Earthwork - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Earthwork

Description:

Examine the materials and construction control process of earthwork operations to determine the degree of compliance ... Assure similar compaction efforts for the ... – PowerPoint PPT presentation

Number of Views:256
Avg rating:3.0/5.0
Slides: 29
Provided by: ben795
Category:

less

Transcript and Presenter's Notes

Title: Earthwork


1
Earthwork
2
LOTs
  • 120-8.1 Embankment Construction LOTs
  • What is the maximum length of a LOT?
  • Mainline pavement lanes, turn lanes, ramps,
    parking lots, concrete box culverts and retaining
    wall systems
  • A LOT is defined as a single lift of finished
    embankment not to exceed 500 feet.
  • Shoulder-Only areas, bike/shared use paths, and
    sidewalk areas
  • A LOT is defined as 2000 feet or one Days
    Production, whichever is greater.

3
Independent Verification
  • Question from Industry How is Independent
    Verification processed.
  • Section 120-10 Independent Verification
  • 120-10.1.5 - In addition to the Verification
    testing, the Engineer may perform additional
    Independent Verification (IV) testing. The
    Engineer will evaluate and act upon the IV test
    results in the same manner as Verification test
    results.

4
Independent Verification
  • QC Sample - 108 pcf
  • VT Proctor - 112 pcf
  • IV Proctor 116 pcf
  • Resolution Proctor 116 pcf
  • What proctor should we use?
  • Should they resample the material?

5
Reclaimed Asphalt Pavement (RAP) 120-8.4
  • Where is RAP prohibited? 
  • Construction areas that are below the seasonal
    high groundwater table elevation.
  • The top 12 inches of embankment.
  • MSE Wall backfill.
  • Minimize RAP content to avoid possible long term
    settlement

6
Reclaimed Asphalt Pavement (RAP)
  • Specifications
  • Soil RAP mixture120-8.4.2
  • Prohibited in Retaining Wall Systems
  • Alternate Layer Construction 120-8.4.3
  • Shoulder Base 283
  • Stabilizing Material 914

7
Max. Lift Thickness
  • Test Strip Requirements for 12 inch thick
    compacted lifts.
  • 125-8.1.6 In the soil envelope - maximum
    allowed thickness of backfill is 6 inches.

Requirements for max. 12 inch thick compacted Earthwork Requirements for max. 12 inch thick compacted Earthwork Requirements for max. 12 inch thick compacted Earthwork
Section Embankment 120-8.2 Pipe Backfill 125-8.1
A-3 and A-2-4 soils with up to 15 fines No Test strip required Test strip required
A-1, Plastic materials, and A-2-4 Materials with greater than 15 fines Test strip required Test strip required
8
Soil Envelope 125-8.3
Top Zone - Up to the base or final grade
1 foot above pipe
PIPE
Cover Zone
Bedding Zone 4 below the pipe
Lowest Zone
Bottom of Trench
9
Reduced Frequency Testing
  • How many passing density tests are required
    before the contract allows Reduced Frequency
    Density Testing for
  • Pipe backfill
  • Embankment

10
Embankment -Reduced Frequency
  • 120-10.1.6
  • Reduced Frequency Testing is allowed after 12
    passing tests with no Resolution tests in favor
    of Verification.
  • Required to use similar compaction effort on the
    untested LOT
  • Select test location randomly from one of the two
    LOTs under consideration.
  • Requires Engineers permission to place material
    over untested LOT
  • Not allowed in shoulder only areas, sidewalks
    bike/shared use paths. (LOT size)

11
Pipe Backfill 125-9.1.1
  • Reduced Frequency Testing is allowed after 6
    passing tests with no Resolution tests in favor
    of Verification.
  • Required to use similar compaction effort on the
    untested LOT
  • Select test location randomly from one of the two
    LOTs under consideration.
  • Requires Engineers permission to place material
    over untested LOT

12
125 Pipe Backfill
  • Plastic and Metal pipe backfill requires 95 of
    Standard Proctor for density.
  • Concrete pipe backfill requires 100 of Standard
    Proctor.
  • Structure backfill requires 100 of Standard
    proctor regardless of the type of pipe joining
    the structures.

13
Metal Pipe / Structure Density Acceptance
  • Metal pipe requires 95 maximum density
  • Structure requires 100 maximum density
  • The pipe and structure require separate density
    tests because of different density requirements.
  • This will be clarified in the July 2013
    specifications

14
Stabilization Materials- Sampling
  • Commercial Material - Approved Source (usually
    Aggregate Base) 160-2.1
  • Requires a Cert from the Mine
  • No field sampling or testing required
  • Existing Base 160-2.3
  • No testing requirements
  • IV testing is encouraged and should be performed
    on any material if there are concerns i.e. bad
    clay or organic materials
  • Local Materials 160-2.2
  • Acceptance requires
  • Source investigation (440 /440A Projects let
    after 3/1/11 )
  • Sample test from the roadway for material
    acceptance 160-3.2.1
  • (440/440B - Projects let after 3/1/11)

15
Stabilization - Local Materials
  • Meet the requirements of Section 914- 160-2.2
    (440/440A)
  • Local material may be clay from on-site, material
    from another construction project, or possibly
    byproducts from a process.
  • The Specifications require testing of the
    material before it is brought to the roadway and
    spread.
  • Sampling
  • Section 914 requires a minimum of 3 organic
    content test results and one LL/PI test result
    per source.
  • The Engineer should partner with the contractor
    to investigate the source or stockpile and
    evaluate each material. (best practice)
  • Use one sample card for each source or stratum of
    material
  • Provide a minimum of 3 - ½ bags of material for
    each source

16
C22 card
  • Material ID - Enter 440 for projects let prior
    to March 1, 2011 and 440A if the project is let
    after March 1, 2011 (This will show in the
    project job guide schedule)
  • Remarks - Enter Source testing
  • Sample Number Enter C001, C002, C003,
    etc and either Q or V

17
Roadway Acceptance Local Material
  • Sampling and Testing of Local Materials - Section
    160-3.2.1 (440/440B)
  • Requires Sampling after spreading and before
    mixing
  • QC 1 per 2 LOTs VT 1 per 8 LOTs
  • Sample Numbering - C001, C002, C003, etc
    and Q or V
  • Collect three pint size bags of material across
    the roadway (FM 1 T267)
  • Engineer Verification, Resolution and Acceptance
    - 160-3.2.1.1
  • Stabilizing materials require acceptance before
    the material is mixed into the Subgrade

18
C-22 CARD Example
  • Material ID - Enter 440 for projects let prior
    to March 1, 2011 and 440B if the project is let
    after March 1, 2011 (This will show in the
    project job guide schedule)
  • Sample Number Enter C001, C002, C003,
    etc and either Q or V
  • Plant or Pit No. Enter ROADWAY
  • QUANT REP Enter LOTS 1 thru 8
  • Remarks Enter LL/PI and ORGANIC TEST

19
RAP orRAP BLENDStabilizing Material
20
RAP or RAP Blend Stabilizing Material
  • Source Investigation (440/440A)
  • Evaluate the stockpile as a local material -
    160-2.2
  • If failing organic content is due to the asphalt
    content of RAP or RAP Blended material the
    department may modify acceptance (after careful
    evaluation)
  • Modified Acceptance for RAP or RAP Blend
    (440/440B)
  • http//www.dot.state.fl.us/statematerialsoffice/ad
    ministration/resources/library/materialsbulletins/
    topics/2011/mb02-11.pdf
  • Sample for LL/PI before mixing
  • Sample and test for Asphalt Content (FM 5-563)
    (NCAT) after Mixing
  • The upper limit for FM 5-563 in the mixed
    Subgrade is 4.7
  • Failure may indicate too much Asphalt or the
    presence of a material with a high organic content

21
Sampling for RAP Stabilizer Material
  • Sample after spreading and before mixing
    according to 160-3.2.1 (440/440B)
  • Sample Transmittal Card Example
  • Remarks
  • RAP Premixing no organic test
  • LL/PI test only
  • Sample size is ½ bag

22
Sample for Asphalt Content
  • Sample the material after mixing in 160-3.3
    (440/440B)
  • Sample size is 1 bag
  • Sample Transmittal Card Example
  • Use the same sample number as used for LL/PI
    testing
  • remarks
  • RAP - Substitute FM 5-563 for FM1-T267

23
  • Appendix

24
Independent Verification
  • 120-10.4.1 Standard Proctor Maximum Density
    Determination The Engineer will verify the
    Quality Control results if the results compare
    within 4.5 lb/ft3 of the Independent
    Verification Verification test result. Otherwise,
    the Engineer will take one additional sample of
    material from the soil type in question. The
    State Materials Office or an AASHTO accredited
    laboratory designated by the State Materials
    Office will perform Resolution testing. The
    material will be sampled and tested in accordance
    with AASHTO T-99, Method C. The Engineer will
    compare the Resolution Test results with the
    Quality Control test results. If all Resolution
    Test results are within 4.5 lb/ft3 of the
    corresponding Quality Control test results, the
    Engineer will use the Quality Control test
    results for material acceptance purposes for each
    LOT with that soil type. If the Resolution Test
    result is not within 4.5 lb/ft3 of the
    Contractors Quality Control test, the
    Independent Verification Verification Test result
    will be used for material acceptance purposes.

A1
25
A2
26
A3
27
FDOT Laboratory Testing Contacts
Name Office Telephone email
Timmy Meeks District 1 7 863-519-4200 timmy.meeks_at_dot.state.fl.us
Larry Keen District 2 386-758-3758 larry.keen_at_dot.state.fl.us
Tonya Myers District 3 850-638-0250 tonya.myers_at_dot.state.fl.us
Ernst Registre District 4 6 954-677-7100 ernst.registre_at_dot.state.fl.us
Joe Owens District 5 386-740-3400 joseph.owens_at_dot.state.fl.us
Ed Cueto Florida Turnpike 954-934-1730 ed.cueto_at_dot.state.fl.us
Daniel Pitocchi State Materials Office 352-955-2945 daniel.pitocchi_at_dot.myflorida.com

A4
28
FDOT Earthwork Material Contacts
Name Office Telephone email
Barbara Beacham District 1 7 863-519-4200 barbara.beacham_at_dot.state.fl.us
Vacant Position District 2 386-758-3758 T.B.D.
Chad Miller District 3 850-638-0250 chad.miller_at_dot.myflorida.com
Ron Arcalas District 4 6 954-677-7100 ronald.arcalas_at_dot.state.fl.us
Jody Clifton District 5 Materials 386-740-3400 jody.clifton_at_dot.state.fl.us
Todd Kelly Florida Turnpike 407-264-3370 todd.kelly_at_dot.state.fl.us
Ben Watson State Materials Office 352-955-2935 ben.watson_at_dot.myflorida.com

A5
Write a Comment
User Comments (0)
About PowerShow.com