Title: Master Slide
1Public Private Partnerships Financing Aspects of
PPPs
ALAIN TERRAILLON European Investment Bank
Concessions and Public-Private
Partnerships Ankara, 10-11 March 2008
2Overview
- Introduction
- What are PPPs
- What is project finance
- Risk allocation
- Financial structures for PPPs
- Role of equity, debt, mezzanine and subcontractor
finance - Issues for Senior Lenders
- How do Senior Lenders look at risk in PPP
transactions? - Issues for the Public Sector
- Why finance is important for the public sector
counterpart
3What are PPPs?
- Delivering public infrastructure through
procuring services rather than capital assets - Public sector defines service requirement
- Private sector designs, finances, builds,
operates, (usually transfers) the asset - Mainly private (not public) financing
- Fiscal environment EMU
- Does not exclude public component (e.g. from
Structural / Cohesion Funds) - Improve the efficiency and quality of public
services - Accelerating investment in infrastructure
- Achieving private sector efficiencies
4Features of PPPs
- Contracts for services, not procurement of assets
- Output, not input, specifications
- Payments related to service delivery
- Whole life approach to design, build and
operation - Private sector funding to underpin risk transfer
- Project Finance for all but smallest projects
5Project Finance
- Project Finance is specialised form of finance
based on - A stand alone project
- A Special Purpose Company (SPC) as the borrower
- High ratio of debt to equity (gearing)
- Lending based on project cash flows (not balance
sheet) - Lenders rely on project contracts, not physical
assets, as project security - Non recourse finance (ie no claim on investors)
- Finite project life (ie debt to be repaid at
project close, in contrast to corporate debt
which can be rolled over)
6Pops and Value for Money
- In principle, PPPs can improve VFM by
- Facilitating and incentivising on time and on
budget project implementation - No service / no pay
- Incentives to cost control
- Optimisation of capital maintenance spends over
project life - Innovation in design and financing structures
- Improving management of operational risks
- Optimal risk allocation ? reduced cost of risk
- Reduced cost of risk ? better Value for Money
7Structuring PPP transactions
- Alignment of risk, incentive and reward is the
key to value for money in PPP transactions - Improved management of risks reduces overall cost
of project - This reduced cost secures value for money
- Correct risk transfer also critical to securing
affordability - Risks are being priced that were previously left
unpriced - Pricing impact on current defined budgets (not
future undefined budgets) - Private funders play lead role in taking on,
allocating and managing PPP project risks
8Which risks?
- Meeting service delivery standards
- For example if the project design is unable to
meet service need, private sector must pay costs
of rectifying
9Which risks?
- Meeting service delivery standards
- For example if the project design is unable to
meet service need, private sector must pay costs
of rectifying - Cost overrun during construction
- For example unstable ground conditions requiring
additional foundations would be a private risk - On time completion
- For example if facility is delivered late due to
ground conditions, no payments until availability - Underlying and future costs of service delivery
- For example latent defects risk in an existing
building - Physical damage to a building
- Market risks in some projects
10UK Education PPP
Local authority (Promoter)
Equity providers
Ministry of Education
Educational services
Catering, cleaning, Security, energy etc
Concession Contract
Services Sub-contract
Students
Borrower / Concessionaire (the SPC)
Lifecycle maintenance
EIB
Lifecycle Sub-contract
Senior Loan
Construction Sub-contract
Commercial Banks/ Bondholders
Construction
Direct agreements
11Welsh DBFO Road - A55 project
Hyder Laing Tarmac
Welsh Office
Direct Agreement
DBFO Contract
Equity / subdebt
Laing Tarmac
Senior loan
Borrower / Concessionaire
EIB
Senior / Junior Loan
Commercial Banks
Construction guarantee
Construction contract
Construction joint venture
Direct Agreement
12Financial structuring
- Senior debt
- Mezzanine debt
- Equity
- Sub-contractor finance
13Financial structuring
- Senior debt
- Typically 80-90 of capital requirement
- Interest and repayment in priority to all other
capital - Seeks to minimise risk of unremedied failure of
PPP contractor - Disciplined approach to due diligence
- Pass through of risks
- Entitlement and incentive to step in to remedy
significant failings - Priced accordingly
14Financial structuring
- Sources of senior debt
- Bank debt
- Debt raised in capital markets
- With a financial guarantee (wrap) from a
monoline insurer (monoline takes risk) - Without a guarantee but rated by a rating agency
(investors take risk) - European Investment Bank
- With or without a guarantee / wrap
15Financial structuring
- Equity
- Typically 10-20 of capital requirement
- Shareholder loans that earn interest
(subordinated debt) - Share capital that receives a dividend
- Primary risk taking tier also seeks significant
pass through of risks - Equity funders paid to take this risk
16Financial structuring
- Equity
- Typically 10-20 of capital requirement
- Shareholder loans that earn interest
(subordinated debt) - Share capital that receives a dividend
- Sources include contractors and (increasingly)
institutional equity investors - Primary risk taking tier also seeks significant
pass through of risks - Equity funders paid to take this risk
17Financial structuring
- Mezzanine debt
- Lies between senior debt and equity in transfer
of risks - Repayment affected by poor performance before
senior debt - Return greater than senior debt
- Usually provided by banks offering senior debt
(ie prepared to accept a higher risk / return
tranche)
18Financial structuring
- Subcontractor finance
- SPV (and lenders) need assurance that contractors
can meet contingent obligations - Parent company guarantees
- Letters of credit
- Performance / surety bonds
- Providers of guarantees etc have no recourse
against SPV
19Implications for Senior Lenders
- Minimisation of risks retained by the SPV
- Gearing determines maximum value of risks that
can be retained in the SPV - Acceptable project structure
- Project agreement, sub contracts, financing
agreements, security package, insurance - Acceptable financial structure
- Sufficient liquidity
- Reserve accounts (debt service, lifecycle etc)
- Robust cashflows and acceptable waterfall
- Adequate cover ratios
20Cover ratios
Surplus cash senior lenders require to be
retained to meet (potential) shortfalls in debt
repayments
- Loan life cover ratio
- NPV of cash flow available for debt service
during the life of the debt - Debt principal outstanding
- Annual debt service cover ratio
- Cash flow available for debt service
- Debt service due in the period
21How do lenders control cash?
- Using ratios
- If base case minimum LLCR is, say, 1.30 and
ADSCR is 1.20 - At, say, LLCR 1.15 and ADSCR 1.10 equity
distributions stop (lock up) - At, say, LLCR 1.10 and ADSCR 1.05 borrower is in
default (default) - Other factors
- A range of other lock up and default
circumstances (reserve accounts not funded,
project agreement defaults, insolvency etc)
22Financial structuring
- Insurance
- Inability of SPV to take financial losses means
risks held by SPV must to maximum extent
possible be insured - Borrowers contractually required to hold a range
of insurances (construction, material damage, 3rd
party liability, business interruption,etc) - Lenders engage insurance advisors, and
implications of future insurance cost increases a
major issue in negotiating deals - What happens if an insured risk becomes
uninsurable?
23Risk and reward
- What happens when things go wrong?
- Implications for the public sector
24Where do the risks go?
Equity Banks Bondholders
Shareholders
Taxpayers
25When things go wrong
- Public sector defaults
- No fault defaults (Force Majeure)
- Private sector (concessionaire) defaults
26Public sector defaults
- Vires
- Can the public sector sign the contract?
- The public sector covenant
- Can the public sector be forced to pay?
- Public sector defaults
- Compensation on termination
- Debt plus some remuneration of equity on public
sector default
27Force Majeure
- No fault reasons for termination
- Public sector generally seeks to limit to prevent
risk transfer from private to public - UK contract does not include all Acts of God
e.g. bad weather - War, civil war, armed conflict, terrorism
- Nuclear, chemical, biological contamination not
caused by contractor - Pressure waves caused by devices travelling at
supersonic speed - Equity and debt back (but no equity return)
following force majeure termination
28Relief Events
- UK contracts defined as
- Fire, explosion, storm, flood, earthquake, riot
- Failure of e.g. power companies to supply power
- Accidental loss to the sites
- Fuel shortages
- General construction strikes (but not contractor
specific strikes) - Archaeological finds
- But only relief from termination principle of
no service, no pay remains
29Concessionaire default
- Concessionaire default means failure to meet the
terms of the concession contract - Termination of sub contractors (insolvency, poor
performance, corruption etc) - Technical due diligence
- Importance of liability caps
- Step-in by senior lenders
- Ability of lenders to act to save the project
- Public sector relies on lenders to control the
project - Importance of Direct Agreements and ability to
replace the concessionaire - Compensation on concessionaire termination
30Replacing sub contractors
- Sub contractors have a key role in taking risk in
PPP projects - Lenders look for contractual right and practical
options replacing non performing contractors - On termination, sub contractors typically
required to pay termination damages - Lenders seek unlimited damages, contractors seek
to limit these (for UK PPP construction
contracts, cap of 50 of contract value typical) - Lenders seek to be assured that damages payable
will be sufficient to meet additional costs with
a new contractor - Lenders will regard geographically remote or
highly specialised projects as particularly risky
31Compensation on termination
- Extent of compensation for lenders depends on the
cause of termination - Lenders will always require full compensation for
termination for authority default or authority
voluntary termination - UK PPPs lenders fully compensated for Corrupt
Gift and Force Majeure termination - Compensation for other concessionaire defaults
based on either Market Value (retendering) or
Fair Value (no retendering) methods
32Market value based compensation on termination
- A feature of UK schools and hospital PPPs
- Applies unless there is no liquid market in
concessions (defined as at least two potential
bidders) - On default by concessionaire, public authority
sells unexpired period of concession contract - Bidders determine what (capital) sum they will
pay to buy future cashflows bearing in mind
they must deliver service to achieve these
cashflows - Lenders compensation bid capital sum
- If no bids (or negative bids), compensation is
zero
33Fair value based compensation on termination
- Applies only where no liquid market
- Present value of future cash-flow over concession
minus present value of future costs minus
rectification costs lender compensation - In theory, fair value and market based
compensation should be identical - In practice, lenders would always prefer greater
certainty of fair value
34Conclusions What do senior lenders need?
- A clear public sector covenant
- A good understanding of the risks taken on by the
private sector - Limitation of the risks taken on by borrower
- Sound insurance arrangements
- A liquid market in sub-contracted services
- Step-in rights
- Appropriate compensation on termination
35Senior Lenders the public sectors best friend!
- Senior lender due diligence
- Public sector gains some reassurance on
deliverability from senior lender due diligence - Clear identity of interest with the public sector
once project is underway - Good project performance key to lenders being
repaid - Public sector looks to senior lenders to control
the project and deal with problems - Lenders take controls and powers necessary to do
this - Public sector should be wary of too tight cover
ratios and other financial parameters
36Issues for the public sector
- Public or private finance?
- Senior debt Bank or bonds?
- Refinancing
- Funding competitions
- Innovations in the funding market
37Public or private finance?
- Options for national funding
- Grants or loans?
- Public funding
- upfront capital or on-going revenue?
- budgetary resources and value for money
- Private finance
- Testing bankability
- Testing affordability
- Testing value for money (public sector comparator)
38Bank or bond?
- Bonds a debt instrument that pays bondholder a
rate of interest in return for bondholder paying
principal amount to the Issuer on issue - Repayment according to a pre agreed repayment
profile - Bonds issued by project companies, rated by
Rating Agencies - Investment grade bond minimum BBB- (SP) / Baa3
(Moodys) converted to AAA via monoline wrap - May be floating, fixed or index linked
39Bank or bond?
- Size In the UK, public bond issues unlikely to
be less than EUR 75 million - Maturities traditionally bonds offer longer
maturities (up to 40 years on some UK PPPs) - Flexibility generally bank debt more flexible as
(tradable) bond conditions fixed. Project
variations more easily dealt with in bank finance
(multiple bond holders) - Early redemption conditions may be
disadvantageous for bonds
40Refinancing
- PPP transactions typically refinanced to take
advantage of better funding conditions at some
stage - Usually post construction, when riskiest part of
project is complete - May be refinance from bank debt to bonds, or
increase in senior debt (i.e. reduction in equity
reflecting lower risk profile) - Issues for public sector
- Should it seek a share of refinancing gain?
- Implications of increased senior debt potential
increase of public sector contingent liability?
41Mechanics of LGTT
- Revenue shortfall during ramp-up -
stand-by-facility drawn to cover debt service - If stand-by-facility can be repaid during the
5-year ramp-up, guarantee not called - If revenues are insufficient to repay the
stand-by-facility during the 5-year ramp up, the
guarantee is called guarantee is then repaid
during project life from revenues left over after
senior debt service.
42Conclusions Implications for the public sector
- Realistic risk sharing expectations
- Clear legal and institutional framework
- Effective use of experienced advisors
- But also need for new public sector skills you
cannot leave it to the lawyers! - Focused, dedicated and experienced public sector
team PPP Task Force - Transparent and competitive procurement
- Recognition of lenders concerns