Software Process and Project Metrics - PowerPoint PPT Presentation

About This Presentation
Title:

Software Process and Project Metrics

Description:

Title: Transparency Masters for Software Engineering: A Practitioner's Approach, 4/e Author: Roger Pressman Last modified by: paulp Created Date – PowerPoint PPT presentation

Number of Views:127
Avg rating:3.0/5.0
Slides: 20
Provided by: RogerPr4
Learn more at: http://www.cs.uky.edu
Category:

less

Transcript and Presenter's Notes

Title: Software Process and Project Metrics


1
Software Process and Project Metrics
0
2
Normalization for Metrics
0
3
Typical Size-Oriented Metrics
0
  • errors per KLOC (thousand lines of code) or FP
  • defects per KLOC or FP
  • per LOC or FP
  • page of documentation per KLOC or FP
  • errors / person-month
  • LOC per person-month
  • / page of documentation

4
Why Opt for Function Point (FP) Measures?
0
5
Analyzing the Information Domain
0
6
Taking Complexity into Account
0
7
LOC per Function Point
0
  • Assembly language 320
  • C
    128
  • COBOL
    106
  • Fortran
    106
  • C
    64
  • Visual Basic
    32
  • Smalltalk
    22
  • SQL
    12

8
Criticism of Function Point measurement
  • The weighting factor makes the FP number highly
    dependent on the developers experience
  • The developer can essentially set the FP number
    to what the developer wants

9
(All? Most?) Projects are Late
0
  • Project estimation is difficult
  • Effort is not progress
  • Management sets unrealistic goals
  • Schedules poorly monitored
  • Brooks law adding persons to a late project
    makes it later
  • NOTE Your project will note be late!

10
Partitioning Tasks
0
  • Perfectly partitionable task
  • Unpartitionable task
  • Partitionable task requiring communication
  • Task with complex interelelationships

11
Programmers are Optimists
0
  • All will go well (Murphys Law doesnt apply to
    our project)
  • Each task will only take as long as it ought to
    take
  • No one (on our project) will ever get sick, take
    vacation time, or have family emergencies
  • Programmers get to spend all their time
    programming (never in meetings, conferences,
    travel)

12
Brooks Scheduling Rule of Thumb
0
  • 1/3 Planning
  • 1/6 Coding
  • 1/4 component and early system test
  • 1/4 system test
  • 40-20-40 rule (40 design, 20 code, 40 test)
  • Testing is usually the most mis-scheduled part
    of programming

13
Piwowarski Scheduling Algorithm
0
  • Estimate all tasks assuming the experience of the
    person doing it (not yourself)
  • Add 25 to this for overhead (meetings, vacation,
    travel, etc.)
  • Add 25 of the previous step for contingency
    (nothing ever goes right)
  • If you do the above .

14
0
  • You still may be late!

15
Scheduling Example
0
  • All tasks to be done by your team (including
    testing documentation, etc.) 160 PM
  • Add 25 for overhead 200 PM
  • Add 25 for contingency 250 PM
  • The final number is over 50 greater than the
    original estimate of actual work that needs to
    be done

16
Programmer Productivity
0
  • Is lower (in LOC per PM) than you think!
  • Studies and models (Brooks, Pressman) vary widely
  • Some projects at IBM used a rule of thumb of
    100-200 lines per person month

17
Productivity
0
  • Reasons for low LOC/PM (see Programmers are
    Optimists)
  • Productivity highly dependent on the task
  • System Code vs. application code
  • New programs vs. modification to current programs
  • Experience of programmers
  • 10 to 1 difference in programmer productivity
  • No formula will work
  • You must make adjustments for your project

18
Brooks Advice for Late Projects
0
  • DONT ADD PERSONS TO A LATE PROJECT
  • But you can
  • Reschedule (but take no small slips) Cant be
    done for your project
  • Trim the task (drop the unneeded features - the
    bells and whistles)

19
What can be done for CS499 projects
  • START ON TIME AND KEEP TO YOUR SCHEDULE
  • Have project checkpoints during the semester to
    keep you to your schedule
  • Drop the bells and whistles (but check with
    your customer first), BUT
  • Make sure essential customer requirements are met
Write a Comment
User Comments (0)
About PowerShow.com