Title: ILC Baseline Schedule, Milestones, and Decision points
1ILC Baseline Schedule, Milestones, and Decision
points
2Preface
- There is a large amount of ongoing RD.
- I will concentrate on those aspects which have
major effects on the ILC design. - Note that ILC RD, engineering, and
industrialization are all going on in parallel. - Ill describe each RD project with its goals,
explain why it is useful, give its schedule, and
some results. - We know many pieces of the schedule, but the
fully integrated schedule will be developed
during the EDR.
3Contents
- Preview of Overall Schedule
- Major risk mitigation RD efforts
- Cavity gradient
- Cryomodule at full gradient
- Linac string test
- E cloud, DR kicker
- BDS system test
- Design for High Availability
- Cost reduction RD
- High power RF
- Construction Schedule and overview
4Technically Driven Timeline
2006
2010
2014
2018
Engineer Design
Construction ? Startup
BCD
Begin Const
End Const
RDR
EDR
Detector Install
Detector Construct
Siting Plan being Developed
Site Select
Site Prep
Pre-Operations
All regions 5 yrs
R D -- Industrialization
System Tests XFEL
Gradient
Cryomodule Full Production
August
e-Cloud
5Cavity Gradient Goal
- Current status Nine 9 cell cavities have been
produced with gradients gt 35 MeV/m. Not
reproducible and needs several attempts at final
processing. - Goal After a viable cavity process has been
determined through a series of preparations and
vertical tests on a significant number of
cavities, achieve 35 MV/m at Q0 1010 in a
sufficiently large final sample (greater than 30)
of nine-cell cavities in the low power vertical
dewar testing in a production-like operation e.g.
all cavities get the same treatment. - The yield for the number of successful cavities
of the final production batch should be larger
than 80 in the first test. After re-processing
the 20 underperforming cavities the yield
should go up to 95. This is consistent with the
assumption in the RDR costing exercise.
6Cavity Gradient Plan
- There are three main activities which are closely
coupled and partially progressing in parallel - This is needed to separate cavity preparation and
production issues - 1. Single-cell RD
- Establishing more reliable final preparation
parameters. - Focus on the final rinse after EP before HPR.
- E.g. Ultrasound, Short EP (or HF rinse), H2O2
- 2. Tight-loop (Finish in 2008)
- International multi-cell cavity exchange
- 1st round
- Comparison of regional differences in preparation
and testing - 2nd round
- Use single-cell results and implement on 9-cell
cavities. - 3. Production-like effort (Continues into 2010)
- Monitor ongoing productions
- Esp. XFEL preparation
- Use qualified and new vendors
- Use improved preparation process for an ultimate
batch of cavities - A lot of data will be (is already) available by
the time of the EDR writing
7Cavity Gradient Cost/Benefit
- Optimistic scenario with final batch tight-loop
- Costs 36 MILCU for the RD
- Gives highest confidence about the gradient
distribution - This needs to be compared to
- A reduction of the average gradient for the ILC
from design of 31.5 to 28 - 600 MILCU
8Cavity Gradient Results
2006
2005
- KEK single cell results
- 2005 just learning
- 2006 standard recipe
- 2007 add final 3 µm fresh acid EP
- Note multi-cells are harder than singles
2007
9Module Test Goal
- Intermediate goal
- Achieve 31.5 MV/m average operational
accelerating gradient in a single cryomodule as a
proof-of-principle. In case of cavities
performing below the average, this could be
achieved by tweaking the RF distribution
accordingly. - Auxiliary systems like fast tuners should all
work. - Final goal
- Achieve gt 31.5 MeV/m operational gradient in 3
cryomodules. - The cavities accepted in the low power test
should achieve 35 MV/m at Q0 1010 with a yield
as described above (80 after first test, 95
after re-preparation). - It does not need to be the final cryomodule
design
10Module Test Plan
- Enough good cavities for the cryomodules are
expected from the cavity gradient program.
Module assembly plans - DESY
- 2007 M7 Being tested now. See next slide
- 2007 M8 Probably no slow-down to select best
cavities - 2008 M10 could select best cavities from
several regions - US funding problems have us behind schedule
below - 2007 Assemble a kit of parts from DESY to get
first assembly experience at FNAL - 2008 assemble 2 cryomodules from US produced
parts. Second may be made by selecting the
best available cavities. - 2009 build 2 more cryomodules
- Japan
- 2009-10 Build, test, 3 cryomodules
11Module Test Results
DESY
12String Test Goal
- Build 1 RF unit (3 cryomodules 1 Klystron) to
fully check - What gradient spread can be handled by LLRF
system. This test should be done with and without
beam loading. - For heating due to high frequency HOMs.
- Amplitude and phase stability.
- Static and dynamic heat loads.
- To partially check
- Reliability
- Dark current
- for degradation or other weaknesses
- The ILC cryomodule is enough different than that
of the TTF that a new system test is warranted.
13String Test Plan
- Use cryomodules built for module tests and for
industrialization. - Do more tests at TTF/FLASH
- XFEL will both be a string test and provide
costing, contracting and construction
information. - Build 1 RF unit at KEK and 1 at Fermilab.
- Do this in a phased manner, starting with smaller
tests with modules that dont meet specs. - Full to spec RF unit should work before 1 of
the final industrial production of ILC
cryomodules is complete. (2014) - There will be a larger second phase string test
to verify quality of the modules going into the
ILC.
14String test Cost/Benefit
- The risk if we dont do the string test is that
we will build 1.5 BILCU of cryomodules and then
discover a design flaw. - Fixing them all could take years and easily cost
more than 20 of the original cost. - If there is a medium risk (25) of this type of
error then the riskcost 75 MILCU plus the loss
of a few years in schedule. - Note the risk would be high 50-100 if not for
the TTF. - The planned string tests will cost over 50 MILCU.
15Schedule in Graphical Form
2009
2012
2015
2018
Construction Schedule
Cryomodule Production
RF System Tests
16E cloud Goal
- Ensure the e- cloud wont blow up the e beam
emittance. - Do simulations (cheap)
- Test vacuum pipe coatings, grooved chambers, and
clearing electrodes effect on e- cloud buildup - Do above in ILC style wigglers with low emittance
beam to minimize the extrapolation to the ILC.
17E cloud Plan
- Grooved chambers and special coatings are being
tested in PEP-II and KEK-B straight sections. - Lots of simulations have been done and
bench-marked against existing accelerators. - Still, the long extrapolation leaves us nervous.
- Plans are being developed to test special
chambers in wigglers in CESR and KEK-B. - The funding is not yet assured for these more
definitive tests. - Schedule is for results in 2009
18E Cloud Cost/Benefit
- If we dont do the RD, there is a high (50)
risk that we have to build a second e DR at a
cost of 200 MILCU. Costrisk 100 MILCU - The first 2 types of RD cost only a few million.
- The costs of the KEK-B and CESR tests are
difficult to evaluate as they involve the
dedicated use of the whole ring and it is unclear
which costs should be accounted to the ILC. The
scale is 10 MILCU.
19E Cloud Results
SLAC
20BDS System Test Goal
- Build ATF2, a scaled BDS prototype at KEK to
test - Optics design including never before done local
chromatic correction - Keeping a beam small (35 nm) and stable to a few
nm for days at a time - Laser wires
- Intra-train feedback
- BPMs
- High availability power supplies
- Tuning algorithms
21BDS System Test Plan
- ATF2 is already under construction by a
multi-regional collaboration. - Will be commissioned in 2009 with optics tests
done in 2010
22BDS System Test Cost/Benefit
- Cost is 5 MILCU
- Ameliorates a medium (25) risk of having to do a
major BDS redesign that could lengthen the BDS
and cost 200 MILCU extra - Would be a bargain at twice the price
23High Power RF Goals
- The baseline HPRF design is mature and has very
little risk. - The RD concentrates on cost reduction
- A Marx modulator to replace the bouncer modulator
- Modified RF distribution system
- Sheet-beam klystron to replace multi-beam
klystron - If all are used, the HPRF cost is cut in half.
24Marx Modulator Results
SLAC
25Marx Modulator Results
100kV Output 1400 µsec, Leveled
SLAC
Long term test planned in coming year.
26Modified RF Distribution System Plans
SLAC
27Sheet Beam Klystron Plan
- Build beam tester and klystron by Summer 2008
- The beam tester will validate 3-D beam transport
simulations and allow a more rapid turnaround for
electron gun changes - The klystron will be developed in parallel with
little feedback from the beam tester. A rebuild
of the klystron can incorporate design changes
motivated by the beam tester
28Sheet Beam Klystron Plan
29Americas Site Plan
30Preconstruction Plan for Fermilab
Central Area fits inside the Fermilab boundary
Boundary of Fermilab
Site Characterization of the Central Area can be
done
5.5 km
5.5 km
31Preparing for 2012 Construction Start
2007
2010
2012
Phase 1
Phase 2
Phase 3
32Civil Construction Timeline
33Technically Driven Timeline (reprise)
2006
2010
2014
2018
Engineer Design
Construction ? Startup
BCD
Begin Const
End Const
RDR
EDR
Detector Install
Detector Construct
Siting Plan being Developed
Site Select
Site Prep
Pre-Operations
All regions 5 yrs
R D -- Industrialization
System Tests XFEL
Gradient
Cryomodule Full Production
August
e-Cloud