Title: CCFB
1A presentation by
CCFB
On Beira Rail Concession Workshop on Large
Project Finance Feb 07, 2008, Maputo, Mozambique
2 Mozambican Rail Network
3Topics
Background Beira Rail System
Steps before embarking on PPP
Concession features
Key Success Factors
Procurement, Monitoring and Evaluation
4Background Rail Port Systems Mozambique
- early 90s GOM decision to embark on
concessioning rail port systems - restructuring of state-owned operator CFM into
lean holding company with minority stakes in
concessions - majority of ports already concessioned (e.g.
Maputo, Beira, Quelimane, Nacala) - currently two rail concessions in operation
Beira and Nacala - rehabilitation of Beira Railway System
constituted national priority - rich potential in mining, forestry, agriculture,
animal husbandry, power generation - social responsibility to re-open hinterland to
Beira Maputo (catchment area comprises
provinces of Tete, Zambezia, Sofala and Manica
with approx. 30 of Mozambiques population)
5Beira Rail System (BRS)
- BRS comprises 2 Railway lines
- Machipanda Line (317km)
- domestic international freight (Zimbabwe)
- freight traffic 0.66mt in 05, 0.8mt in 06,
0.54mt in 07 (peak in 1996 1.2mt) - estimated rehabilitation cost 25m(revised 39m)
- Sena Line (670km)
- closed in 1983 due to civil war
- formerly carried sugar, cotton, limestone, coal
(Moatize) - carried domestic international freight (Malawi,
Zambia) - estimated rehabilitation cost 127.5m(revised
158m) - original estimated freight traffic 1.57mt in
2010 2.29mt in 2023 (historic peak freight
traffic 2mt in early 80s)
6(No Transcript)
7Steps before embarking on PPP alternative
projectdesigns considered in light of
uncertainty of Coal Mining
- Five alternative structures for the design of
project considered - An integrated coal/mines/port facilities/railway
concession - Designing the project as a two-phase concession
- Rehabilitating the Sena Line to the ultimate
standard in one phase - Separating the rehabilitation program from
concessioning - Separating concessions for the Machipanda and
Sena Lines - Final design chosen as combination of
alternatives 2 and 3. - Track infrastructure to be constructed to
ultimate axle load and speed design
standards - Limiting the design of other infrastructure such
as signaling and telecommunications, passing
loop lengths, and additional stations to the
requirements of the essentially non-coal traffic
8Steps before embarking on PPP technical
operational performance standards
- study confirmed technical feasibility
(reconstruction of bridges track) - Infrastructure
- rehab to be undertaken with new materials
- min. capacity 18-ton axle loads and 60 km/h train
speeds - construction and renewal tolerance in line with
UIC specifications - Track to be maintained as per international (AAR)
standards1 - installation of signaling and modernization of
communication systems - Operation
- less than 2 of track under speed restriction
- average kilometers between locomotive failure not
less than 100,000 - Availability of locomotives 85 and wagons 90
- time between demand and supply of wagons less
than 2 days - working ratio (operating cost/revenue lt 70, etc.)
1) Track Safety Standards, Federal Railroad
Administration, Title 49, Part 213, February 1996
for Passenger Trains speeds 60mph
9Steps before embarking on PPP economic
viability
- major benefits of rehabilitating BRS comprise
(in order of magnitude) - reduced transport costs (shift from expensive
road barge transport to rail) - generated traffic (net value added first order)
- additional rail revenue (non-domestic traffic)
- generated traffic (net value added second order)
- poverty alleviation (e.g. increased economic
activities employment) and increased
mobility - major costs of rehabilitating operating BRS
comprise (in order of magnitude) - maintenance operation
- infrastructure investment costs
- investment in feeder roads
10Steps before embarking on PPP economic
viability
- PV of total benefits 288 million
- PV of total costs 225 million
- NPV (benefits costs) 63 million
- ERR at 18, greater than opportunity cost
of capital (12-15) - Robust analysis ERR between 1023
within confidence interval of 90 using Monte
Carlo simulation
11Steps before embarking on PPP PPP structure
- GOM applied for IDA loan to be on-lent to
concessionaire - WB supported GOM through Technical Assistance
(for structuring bidding process, preparation,
negotiation and award of concession) - 49 GOM share of which 16 to be offered to
public
RITES/IRCON(India)
CFM (GOM sole shareholder)
51
Joint Venture
49
CCFB(Concessionaire)
CFM share will eventually diminish to 33 (IPO
for remaining 16 envisaged
on-lending, 105m of IDA credit
IDA credit
WB
GOM
12Steps before embarking on PPP financial
viability
Project Financing Project Financing Amount (USD m)
EQUITY FINANCING EQUITY FINANCING Equity RITES IRCON (51) 10.07
EQUITY FINANCING EQUITY FINANCING Equity CFM (49) 9.67
EQUITY FINANCING EQUITY FINANCING Sub Total Equity 19.74
DEBT FINANCING DEBT FINANCING IDA 104.5
DEBT FINANCING DEBT FINANCING Government of India LOC 22.62
DEBT FINANCING DEBT FINANCING Commercial Loan 2.82
DEBT FINANCING DEBT FINANCING Loan from Promoters 0
DEBT FINANCING DEBT FINANCING Sub Total Debt 129.94
INTERNAL CASH GENERATION INTERNAL CASH GENERATION Machipanda Cash Flow 2.78
Total 152.46
1) Debt Service Cover Ratio (net operating
income over annual debt service)
13Concession Features selection of concessionaire
- award method International Competitive Bidding
(ICB) - first pre-qualification repeated to adjust for
changed conditions, final pre-qualification in
April 2003 (5 applicants) - past railway operation or management experience
mandatory - final set of bidding documents released to
pre-qualified bidders in October 2003 - receipt of 3 bids in December 2003
- Rites/Ircon declared successful bidder early
2004 - Concession agreement signed in August 2004
- Machipanda Line taken over in Dec. 2004, Sena
Line in March 2005 - award criteria bid substantially responsive to
bidding document and requiring the lowest
government (IDA) support for rehabilitation of
Sena Line (in terms of present value _at_ 10
discount rate)
14Concession Features key contract features
- concession fee
- 2 million entry fee
- 1 million fixed fee per annum from year 11 to
25 (indexed from take over date to USA CPI) - variable fee from year 6 onwards 3 of turnover
for traffic up to 300 million ntkms, 5 for
traffic in between 300 million and 1 billion
ntkms and 7.5 for traffic above 1 billion
ntkms - tariff setting
- Concessionaire free to set tariffs
- dispute resolution
- by parties in good faith
- referral to technical expert if parties unable to
resolve tech. dispute - arbitration in accordance with Rules of
Conciliation Arbitration of International
Chamber of Commerce as last resort
15Concession Features key contract features
- termination clauses covered Company
Conceding Authority Defaults - risk management
- De-mining risk
- commercial risk (traffic risk)
- construction risk
- VAT risk
- force Majeure
- political risks
- foreign exchange
- economic situation of neighboring countries
16Concession Features key contract features
- regulatory framework
- no economic regulation
- regulation of Safety/Health/Environmental issues
(SHE) - resort to unfair competition commission for user
complaints
17Procurement during Implementation
- IDA funds on-lent to concessionaire for Sena
Line rehabilitation - as the concessionaire was selected through ICB,
in compliance with WB procurement rules, he
is generally free to choose his own procurement
methods for goods, works and services - obligation of IDA is to ensure the agreed
procurement plan is fully complied with and
there is efficiency, transparency and fairness in
the adopted procedures. -
18Monitoring Evaluation
- concession agreement stipulates that
concessionaire shall achieve recognized
international performance norms for railway
services agreed between conceding authority and
concessionaire - failure to achieve such will result in
financial penalties to be drawn from the
Performance Security for Maintenance - additionally, WB, CCFB and the Borrower have
agreed on Project Development Objectives,
outcomes end of project results which would
be monitored through agreed performance
indicators and intermediate output targets
during project implementation (five years)
19Implementation Status
- Sena Line
- De-mining bush clearing 100 completed
- Formation preparation 30
- Track laying 25
- Sleeper Plant at Dondo capacity 25,000 sleepers
per month - Another Sleeper plant at Sena has started
production from Nov, 2007 15,000 sleepers per
month - Rehabilitation work on two major bridges
commenced - Supply of ballast key constraint
- About 3000 personnel working
- Interim freight operation expected by April, 2008
- Beira-Marromeu
20Key Success Factors
- Invest considerable time and effort in
conceptualizing and finalizing project design - Socio-economic justification essential before
structuring PPP and finalizing financing
arrangements - Beira Railway Project is a unique case of
accommodating uncertainty of coal concession - Full involvement of key Government officials
and decision makers essential every step of
the way to concession award and implementation - No negotiations allowed on any of the terms and
conditions of concession agreement clauses
after bidding - All elements of procurement, including domestic
preference and local industry involvement,
agreed up-front - Flexibility during implementation essential to
overcome unforeseen difficulties - Aggressive marketing and optimum utilisation of
resources to make Machipanda Line profitable
21CCFB expresses its gratitude to GOM, WB and
above all to the generous people of Mozambique
for their help and support. THANK YOU