Title: Joseph M. Mwangala
1ASYCUDA World Implementation at Uganda Revenue
Authority
By Joseph M. Mwangala Project Manager - CBSEP
2Introduction
- ASYCUDA World is implemented by the Customs
Business Systems Enhancement Project (CBSEP), one
of the projects under the Managing Compliance
Program (MCP). - ASYCUDA World implementation at Uganda Revenue
Authority (URA) started in August 2011 by the
appointment of the National Project Team (CBSEP). - In addition to the implementation of ASYCUDA
World, the project team is also charged with
implementing the following components - Business Processes Review and Reengineering
- The National Authorized Economic Operator Program
- The Electronic Cargo Tracking System
- Capacity Building
- The project team responsible for ASYCUDA WORLD
has 21 (16 Business and 5 IT) full time members
headed by a Project Manager
3Introduction
- The project is Supported by a Customs Advisors
and IT Consultant from UNCTAD - The project is Funded by Trademark East Africa
(TMEA) and the Government of Uganda - The Project activities started in earnest in
November, 2011 with the signing of the
implementation agreement between URA and UNCTAD. - A phased approach was adopted for the
implementation of ASYCUDA World.
4Project Status
- National Project Team trained in Asycuda World
Functional and Technical (March, April 2012) - UNCTAD Advisors Arrive Uganda (June/July 2012)
- ASYCUDA World Servers procured and installed at
the Data Center (August 2012) - ASYCUDA World was piloted at JINJA Customs
station, an inland Customs station, starting on
the 26th November, 2012 until March 2013. - The pilot strategy involved having all the
transits to Jinja from the 4 key border stations
(Malaba, Busia, Katuna and Mutukula) done in
ASYCUDA World and the transits between those
stations.
5Asycuda World Pilot Strategy
6The National Rollout
- The National rollout was phased as below
PHASE OFFICE(S) OF DECLARATIONS DATES
PHASE 1 Entebbe (CAPT Cargo) 8 8/4/2013 24/5/2013 (6 weeks)
PHASE 2 Malaba, Busia, Mbale, Lwakhakha, Suam River, Katuna , Mutukula. 57 27/5/2013 28/6/2013 (5 weeks)
PHASE 3 Kampala 28 15/07/2013 06/09/2013 (8 weeks)
PHASE 4 Bunagana, Busunga, Cyanika, Mirama Hills, Kikagati, Kamwezi, Oraba,Vurra, Elegu, Arua, Goli, Paidha, Busitema, Kona Kamdin, Pakwach, Koboko, Lia, Lokung, Madi-Opei, Mbarara, Moyo, Mpondwe, Ntoroko, Kasese, Ishasha, Butiaba 7 16/09/2013 31/12/2013 (14 weeks)
7Lessons learnt
- The importance of continuous stakeholder
engagement - The importance of investing in good network
connectivity infrastructure - There is need to assess the existing equipment
infrastructure and document all required inputs
prior to project kick off. Realised late the need
for extra computers, scanners country-wide! - Procurement of all required inputs need to be
started way ahead of implementation. We are yet
to conclude the procurement of soClass licenses! - There is need for upfront preparations
- finances
- Publicity and sensitization
- Training
8Challenges
- Data Migration from A
- Network - intermittent and inadequate
connectivity - The need for stakeholders to procure computers
reliable network equipment for their offices - The continued use of DTIs by our clearing agents
due to lack of resources - Change of staff mindsets
- Project team skills/capacity e.g. mapping
processes, reforming customs! - Installed/Implemented AW Asycuda World as is,
before conclusion of the BPR process. Need
technical assistance to get this done properly. - OGA capacity to meet the clearance requirements -
in terms of hardware and staff
9ICT and Facilities Requirements
- What kind of technical expertise in Information
Technology IT is needed? - Practical experience in Software development
using Java - Knowledge in database management
- Knowledge in implementing web services in Java
- What are the types of new facilities needed?
- In addition to the live server upon which Asycuda
world runs, the following are needed - A Test server is needed to test all modules
before deployment to the live server - A development server is needed for ode version
management and developer testing of the new
modules.
10ICT and Facilities Requirements
- What are the requirements of ICT connectivity and
hardware upgrades? - From our experience, an 8 MB internet connection
is sufficient for the Asycuda world server side.
- Clients accessing the service externally require
a network connection with a minimum of 128 Kbps
11Legislation requirements
- Part XVI of the East African Community Customs
Management Act, 2004 provides for the Application
of IT in carrying out Customs formalities or
procedures. - There are no legal instruments governing the
interaction between OGAs and customs. We intend
to rely on MoUs between the semi-autonomous
government bodies
12Management and Training Support
- Projects at URA are coordinated and supported by
a Program Management Office under the MCP. - Projects are headed by a Project Owner (PO) The
Commissioner Customs is the PO for the CBSEP - Project staff are fully dedicated project team
(business and IT) to manage the project - The PMO manages and coordinates the capacity
building activities - Also funds general project management trainings
13Stakeholder engagement
- The Project Change Team together with the
Corporate Change Team and the Public and
Corporate Affairs communication team, carried out
stakeholder mapping and holds - awareness seminars
- Sensitizations
- radio and TV talk shows
- use of social media facebook, twitter, etc
- to sensitize stakeholders about the project
14Financing Requirements
- What is the financing required for investment in
new hardware, connectivity, telecoms upgrades? - From URA experience 3.56 Million USD was required
for hardware and licenses for both the primary
and disaster recovery sites - Network infrastructure in existence has a
recurring cost 1M USD per Year with a standing
backup link of the similar capacity and cost. - What is the cost of running the program?
- The 3 year activities to cost about USD 7.9
Million - BPR - 0.083
- Asycuda World - 1.930
- Capacity Building - 0.549
- Document Processing Center - 1.268
- National Targeting Center - 0.215
- Hardware/equipment - 3.868
15eSW related functionalities
- We have targeted OGAs who play a key part in
trade facilitation at the borders. These
include - Uganda National Bureau of Standards
- Uganda Coffee Development Authority
- National Drugs Authority
- Ministry of Agriculture
- Ministry of Health
- Ministry of Foreign Affairs
- Currently piloting with 2 OGAs UNBS and UCDA
- The OGAs have set their own selectivity criteria
16Q A
The end!