Title: NEW ISSUES AND RECENT CASES IN CHARTERING
1NEW ISSUES AND RECENT CASES IN CHARTERING
- TokyoMay 12, 2009
- William J. Honan
- Holland Knight LLP
2Clause 5, Part II, ASBATANKVOY
- 5. LAYDAYS. Laytime shall not commence before
the date stipulated in Part I, except with
Charterer's sanction . . .
3Clause 6, Part II, ASBATANKVOY
- 6. NOTICE OF READINESS. Upon arrival at
customary anchorage at each port of loading or
discharge, the Master or his agent shall give the
Charterer or his agent notice by letter,
telegraph, wireless or telephone that the vessel
is ready to load or discharge cargo, berth or no
berth, and laytime, as hereinafter provided,
shall commence upon the expiration of six (6)
hours after receipt of such notice, or upon the
vessel's arrival in berth . . . whichever first
occurs. However, irrespective of whether the
berth is reachable on arrival or not where delay
is caused to Vessel getting into berth after
giving notice of readiness for any reason over
which Charterer has no control, such a delay
shall not count as used laytime or demurrage. In
any event, Charterer shall be entitled to six
hours notice of readiness at loading and
discharging ports, even if the vessel is on
demurrage.
4Issue No. 1
- 1. If a vessel arrives prior to commencement of
the laydays and is ready to load, is the vessel
under an obligation to give its notice of
readiness?
5Issue No. 2
- 2. If the vessel gives its notice of readiness
prior to the commencement of laydays, does the
six hour free period begin running upon the
giving of the notice of readiness or at midnight
of the first layday?
6Issue No. 3
- 3. Does the giving of an early notice of
readiness require the charterer to commence
loading immediately (or at least 6 hours
afterwards)?
7Issue No. 4
- 4. If the charterer upon receipt of the early
notice of readiness, orders the vessel to a
berth, can the vessel refuse?
8Issue No. 5
- 5. If the charterer orders the vessel to its
berth upon receipt of the early notice of
readiness and begins loading the vessel, all
before the commencement of the laydays, does the
time used prior to the first layday count as
laytime?
9Mr. Justice Langleys Holding
- 1. "Laytime never started at all, with the
consequence not only that the owners have earned
no demurrage, but also that they are obliged to
pay the charterers despatch money for the whole
of the laytime." - 2. Charterers awareness that discharge had
commenced without protesting or reserving its
rights was not itself a sufficient happening to
cause laytime start.
10Northgate Clause 6
- Vessel is to give its NOR upon arrival at the
inner anchorage at Sepetiba but may give its NOR
at the outer anchorage if space is unavailable in
the inner anchorage.
11Judge Siberry said
- . . . , I consider that is a matter of
commercial practicality, such an intended
recipient of the NOR must have implied authority
to waive a condition as to the commencement of
laytime.
12He continued
- . . . if Charterer did not communicate the
Northgate charter terms to the Terminal/MBR
and/or give specific instructions that NOR was
not to be accepted from the other anchorage
unless the vessel was compelled to wait there
because the inner anchorage was congested, it
seems to me that they i.e., the Charterer took
the risk that the Terminal/MBR would accept a NOR
that could have been rejected under the Northgate
Charter and thereby waive Charterers' right to
invoke the invalidity of that NOR.
13Clause 6, Part II, ASATANKBOY
- Upon arrival at customary anchorage at each port
of . . . discharge, the Master shall give the
Charterer . . . notice . . . that the Vessel is
ready to discharge . . . .
14The arbitrators said
- In the tribunal's view "anchorage" in clause 6
could not be read too literally. The situation
in the waters off Lagos was notorious . . . . To
deprive an owner of the right to give a valid
notice of readiness under the Asbatankvoy form of
charter in such circumstances seemed to the
tribunal wholly unreasonable and not what the
parties could have intended.
15Agios Dimitrios Clauses 23(b) and 25
- Clause 23(b)
- At loading port(s) when tendering notice of
readiness, Vessel's cargo holds and hatch covers
shall be clean, dry of loose rust and otherwise
ready and suitable to receive the intended cargo. - Clause 25
- Crew and mechanical failure time lost at
loading and/discharging port(s) which can be
reasonably attributed to crew and/or ship's
mechanical failure, shall not be counted as
laytime or time on demurrage.
16Nikmary Facts Summary
- The vessel arrived at the port of Sikka to load a
cargo of gasoil on December 2 and proceeded
immediately to its berth. - The vessel's tanks were inspected on December 3rd
by an independent surveyor appointed by the
charterer and were rejected. - The supplier, Reliance Petroleum Limited, was
prepared to supply the cargo on December 3rd. - The vessel's crew cleaned the holds and, on
December 5, the two surveyors, one appointed by
the owner and the other appointed by the
charterer passed the holds and the vessel gave
its valid NOR to the receiver. - No cargo was forthcoming and, on December 9,
Reliance notified the charterer that due to its
other commitments, the Nikmary would not be
loaded until the end of the month. - Loading in fact did not commence until January 3.
17Nikmary Clause 30(c)(v)
- Owner shall indemnify Charter for all direct
and/or indirect costs and consequences as a
result of the Vessel not being clean to the
satisfaction of jointly appointed inspector and .
. . all time until connection of hoses, after the
Vessel has been passed as clean to the
satisfaction of jointly appointed inspector shall
not count as laytime or, if on demurrage, as time
on demurrage.
18Charterers Duty to Provide Cargo
- A voyage charterer owes an absolute and
non-delegable duty to provide cargo for loading
and - Charter exceptions will normally be read as
protecting a charterer only in respect of its
duty to load, and not as covering its duty to
provide a cargo.
19Clause 23
- 23. Charterers shall be discharged and
released from all liability in respect of any
claim for demurrage which Owners may have under
this Charter unless a claim in writing has been
presented to Charterers together with supporting
documentation substantiating each and every
constituent part of the claim within 90 days of
the completion of discharge of the cargo carried
hereunder.
20Owner argued
- 1. the absence of the vessel officer's
signature was of no relevance indeed, it was
prepared to sign the pumping logs anytime. - 2. the Charterer was shown to have received
pumping logs signed by its own representative
within the 90 day period. - 3. even if the discharge port demurrage was
time barred, due to the absence of a signed
pumping log, the Owner should be able to recover
the demurrage that it incurred at the load port.
21Mrs. Justice Gloster held
- 1. There as a significant commercial purpose in
requiring a signature of a vessel's officer for
someone should be identified that is willing to
confirm its accuracy. - 2. The Charterer should have the documents in
one package and should not have to review its own
files or make its own investigation. - 3. Clause 23 refers to a single claim and there
is no suggestion that part of a claim would be
permitted if the Owner's submission was defective.
22Mr. Justice Steel ruled
- . . . I am not persuaded that . . . the failure
to provide all "supporting documentation" . . .
for one constituent part of the claim discharged
liability for the entire demurrage claim.
23Time Bar General Principles
- 1. Contractual time bars are enforced.
- 2. Arbitrators require strict compliance to
satisfy contractual time bars. Substantial
compliance probably is insufficient. - 3. Contractual time bars are enforced even if
there is no dispute concerning the claim in
question. - 4. Contractual time bars are construed strictly
against the drafter.
24Time Bar Practice Tips
- 1. If the Owner
- a) seek to eliminate altogether
- b) make the clauses mutually applicable
- c) provide as long a period as possible
- d) provide training to the persons handling
claims - 2. If the Charterer
- a) include all claims not just demurrage and
detention - b) draft the clause so as to avoid obvious
loopholes
25Eland S.M.A. 4027 (March 4, 2009)
- The term "WVNS," coupled with a description of
the cargo segregation system, exists primarily to
protect owners . . . from being compelled to load
different cargoes in such manner as to result in
potential cargo claims. It is not a descriptive
phrase that charterers . . . can waive in order
to maximize the amount of cargo intake. - . . . Since the Owner did not have to follow the
improper voyage orders, it could impose, within
reason, any conditions it felt necessary to
protect its contractual rights.
26Elinda S.M.A. 4006 (May 30, 2008)
- Should the vessel be off-hire for more than
fifteen (15) days, charterer shall have the
option to cancel the charter party provided there
is no cargo onboard.
27Clause 23
- Charterer to give 30 days notice with 10 days
notice laycan speed and Owners to nominate the
vessel latest 10 days prior first day with
complete itinerary of he vessel . . . .
28Charterer instructed
- "Baltimore/Constanza shipment 5 under the
subject COA 5/14 Oct. - then
- ". . . would like to move the laycan for
shipment 5 to 21/30 Oct.
29Charterer replied
- Actually the stem 5/14 has moved to 22/30 by the
shippers because of cargo availability in this
port. Therefore requesting owners for this
amendment .
30Mr. Justice Steel held
- ... , in my judgment, as soon as the notice is
given the owners can rely on it. The idea that
over the period of 20 days before the nomination
of the vessel has to be made the charterers can
change the lays on dates as frequently and as
substantially as they see fit, or even thereafter
up to the stage that an estoppel be clearly
established, is commercially unreal and uncertain.
31Redelivery Clause
- . . . charterers are to give Owners not less
than 30 days followed by 20/5/10/7 days notice of
approximate redelivery date and intended port
thereafter 5/3/2/1 days definite notice of
redelivery date and port.
32Charterer stated
- approximate notice of redelivery for the MV
Zenovia at DLOSP 1 sp China on about 04 Nov 2007
basis agw, wp, wog, uce
33Charterer revised instruction
- Pls note that we hereby revise the date of
redelivery to owners to about Nov. 20th within
the range of redelivery.
34Panel held
- 1) the Owner had relied on Charterer's
statement in refixing its vessel on the
assumption that it would have the vessel back on
about Nov. 4 (promissory estoppel). - 2) there was implied a term that, when an
approximate date is given by the Charterer, the
Charterer was obliged "not to do anything
deliberately which prevents that approximate date
being met."
35Mr. Justice Tomlinson
- 1) If the arbitrators believed the acronym "WP"
stood for "without prejudice" those words should
have put the Owner on notice that Charterer could
change the approximate redelivery date. - 2) To imply a term in a negotiated contract,
the term must be so obvious that the parties
must have intended it for a part of the contract.
Pointing to the notice periods (30/20/10/7
approx 5/3/2/1 definite), the Court stated that
"in my judgment the very structure of that
regime militates against any argument that the
parties must be bound to have agreed that the
giving of the first notice constrained
36For Promissory Estoppel
- (i) a clear and equivocal representation by the
charterers that they were giving up their rights
(that is, giving up their right to retain the
vessel until November 22) and - (ii) owner acted in reliance on that
representation in a way that would make it
inequitable to permit charterer to change its
position.
37NEW ISSUES AND RECENT CASES IN CHARTERING
- TokyoMay 12, 2009
- William J. Honan
- Holland Knight LLP