The MiniBooNE Horn - PowerPoint PPT Presentation

About This Presentation
Title:

The MiniBooNE Horn

Description:

The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration – PowerPoint PPT presentation

Number of Views:82
Avg rating:3.0/5.0
Slides: 59
Provided by: BDMacOffi8
Category:
Tags: miniboone | horn | steel | truss

less

Transcript and Presenter's Notes

Title: The MiniBooNE Horn


1
The MiniBooNE Horn
  • Ioanis Kourbanis
  • For
  • The MiniBooNE Collaboration

2
Outline
  • List of people
  • Horn characteristics
  • Horn Power Supply
  • Horn Striplines
  • Highlights of Horn Construction and Assembly
  • Horn Testing
  • Horn Changeover
  • Future Plans

3
List of People
  • C. Anderson
  • L. Bartotzek (Bartoszek Engineering)
  • L. Bartelson
  • L. Bugel
  • C. Jensen
  • H. Le
  • B. Markel (Markel Associates)
  • J. Misek
  • F. Nezrick
  • H. Pfeffer
  • R. Reilly
  • D. Snee
  • M. Sorel
  • E. Zimmerman

4
Horn Characteristics
  • We are using one horn with a narrow neck and a
    conical inner conductor (BNL Design) designed to
    run at a current of 170 KA.
  • The horn is made out of Al alloy 6061-T6 and is
    excited by a 143 ?sec current pulse.
  • Keep the voltage at the PS below 10 KV (use solid
    state SCRs instead of thyristors)
  • Reduce the current pulse width as much as
    possible to avoid excessive heating of the horn .
  • Keep the voltage at the horn as low as possible
    (small inductance).
  • The horn will operate at an average rep rate of 5
    Hz. Total average power deposited in the horn is
    2.4 KW.

5
3-D Model of the Horn
6
Horn Power Supply
  • The Power Supply consists of a Capacitor bank
    (1,344 ?F) discharged through an inductive load
    by an SCR switch. The system has a separate
    circuit for energy recovery.
  • The circuit is divided into 16 parallel
    capacitors, each with its own SCR switch.

7
Horn PS Parameters
8
Power Supply Schematic
9
Power Supply View (Front)
10
Power Supply View (Back)
11
Horn Stripline
  • Balanced design (odd number of conductors) to
    minimize forces.
  • The conductor spacing is 1 inch. Fluted alumina
    insulators with a 2 inch creepage length were
    used to separate the conductors.
  • The test stripline piece, along with a clamped
    joint, were corona tested.
  • The inductance of the final stripline was
    measured to be 18.5 nH/m.

12
View of the Long Stripline Section
13
View of a Stripline Joint
14
View of the Small Stripline Section
15
Construction and Assembly Highlights
  • Forged Outer Conductor
  • The water sprayers were vibration isolated from
    the Horn Outer Conductor.
  • Solid connections from the striplines to the
    Horn.
  • The Horn Inner Conductor was welded at Fermilab
    using a programmable TIG welding machine.

16
Outer Conductor after Forging
17
Outer Conductor after Machining
18
Outer Conductor after Welding
19
Water Manifolds
20
Water Truss
21
Water Truss and Water Manifolds
22
Water Truss Bellows Detail
23
Water Connection Detail
24
Outer Conductor with Water Truss
25
Water Drain Connection
26
Water Nozzle Detail
27
Twist Transitions
28
Inner Conductor Before Welding
29
Hand Scraping before Welding
30
Welding Sample
31
Large Weld
32
Small Diameter Weld
33
Inspecting the Small Diameter Weld
34
Radiography of Weld
35
Radiography of Large Weld
36
Moving the Inner Conductor from The Welding
Machine
37
Inserting the Inner into the Outer Conductor
38
Horn Testing
  • The horn was pulsed for the first time on
    07/27/01.
  • The horn test was completed on 02/12/02 after
    completing 11M pulses at full current.
  • We completed horn magnetic field measurements.
  • Completed a series of vibration measurements.
  • Things we were monitoring
  • Total current
  • Current in the four striplines feeding the horn
  • Total voltage
  • Cooling water supply and return temperatures
  • Horn temperatures

39
Overview of MI-8 Test Area
40
Horn module overview
41
Stripline Configuration at the TSB
42
Current and Voltage Profiles
43
Horn Magnetic Field Measurement
44
Horn Temperature Profiles with Different Sprayer
Configurations
45
Correlation between Horn and Water Return
Temperatures
46
Horn Vibration Spectrum
47
Horn Axial Displacement vs. Time
48
Horn Changeover
  • The horn module is expected to be highly
    radioactive (30 Rad/hr at 2 ft).
  • In order to reduce the Radiation Exposure to
    under 100 mR/hr at 1 ft, the shielding
    requirement is 5 of steel on all sides.
  • Because of the crane lifting capacity, two
    separate coffins (an inner and an outer ) will be
    used.
  • The inner coffin has 1.5 thick walls except
    from the top cover and the front door (5 thick).
  • The outer coffin has 3.5 thick walls and is open
    at the top and the front.

49
Horn Changeover (2)
  • The radioactive horn module will be stored inside
    the two coffins in the Target Service Building in
    the old Proton Line.
  • Four coffins (two inner and two outer coffins)
    will be needed for a changeover.
  • A detailed procedure outlining all the steps for
    a changeover has been written and reviewed.
  • Total estimated time for a changeover is 2 weeks.

50
Inner Coffin
51
Outer Coffin
52
Initial Configuration
53
Inner and Outer Coffins
54
Open Inner Coffin Door
55
Position the Coffins next to the Horn Module
56
Pull the Horn Module in the Coffin
57
Close Inner Coffin Door
58
Future Plans
  • We have started disassembling the Power Supply
    and the Striplines.
  • The horn modules will be stored in the inner
    coffin.
  • Plan to install the horn in the target pile on
    May 7.
  • We estimate to be ready for a horn changeover
    test on May 15.
  • We should be ready for beam on June 15.
  • We have started ordering the large pieces for a
    spare horn.
Write a Comment
User Comments (0)
About PowerShow.com