Title: The SPL-based Proton Driver at CERN
1The SPL-basedProton Driver at CERN
- OUTLINE
- 1. Introduction
- 2. SPL characteristics
- 3. On-going work
- 4. Staging
- 5. Summary and Conclusion
2SPL Working Group
REFERENCE
Conceptual Design of the SPL, a High Power
Superconducting Proton Linac at CERN Ed. M.
Vretenar, CERN 2000-012
31. Introduction
CERN baseline scenario for a Neutrino Factory
4Other applications of the proton driver
- Approved physics experiments
- CERN Neutrinos to Gran Sasso (CNGS) increased
flux ( 2) - Anti-proton Decelerator increased flux
- Neutrons Time Of Flight (TOF) experiments
increased flux - ISOLDE increased flux, higher duty factor,
multiple energies... - LHC faster filling time, increased operational
margin... - Future potential users
- Conventional neutrino beam from the SPL
super-beam - Second generation ISOLDE facility (EURISOL
-like) - LHC performance upgrade beyond ultimate
52. SPL characteristics
H- source, 25 mA 14 duty cycle
CCDTL
new SC cavities b0.52,0.7,0.8
Fast chopper (2 ns transition time)
- RF system
- freq. 352 MHz
- ampli. tetrodes and LEP klystrons
6Improvements w.r.t. the reference design
- Improved transitions between sections ? better
beam stability - Doubled period length above 1.1 GeV ? save 25
doublets, 8m, 3 MCHF - Improved error studies ? 100 beam radius lt 20
mm, even for large error case (30 ) ? quad.
radius reduced from 100 mm to 60 mm, (17rms) ?
save 2 - 3 MCHF - Reduced longitudinal emittance 0.6 ? 0.3 ?ºMeV
? improved design of the transfer line (drift
length 230 ? 175 m, bunch length 180 ? 130 ps) - Use of beta0.8 cavities up to the highest energy
? shorter tunnel (- 100 m), less cavities per
klystron, better control of mechanical resonances
7SPL beam specifications
8Accumulator-Compressor scheme
9Characteristics of the beam sent to the target
10Layout on the CERN site (top view)
11Cross section
123. On-going work
13Progress highlights
Chopper structure
3 D view of a coupled cavity drift tube
module (CCDTL)
Scaled model (1 GHz) in test
- Full performance prototype tested
- Driver amplifier in development
14Chopper
? Travelling wave electrostatic deflector,
meander line to match beam and wave velocity ?
Used to create gaps in the linac bunch
distribution between accumulator buckets ? Needs
very short rise/fall times (2 ns !) to avoid
partially deflected bunches ? Development of
pulser
1982mm (33 cells)
50 mm
accumulator bucket
15Study of RT structures for the SPL front-end
bl
Alvarez Drift Tube Linac unsurpassable lt20
MeV good but expensive for 20-120 MeV
bl
Cell Coupled Drift Tube Linac attractive solution
for 20-150 MeV (a cold model is being designed)
bl/2
Coupled-Cell Cavity (LEP1) better efficiency
gt110 MeV
quadrupole
quadrupole
The final choice will depend on preferred
apertures, RT final energy, etc.
16Superconducting cavities
- ? CERN technique of Nb/Cu sputtering
- for b0.7, b0.8 cavities (352 MHz)
- excellent thermal and mechanical stability
- (very important for pulsed systems)
- lower material cost, large apertures, released
- tolerances, 4.5 ?K operation with Q 109
The b0.7 4-cell prototype
? Bulk Nb or mixed technique for b0.52 (one 100
kW tetrode per cavity)
17RF and Superconducting cavities Parameters
18Pulsed operation of a LEP klystron set-up
RF output power (800 kW max.)
Mod anode driver
14/05/2001 - H. Frischholz
Þ LEP power supplies and klystrons are capable to
operate in pulsed mode after minor modifications
19RF power distribution field regulation in the
superconducting cavities
Effect on field regulation
Effect on the beam
Þ unsolved problem ! Needs work Þ similar
difficulties are likely in the muon
accelerators...
204. Staging
- Test of the 3 MeV H- injector
- Means strengthen collaboration with the
CEA-IN2P3 and jointly exploit the IPHI set-up - Contribute to the chopper and bunchers
- 120 MeV H- linac in the PS South Hall
- Goal increase beam intensity for CNGS and
improve characteristics of all proton beams (LHC,
ISOLDE) - Under study detailed design report with cost
estimate in 2003 - Needs new resources (collaborations, manpower,
money) - SPL
21Proton Intensity increase location of the SPL
front-end in the PS South Hall
PS
To the PSB
Beam dump
H- source
LEIR
Þ Increased brightness for LHC, 1.8 the flux to
CNGS ISOLDE, (with upgrades to the PSB, PS
SPS) Þ cheap installation, giving benefits from
SPL related hardware before the full machine is
operational shortening the final setting-up
225. Summary and Conclusion
- The SPL design is improving
- Work is started on most items, based on
collaborations - A staged approach is proposed
- Feedback (and support !) is needed from potential
users