Title: Project Planning - 1
1Project Planning - 1
Lecture-4
Presented byM. A. Kamal, Ph.DDirector
GeneralNational Academy for Planning
Development
2Outlines
- Introduction
- Objectives of Project Appraisal
- Scope of Project Appraisal
- Methods of Calculating Profit Worthiness
- Formula for
- Acceptability Criteria
- The basic Difference between Financial Appraisal
Economic Appraisal - Types of Project Appraisal
- Conclusion.
31. Introduction
- 1.1 Project Appraisal Pre-Investment
Analysis/Ex-ante Analysis. - 1.2 Project Evaluation Post-Implementation
Analysis/ Ex-post Analysis.
4Project Appraisal
- 1.3 Project Appraisal involves comparison of
costs and benefits. If benefits exceeds costs,
the project could be considered for acceptance. - 1.4 The basic principle in appraisal / CBA is for
potential acceptance of a project. - 1.5 Project Appraisal means a pre-investment
analysis of a project to determine whether the
project should be implemented or not.
52. Objectives of Project Appraisal
- 2.1 Project Appraisal is necessitated because
resources or means are Limited as compared to the
needs of the society. - 2.2 As a result, any investment undertaken
implies depriving other projects resources. - 2.3 Each project is appraised before investment
decision so that scarce resources are utilized in
the best possible ways. - 2.4 Before allocation of resources for a
particular project, the decision making authority
must convince itself that the proposed project is
the best and most economical way of achieving the
desired objective (socio-economic benefits). - 2.5 For ensuring economic use of resources we
have to appraise each project very minutely from
different angles. - (Cont.)
6- 2.6 Project Appraisal involves detailed
pre-investment analysis of market technical
feasibility, financial soundness, economic
desirability and, finally, measuring its
investment worth. - 2.7 The task aims mainly at ensuring that scarce
resources are put to most effective use. - 2.8 It requires the combined efforts of a team of
persons from various disciplines (engineers,
financial analysts, economists etc.) working in
close, co-ordination.
73. Scope of Project Appraisal
- 3.1 Market Feasibility study.
- 3.2 Technical Feasibility / viability.
- 3.3 Financial Soundness.
- 3.4 Management and Organizational Aspects /
Managerial Soundness. - 3.5 Economic viability / Appraisal.
- 3.6 Environmental Appraisal / Viability.
83.1 Market Feasibility
- Whether sufficient demand does exist?
- b) In case of import substitution whether
domestic cost of production is less than cost of
import.
93.2 Technical Appraisal
- Availability of inputs at reasonable cost.
- Consistency soundness of engineering design.
- Economics of scale in production.
- Appropriate technology alternative ways of
production. - Advantageous Location of the project.
- Maintenance Repairs.
- Provision for expansion.
- Balancing of equipment
103.3 Financial Soundness
- Exhaustive realistic cost estimation
- Sound capital structure Fund Source
- Provision for working capital requirement
- Generation of sufficient cash flow to cover
debt-service Liability. - Generation of adequate profit.
- Safety margin.
- Break- Even Point
- Pay back period.
- Pay back period Pay back period is a measure of
Projects Capital recovery. It is defined as the
Length of time it takes to recover the initial
investment of a Project.
113.4 Managerial Soundness
- Experience of the top managerial personnel in the
line. - Expertise and ability of supervisory staff
members. - Balance between supervisory staff and work
forces. - Clarity of job description, responsibility and
accountability.
123.5 Environmental Aspects
- The environmental impacts include
- Ecological Fisheries, Tree Plantation, Wet Land
/ Wet Land Habitat, Forest. - Physico- Chemical Flood Control Drainage
Erosion, Drainage, Congestion / Water Logging,
Obstruction to waste water Flow, Soil Fertility,
Early Flooding. - c. Human Interest Areas of Settlements,
Agricultural Lands, Navigation / Boat
Communication, irrigation Facilities, Landscape,
Land values.
133.6 Measurement of Investment Worthiness
- What benefit does the project promise for its
sponsors or owners? - What benefit does the project promise for the
national economy? - The satisfactory answers to these questions
provide the prime test of a projects
acceptability.
144. Methods of Calculating Profit Worthiness.
- 4.1 Net Present Value NPV
- 4.2 Benefit Cost Ratio B/C Ratio
- 4.3 Internal Rate of Return IRR
155. Formula for
- 5.1 NPV Discounted Total Benefits Discounted
Total costs. -
- 5.2 B/C Ratio Discounted Total Benefits
- Discounted Total costs
165.3 Formula for IRR
- NPV
- 3. IRR LRD LRD x ( HRD LRD )
- NPV - NPV
- LRD HRD
- Where,
- LRD Lower Rate of Discount at which NPV is
positive - HRD Higher Rate of Discount at which NPV is
negative - NPV Net Present value at the Lower Rate of
Discount - LRD
- NPV Net Present value at the Higher Rate of
Discount. - HRD
- What is IRR?
- IRR Internal Rate of Return is that rate
of discount that makes/ reduces the
Net Present Value (NPV) of a project
is to Zero.
17Year Cost Benefit Discount Factor at 15 Discounted Cost Discounted Benefit D.F at 25 Discounted Cost Discounted Benefit
0 200 - 1.00 200 - 1.00 200 -
1 60 160 .870 52.2 139.2 .800 48.00 128.00
2 60 160 .756 45.36 120.96 .640 38.40 102.4
3 60 160 .658 39.48 105.28 .512 30.72 81.92
337.04 365.44 317.12 312.32
NPV DTB DTC NPV at 15 365.44 337.04
28.40 B/C at 15 365.44
337.04 1.08
NPV at 25 312.32 317.12 -
4.8 IRR 15 28.4 (25 -15)
28.4 (- 4.8) 15 28.4
10 28.4 4.8 15 28.4 10
33.2 15 8.55
23.55 ? IRR 23.55
186. Acceptability Criteria
- 6.1 NPV (Net Present Value) if NPV gt
0 ACCEPT - if NPV lt 0 REJECT
- if NPV 0 AMBIGUOUS
- 6.2 BCR (Benefit Cost Ratio) if BCR gt I ACCEPT
- if BCR lt I REJECT
- if BCR I AMBIGUOUS
- 6.3 IRR (Internal Rate of Return) if IRR gt
r ACCEPT - if IRR lt r REJECT
- if IRR r AMBIGUOUS\
- r MARKET RATE OF INTEREST
197. The basic difference between Financial
Appraisal Economic Appraisal
208. Types of Project Appraisal
- 8.1 Financial / commercial Appraisal
- 8.2 Economic Appraisal
- 8.3 Technical Appraisal
- 8.4 Social Appraisal.
219. Conclusion
- 9.1 Project appraisal is the basic criterion of
selecting a project. - 9.2 Objectives of project appraisal are to
measure the different worthiness of a project - 9.3 Scope is wide and essential
- 9.4 Environment impact is crucial in project
implementation. - 9.5 Measurement of investment worthiness are
principal decision making tools. - 9.6 Positive signal is the key to successful
selection of a project.
22THANK YOU