Title: A Design-Build Success Story
1Landfill Gas Migration Control
- A Design-Build Success Story
- Dick Sprague
- HDR, Inc.
2Purpose Background
- Design-Build Project Delivery
- Emerging delivery system in public sector
- Single source of responsibility
- Faster, less contentious delivery
- Not necessarily cheaper
- Landfill
- Historic landfill cell began in early 1950s
- New, lined landfill cell began in late 1990s
- Landfill gas migration discovered in 2001
3Landfill Site
4Landfill Gas Migration
- Anaerobic decomposition
- Predominantly methane and carbon dioxide
- March 2001 monitoring
- High concentrations of Lfg at property boundary
- gt1,000 feet beyond property boundary
- May 2001
- Issued engineering RFP
- Informed state agency neighbors
5Extent of Contamination
6 7Design-Build Project
- Too little time for traditional design-bid-build
- 2-part contract
- Several form contracts
- AGC, AIA, EJCDC
- DBIA is fairest to all parties
- 2-Part form contract includes
- Terms Conditions
- Scope
- Price Schedule
8Design-Build Project (cont.)
- Part I - Concept Design Proposal
- 30 Design
- Proposal for Part II
- Firm, fixed price based on bids
- Drilling subcontractor
- Equipment supplier
- Balance of construction contractor
- Documents Belong to Owner
- Negotiate with Part I contractor
- Bid the work
- Cancel the project
9Design-Build Project (cont.)
- Part II
- Final Design
- Construction, Start-up Warantee
- Firm schedule based on WES commitments
- Contract (part II) signed on September 27
- Completion planned for December 14
- Best Value Selection
10Design-Build Project (cont.)
11Design-Build Project (cont.)
- Performance
- Drilling subcontractor failed to perform
- Primarily his lower tier subs
- Third lower tier sub required to complete project
- Flare station operational December 14, accepted
December 18 - 60 percent of wells operational on December 18
met commitment to state agency - Final completion January 18
12Design-Build Project (cont.)
13Design-Build Project (cont.)
14Design-Build Project (cont.)
15Design-Build Project (cont.)
16Design-Build Project (cont.)
Event Planned Actual
Engineering Contract June 18 July 20
Construction Contract October 1 September 27
Begin Construction October 15 October 2
System Startup December 18
System Complete December 15 January 18
17Design-Build Project (cont.)
- Lump Sum Price
- Change Orders
- Net Price
18Design-Build Project (cont.)
- Lump Sum Price
- Change Orders
- Net Price
- 929,367
- ( 25,129)
- _________
- 904,238
19Questions?
20Design-Build Project (cont.)