
  • A lot of data will be (is already) available by
    the time of the EDR writing

7
Cavity Gradient Cost/Benefit
  • Optimistic scenario with final batch tight-loop
  • Costs 36 MILCU for the RD
  • Gives highest confidence about the gradient
    distribution
  • This needs to be compared to
  • A reduction of the average gradient for the ILC
    from design of 31.5 to 28
  • 600 MILCU

8
Cavity Gradient Results
2006
2005
  • KEK single cell results
  • 2005 just learning
  • 2006 standard recipe
  • 2007 add final 3 µm fresh acid EP
  • Note multi-cells are harder than singles

2007
9
Module Test Goal
  • Intermediate goal
  • Achieve 31.5 MV/m average operational
    accelerating gradient in a single cryomodule as a
    proof-of-principle. In case of cavities
    performing below the average, this could be
    achieved by tweaking the RF distribution
    accordingly.
  • Auxiliary systems like fast tuners should all
    work.
  • Final goal
  • Achieve gt 31.5 MeV/m operational gradient in 3
    cryomodules.
  • The cavities accepted in the low power test
    should achieve 35 MV/m at Q0 1010 with a yield
    as described above (80 after first test, 95
    after re-preparation).
  • It does not need to be the final cryomodule
    design

10
Module Test Plan
  • Enough good cavities for the cryomodules are
    expected from the cavity gradient program.
    Module assembly plans
  • DESY
  • 2007 M7 Being tested now. See next slide
  • 2007 M8 Probably no slow-down to select best
    cavities
  • 2008 M10 could select best cavities from
    several regions
  • US funding problems have us behind schedule
    below
  • 2007 Assemble a kit of parts from DESY to get
    first assembly experience at FNAL
  • 2008 assemble 2 cryomodules from US produced
    parts. Second may be made by selecting the
    best available cavities.
  • 2009 build 2 more cryomodules
  • Japan
  • 2009-10 Build, test, 3 cryomodules

11
Module Test Results
DESY
12
String Test Goal
  • Build 1 RF unit (3 cryomodules 1 Klystron) to
    fully check
  • What gradient spread can be handled by LLRF
    system. This test should be done with and without
    beam loading.
  • For heating due to high frequency HOMs.
  • Amplitude and phase stability.
  • Static and dynamic heat loads.
  • To partially check
  • Reliability
  • Dark current
  • for degradation or other weaknesses
  • The ILC cryomodule is enough different than that
    of the TTF that a new system test is warranted.

13
String Test Plan
  • Use cryomodules built for module tests and for
    industrialization.
  • Do more tests at TTF/FLASH
  • XFEL will both be a string test and provide
    costing, contracting and construction
    information.
  • Build 1 RF unit at KEK and 1 at Fermilab.
  • Do this in a phased manner, starting with smaller
    tests with modules that dont meet specs.
  • Full to spec RF unit should work before 1 of
    the final industrial production of ILC
    cryomodules is complete. (2014)
  • There will be a larger second phase string test
    to verify quality of the modules going into the
    ILC.

14
String test Cost/Benefit
  • The risk if we dont do the string test is that
    we will build 1.5 BILCU of cryomodules and then
    discover a design flaw.
  • Fixing them all could take years and easily cost
    more than 20 of the original cost.
  • If there is a medium risk (25) of this type of
    error then the riskcost 75 MILCU plus the loss
    of a few years in schedule.
  • Note the risk would be high 50-100 if not for
    the TTF.
  • The planned string tests will cost over 50 MILCU.

15
Schedule in Graphical Form
2009
2012
2015
2018
Construction Schedule
Cryomodule Production
RF System Tests
16
E cloud Goal
  • Ensure the e- cloud wont blow up the e beam
    emittance.
  • Do simulations (cheap)
  • Test vacuum pipe coatings, grooved chambers, and
    clearing electrodes effect on e- cloud buildup
  • Do above in ILC style wigglers with low emittance
    beam to minimize the extrapolation to the ILC.

17
E cloud Plan
  • Grooved chambers and special coatings are being
    tested in PEP-II and KEK-B straight sections.
  • Lots of simulations have been done and
    bench-marked against existing accelerators.
  • Still, the long extrapolation leaves us nervous.
  • Plans are being developed to test special
    chambers in wigglers in CESR and KEK-B.
  • The funding is not yet assured for these more
    definitive tests.
  • Schedule is for results in 2009

18
E Cloud Cost/Benefit
  • If we dont do the RD, there is a high (50)
    risk that we have to build a second e DR at a
    cost of 200 MILCU. Costrisk 100 MILCU
  • The first 2 types of RD cost only a few million.
  • The costs of the KEK-B and CESR tests are
    difficult to evaluate as they involve the
    dedicated use of the whole ring and it is unclear
    which costs should be accounted to the ILC. The
    scale is 10 MILCU.

19
E Cloud Results
SLAC
20
BDS System Test Goal
  • Build ATF2, a scaled BDS prototype at KEK to
    test
  • Optics design including never before done local
    chromatic correction
  • Keeping a beam small (35 nm) and stable to a few
    nm for days at a time
  • Laser wires
  • Intra-train feedback
  • BPMs
  • High availability power supplies
  • Tuning algorithms

21
BDS System Test Plan
  • ATF2 is already under construction by a
    multi-regional collaboration.
  • Will be commissioned in 2009 with optics tests
    done in 2010

22
BDS System Test Cost/Benefit
  • Cost is 5 MILCU
  • Ameliorates a medium (25) risk of having to do a
    major BDS redesign that could lengthen the BDS
    and cost 200 MILCU extra
  • Would be a bargain at twice the price

23
High Power RF Goals
  • The baseline HPRF design is mature and has very
    little risk.
  • The RD concentrates on cost reduction
  • A Marx modulator to replace the bouncer modulator
  • Modified RF distribution system
  • Sheet-beam klystron to replace multi-beam
    klystron
  • If all are used, the HPRF cost is cut in half.

24
Marx Modulator Results
SLAC
25
Marx Modulator Results
100kV Output 1400 µsec, Leveled
SLAC
Long term test planned in coming year.
26
Modified RF Distribution System Plans
SLAC
27
Sheet Beam Klystron Plan
  • Build beam tester and klystron by Summer 2008
  • The beam tester will validate 3-D beam transport
    simulations and allow a more rapid turnaround for
    electron gun changes
  • The klystron will be developed in parallel with
    little feedback from the beam tester. A rebuild
    of the klystron can incorporate design changes
    motivated by the beam tester

28
Sheet Beam Klystron Plan
29
Americas Site Plan
30
Preconstruction Plan for Fermilab
Central Area fits inside the Fermilab boundary
Boundary of Fermilab
Site Characterization of the Central Area can be
done
5.5 km
5.5 km
31
Preparing for 2012 Construction Start
2007
2010
2012
Phase 1
Phase 2
Phase 3
32
Civil Construction Timeline
33
Technically Driven Timeline (reprise)
2006
2010
2014
2018
Engineer Design
Construction ? Startup
BCD
Begin Const
End Const
RDR
EDR
Detector Install
Detector Construct
Siting Plan being Developed
Site Select
Site Prep
Pre-Operations
All regions 5 yrs
R D -- Industrialization
System Tests XFEL
Gradient
Cryomodule Full Production
August
e-Cloud
Write a Comment
User Comments (0)
About PowerShow.com