Measurement and Payment Construction Progress Payments Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed (quantities) RPR ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 15
Provided by: AndrewW184
Category:

less

Transcript and Presenter's Notes

Title: Measurement and Payment


1
Measurement and Payment
2
  • Construction Progress Payments
  • Contractor gives a bill for progress to RPR
  • Outlines what bill is for
  • Give details as needed (quantities)
  • RPR reviews
  • Approves (sends to owner) or disapproves (calls
    contractor)
  • Contractor gets paid

3
  • Approval of Payment Requests
  • RPR responsible for checking quantities and costs
  • Quantity take off
  • Inventory of equipment and materials on site but
    not used
  • Field measure work completed or claimed
  • Construction Cost Estimate of all completed work
  • Audit of Invoices and costs
  • Review of claims for extra work and completed
    change orders
  • Check of retention amount
  • Check method used for profit and overhead,
    material costs for estra work or change orders

4
  • Basis for Payment Amounts
  • Accuracy of field measurements determined by
    contract type
  • Lump sum contracts do not need accurate field
    measurements
  • Cost plus or Unit price contracts need very
    accurate field measurements
  • Pg 432

5
Schedule of Values v. Cost loaded CPM Schedule
  • Unit Price Contracts
  • Do not call for Cost Loaded CPM Schedule
  • Conflicts with line items on unit price sheet
  • Do not call for schedule of Values
  • A breakdown of all line items is submitted w/
    contractors bid and is binding throughout job

6
  • Lump Sum Contracts with Cost Loaded CPM
  • Do not ask for Schedule of Values cost loaded
    CPM is equal
  • Request Cost loaded CPM be submitted before first
    pay period ends
  • Lump Sum Contracts w/o Cost loaded CPM
  • Do not ask for a cost loaded CPM schedule
  • Do not ask for a bid breakdown
  • Request a schedule of values before starting work
    on project

7
Evaluation of Contractors Payment Requests
  • Contractor submits request for payment at a
    prearranged date each month for previous months
    work
  • Lump sum contract payment based on a fair
    estimate of work completed plus overhead and
    profit
  • Unit Price Contracts contractor gets paid based
    on quantity used RPR must have accurate field
    measurements
  • /- 25 is okay more or less allows for
    renegotiations by either party

8
  • Equipment And Materials delivered but not used
  • Contractor brings stuff on site early
  • May try to bill owner since stuff is on site
  • Contractor only paid when stuff is used
  • Includes materials used but not completed pipe
    not paid for until covered and tested
  • Unit price contracts are usually for installed in
    place materials on site is not in place
  • Can make exceptions for long lead items which
    arrive on site early

9
  • Force Account
  • Daywork or for any type of cost plus payment
  • In US associated with extra work and change
    orders
  • May be used to pay contractor when it is
    difficult to provide adequate measurements or
    estimate cost of certain items of work
  • Should be last choice when setting up items for
    payment

10
Force Account
  • Change order is a must
  • Force account payments not authorized for supers.
    Allowances for supers is in contractors OP.
    Foremen working full time on item would be
    covered by account
  • PM has authority to direct every aspect of force
    account work

11
  • PM and Contractor must agree on
  • Labor
  • Classification and approximate N of workers, wage
    rates, travel allowance, subsistence, are foremen
    included
  • Equipment
  • Types to be used including size, rating,
    capacity, which indicate that item can do work
    required, owned or leased, cost per hour for use
  • Materials
  • Cost and freight charges, purchased for project
    or from contractors stock

12
  • PM prepares lists of equipment and labor
    classifications actually used and corresponding
    rates
  • Equipment list includes complete nomenclature of
    the equipment to establish rental rate from a
    Rental Rate Book
  • Labor list includes labor classification and
    composite hourly rate (basic wage added costs
    listed in DOT standard specs)

13
  • Payments for Extra Work and Change Orders
  • Usually laid out in Contract
  • Common is cost plus with a reasonable allowance
    for OP
  • State agencies may allow 15, 20, 24,33 on labor
    and then 15 on equipment, 15 on materials 5 on
    primary subs (not subs subs)

14
  • RPR must evaluate all change orders and requests
    for payment of extra work
  • RPR should consult PM or owner to determine the
    exact terms of the agreement that cover extra
    work
  • RPR keeps daily record of extra work performed
    and materials used