Title: Daimler-Chrysler Layered Process Audits (DCX LPA)
1Daimler-Chrysler Layered Process Audits(DCX LPA)
2Goal
- Satisfy Daimler-Chrysler mandated LPA (Layered
Process Audit) - Training of Managers and Supervisors
- Satisfy Customer Specific Requirements and
TS16949 requirements - Continual Improvement
3Continual Improvement
4Where are we now?
- No Layered Process Audits (LPA) are currently
being performed - Training has been started at SRAF (Today)
- Input in Chryslers Powerway will begin when LPAs
have started
5SRAFs Training
6Training
- Training will be Painless
- Training will be Hands on
- Training will encompass all management levels
- Training will be completed
7Kinda Painless
8Past History
- No history on LPA
- Were creating the line in the proverbial sand.
- Lessons Learned can and should apply
9SRAFs Line in the Sand
10What are our choices
- 1. Not performing LPAs?
- 2. Pitch in and get it done
11 The only Choice
- Pitch in and get it done and perform LPA as
required.
Why No Choices ?
12Daimler-Chrysler Mandated
13Farmington Managers and Supervisors
Daimler Chrysler
14What is a Layered Process Audit? (LPA)
- LPA is an ongoing system of process checks that
verify proper methods, settings, operator
craftsmanship, error proofing devices and other
inputs are in place to ensure a defect free
product.
15What is a Layered Process Audit (LPA)?
Continued
- LPAs assure that defined methods and work
instructions are utilized, problem solving
solutions are held in place, and all process
issues are identified and quickly corrected.
16What is a Layered Process Audit?
continued
- Two types of LPAs
- Auditing the Process itself
- Auditing the Error Proofing
171. Process Audit
18LPA Process Audit
19LPA Process Audit continued
202. Error Proofing Audit
21(No Transcript)
22How Long Will either LPA Take?
23What do we need to perform a LPA?
- A pen or pencil
- A Checklist
- Knowledge of the Process
- (A sense of humor helps)
- Commitment for success
24(No Transcript)
25LPA Frequency Plan
Plant Manager-once a week
Area Managers-once a week
Production Supervisors-once a shift
This Proposed Frequency will
Encourage Management Involvement Establish
Operator Feedback Establishes Accountability
26Where do we start ?
- Recommended starting point
- At the highest point of risk.
27SRA LPA Audit Frequency and Structure