Title: WANG, Li
1MICE/Muool Coupling Magnets Progress
WANG, Li 2009-01-15 Institute of Cryogenics and
Superconductivity Technology Harbin Institute of
Technology, China
2Contents
- MICE/MuCool Coupling Magnet Updated Design Review
- Done in ICST/HIT on Dec.06 to Dec.08, 2008,
and further improvement has been carried out
after the review according to the Close Out from
the review panel (to be presented by Hong Wu/Heng
Pan/XingLong Guo).
- Large Coil Test and Plan
- To be presented by Dr. FengYu Xu
- Fabrication Plan of MICE/MuCool Coupling Magnets
- Visits to possible collaborators in China
Request for quotations and further technical
discussions, preparation for public bidding
procedure etc.
3MICE/MuCool Coupling Magnet Updated Design
The updated engineering design were carried
out according to the A Technical Agreement on
the MICE and MuCool Coupling Solenoid Magnet
Fabrication, Assembly, Test and Shipping issued
in September, 2007 and experience learnt form
test coils winding in collaboration with
Lawrence Berkeley National Laboratory. The main
differences between the previous design reviewed
in May, 2007 and the updated design reviewed in
Dec., 2008 mainly include
- The inner radius of the coupling coil is changed
from 744mm to 750mm considering very tight space
on the inner side of the magnet. - The coil assembly is designed different from the
previous one in terms of winding, mandrel
fabrication, cooling and quench protection
assembly. - A double-band cold mass support system is
presented instead of a single-band system
considering the shipping load during long-term
transportation and space limitation.
4- Two drop-in PTR coolers are to be used for
cooling the coupling magnet for the sake of easy
removal from the cryostat during transportation. - Thermal shields are designed to be supported from
the vacuum vessel by four pairs of G-10 rods
instead of being supported onto the cold mass
support assembly as previous design. - The cooling configuration for the warm end of the
HTS leads is designed different from the previous
one.
Further improvement after the review
- To validate
- Stress analyses on final coil cold mass
design, mechanical (loads, stress) and thermal
analyses on the current design for the coil cold
mass support assembly, stress and deflection
analyses on the vacuum chamber, etc. - To update the following engineering design
drawings - Vacuum chamber and interface, coil cold mass
assembly, cold mass support assembly, etc.
5(No Transcript)
6Updated design
7Piping round tubing instead of ? type tubing
more cold surface to mount QPAssembly more space
for mounting CMSupport cold end base, etc.
- Coil assembly and its cooling
Updated design
Previous design
8Single-band to double-band space for cold end
base and its strength
Previous design
Updated design
9Large Coil Test and Plan
- SC splices strength test at LHe temperature
- The strength of SC splices soldering by Sn-Ag
solder under LHe temperature is a major concern
presently considering the rigorous stress state
in the coupling coil because all the splices are
wound inside the coil and should be tested before
winding the MuCool coil according to Dr. Mike
Greens advice. - ICST has performed the strength test for the SC
splices at LN2 temperature and the results show
its strength is close to that of the SC wire
itself . - ICST has prepared some of SC splices and to see
if they could be tested in LBNL under LHe
temperature.
10Winding of prototype coil
Cryo-test system
Welding
Cryostat for prototype coil
Large test coil
11Fabrication Plan of MICE/MuCool Coupling Magnets
- Visits to possible vendors in China last December
- CSRDA in Beijing
- Experience in fabrication and assembly of
coil mandrel cooling tubing welding, heat
shields vacuum chamber for SSM and Ion-removal
SC solenoid in BEPCII, fabrication, assembly, and
maintenance of several MRI magnet systems since
1987 (winding coil, cold mass, cryostat, etc.). - SINAP in Shanghai
- Experience in fabrication, assembly and test
of a small SC magnet (EBIT, solenoid coil ID
100mm) for Shanghai FuDan University, various
advanced equipment or device for alignment,
measurement and cryo-test, a set of 600W/4.5K
refrigerator system etc.
- Request for quotation
- Cold mass assembly by Jan. 17
- Cryostat assembly by the middle of February
12Plan for Fabrication the MuCool magnet
- Possibilities to cause delays
- Manpower skilled technicians and their
supervisor, experienced mechanical engineers,
etc. - Funds available time?
- Request for quotation
- Further technical discussions with possible
vendors before public bidding for Cryostat
Assembly (after Chinese Spring Festival till Feb.
1st ) are needed. - Public bidding procedure
- At least 3 vendors and 7 days workday for
publicity, otherwise invalid bidding if sole
source, it will take a longer time, more paper
work and complicated procedure. - Contract award and sign it after bidding
- At least one to two weeks are needed.
- Winter holidays in HIT Jan. 19 to Feb. 22
- No possibility for processing bidding in HIT
Hopefully, to contract the first MuCool coil
assembly fabrication out before or right after
the Chinese Spring Festival (at latest by the
middle of this February) in order to avoid more
delay!
13Thank You !
Icst.hit.edu.cn
- Click to edit company slogan .