Title: The MiniBooNE Horn
1The MiniBooNE Horn
- Ioanis Kourbanis
- For
- The MiniBooNE Collaboration
2Outline
- List of people
- Horn characteristics
- Horn Power Supply
- Horn Striplines
- Highlights of Horn Construction and Assembly
- Horn Testing
- Horn Changeover
- Future Plans
3List of People
- C. Anderson
- L. Bartotzek (Bartoszek Engineering)
- L. Bartelson
- L. Bugel
- C. Jensen
- H. Le
- B. Markel (Markel Associates)
- J. Misek
- F. Nezrick
- H. Pfeffer
- R. Reilly
- D. Snee
- M. Sorel
- E. Zimmerman
4Horn Characteristics
- We are using one horn with a narrow neck and a
conical inner conductor (BNL Design) designed to
run at a current of 170 KA. - The horn is made out of Al alloy 6061-T6 and is
excited by a 143 ?sec current pulse. - Keep the voltage at the PS below 10 KV (use solid
state SCRs instead of thyristors) - Reduce the current pulse width as much as
possible to avoid excessive heating of the horn . - Keep the voltage at the horn as low as possible
(small inductance). - The horn will operate at an average rep rate of 5
Hz. Total average power deposited in the horn is
2.4 KW.
53-D Model of the Horn
6Horn Power Supply
- The Power Supply consists of a Capacitor bank
(1,344 ?F) discharged through an inductive load
by an SCR switch. The system has a separate
circuit for energy recovery. - The circuit is divided into 16 parallel
capacitors, each with its own SCR switch.
7Horn PS Parameters
8Power Supply Schematic
9Power Supply View (Front)
10Power Supply View (Back)
11Horn Stripline
- Balanced design (odd number of conductors) to
minimize forces. - The conductor spacing is 1 inch. Fluted alumina
insulators with a 2 inch creepage length were
used to separate the conductors. - The test stripline piece, along with a clamped
joint, were corona tested. - The inductance of the final stripline was
measured to be 18.5 nH/m.
12View of the Long Stripline Section
13View of a Stripline Joint
14View of the Small Stripline Section
15Construction and Assembly Highlights
- Forged Outer Conductor
- The water sprayers were vibration isolated from
the Horn Outer Conductor. - Solid connections from the striplines to the
Horn. - The Horn Inner Conductor was welded at Fermilab
using a programmable TIG welding machine.
16Outer Conductor after Forging
17Outer Conductor after Machining
18Outer Conductor after Welding
19Water Manifolds
20Water Truss
21Water Truss and Water Manifolds
22Water Truss Bellows Detail
23Water Connection Detail
24Outer Conductor with Water Truss
25Water Drain Connection
26Water Nozzle Detail
27Twist Transitions
28Inner Conductor Before Welding
29Hand Scraping before Welding
30Welding Sample
31Large Weld
32Small Diameter Weld
33Inspecting the Small Diameter Weld
34Radiography of Weld
35Radiography of Large Weld
36Moving the Inner Conductor from The Welding
Machine
37Inserting the Inner into the Outer Conductor
38Horn Testing
- The horn was pulsed for the first time on
07/27/01. - The horn test was completed on 02/12/02 after
completing 11M pulses at full current. - We completed horn magnetic field measurements.
- Completed a series of vibration measurements.
- Things we were monitoring
- Total current
- Current in the four striplines feeding the horn
- Total voltage
- Cooling water supply and return temperatures
- Horn temperatures
39Overview of MI-8 Test Area
40Horn module overview
41Stripline Configuration at the TSB
42Current and Voltage Profiles
43Horn Magnetic Field Measurement
44Horn Temperature Profiles with Different Sprayer
Configurations
45Correlation between Horn and Water Return
Temperatures
46Horn Vibration Spectrum
47Horn Axial Displacement vs. Time
48Horn Changeover
- The horn module is expected to be highly
radioactive (30 Rad/hr at 2 ft). - In order to reduce the Radiation Exposure to
under 100 mR/hr at 1 ft, the shielding
requirement is 5 of steel on all sides. - Because of the crane lifting capacity, two
separate coffins (an inner and an outer ) will be
used. - The inner coffin has 1.5 thick walls except
from the top cover and the front door (5 thick). - The outer coffin has 3.5 thick walls and is open
at the top and the front.
49Horn Changeover (2)
- The radioactive horn module will be stored inside
the two coffins in the Target Service Building in
the old Proton Line. - Four coffins (two inner and two outer coffins)
will be needed for a changeover. - A detailed procedure outlining all the steps for
a changeover has been written and reviewed. - Total estimated time for a changeover is 2 weeks.
50Inner Coffin
51Outer Coffin
52Initial Configuration
53Inner and Outer Coffins
54Open Inner Coffin Door
55Position the Coffins next to the Horn Module
56Pull the Horn Module in the Coffin
57Close Inner Coffin Door
58Future Plans
- We have started disassembling the Power Supply
and the Striplines. - The horn modules will be stored in the inner
coffin. - Plan to install the horn in the target pile on
May 7. - We estimate to be ready for a horn changeover
test on May 15. - We should be ready for beam on June 15.
- We have started ordering the large pieces for a
spare horn.