OPSM 301 Operations Management - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

OPSM 301 Operations Management

Description:

Ko University OPSM 301 Operations Management Class 9: Project Management: PERT and project crashing Zeynep Aksin zaksin_at_ku.edu.tr – PowerPoint PPT presentation

Number of Views:157
Avg rating:3.0/5.0
Slides: 29
Provided by: OCA82
Category:

less

Transcript and Presenter's Notes

Title: OPSM 301 Operations Management


1
OPSM 301 Operations Management
Koç University
  • Class 9
  • Project Management
  • PERT and project crashing

Zeynep Aksin zaksin_at_ku.edu.tr
2
Announcements
  • Change in syllabus plan as follows
  • Will swap last session on project management with
    decision trees
  • Last session of project management will be after
    the bayram on 8/11
  • Class will be held in the lab (TBA)
  • Second group assignment will be due
  • We will have quiz 2 on Project Management
  • Decision Trees will be on 1/11
  • Quiz 3 on 10/11 Thursday

3
Example
Suppose you are an advertising manager
responsible for the launch of a new media
advertising campaign. The campaign (project) has
the following activities Activity Predecessors
Time A. Media bids none 2 wks B. Ad
concept none 6 C. Pilot layouts B 3 D.
Select media A 8 E. Client approval A,C 6 F.
Pre-production B 8 G. Final production E,F 5 H
. Launch campaign D,G 0
4
CPM with Three Activity Time Estimates
5
Some CPM/PERT Assumptions
  • Project control should focus on the critical path
  • The activity times in PERT follow the beta
    distribution, with the variance of the project
    assumed to equal the sum of the variances along
    the critical path

6
Beta Distribution Assumption
Assume a Beta distribution
density
activity duration
7
Beta Distribution Assumption
density
activity duration
m
a
b
8
Expected Time and Variance
a 4m b 6
Expected Time
(b - a)2 36
Variance
9
Expected Times
10
21 32
7 21
C, 14
E, 11
0 7
32 36
21 32
7 21
H, 4
A, 7
0 7
7 12
32 36
12 19
36 54
0 0
D, 5
F, 7
Start 0
I, 18
25 32
20 25
0 0
36 54
0 5.33
5.33 16.33
B 5.33
G, 11
19.67 25
25 36
11
Expected Completion Time 54 Days
C, 14
E, 11
H, 4
A, 7
D, 5
F, 7
Start 0
I, 18
B 5.33
G, 11
12
What is the probability of finishing this project
in less than 53 days? We need the variance also!
D53
13
Sum the variance along the critical path
14
Pr(t lt D)
t
TE 54
D53
p(z lt -.156) .436, or 43.6
There is a 43.6 probability that this project
will be completed in less than 53 weeks.
15
PERT Probability Example
  • Youre a project planner for General Dynamics. A
    submarine project has an expected completion time
    of 40 weeks, with a standard deviation of 5
    weeks. What is the probability of finishing the
    sub in 50 weeks or less?

16
Converting to Standardized Variable
-
-
X
T
50
40



Z
2
0
.
s
5
Normal Distribution
Standardized Normal Distribution
s
1
s
5
Z
40
50
X
m
T
Z
0
2.0
z
17
Obtaining the Probability
Standardized Normal Probability Table (Portion)
Z
.00
.01
.02
s
1
0.0
.50000
.50399
.50798
Z




.97725
.97725
.97784
.97831
2.0
m
Z
0
2.0
.98214
.98257
.98300
2.1
z
Probabilities in body
18
Variability of Completion Time for Noncritical
Paths
  • Variability of times for activities on
    noncritical paths must be considered when finding
    the probability of finishing in a specified time.
  • Variation in noncritical activity may cause
    change in critical path.

19
Time-Cost Models
  • Basic Assumption Relationship between activity
    completion time and project cost
  • Time Cost Models Determine the optimum point in
    time-cost tradeoffs
  • Activity direct costs
  • Project indirect costs
  • Activity completion times

20
Project Costs vs. Project Duration
21
Cost Analysis
  • We assume a linear relation between activity
    duration and activity cost
  • Regulate activity durations to minimize the total
    project cost

22
Cost Analysis
  • We require two time estimates and two associated
    cost estimates
  • Normal Time Time required if a usual amount of
    resources are applied to the activity.
  • Normal Cost Cost of completing an activity in
    normal time.
  • Crash Time Least time that an activity can be
    performed in if all available resources are
    applied to it.
  • Crash Cost Cost of completing an activity in
    crash time.
  • Incremental Cost
  • I (Crash Cost - Normal Cost)/(Normal Time -
    Crash Time)
  • ICost of reducing duration of an acitivity by 1
    unit of time

23
Crash and Normal Times and Costs for Activity B
24
Steps for Solution
  • 1. Perform PERT analysis using normal times and
    calculate I for all critical activities
  • 2. Pick the activity (critical) with the smallest
    I and shorten its duration as much as possible.
    That is, until
  • a. Duration reaches crash time
  • b. Another path becomes critical
  • 3. If duration of the project cannot be reduced
    any more, then stop otherwise return to the
    second step
  • The above process results in the modified crash
    program.

25
Example
NT,CT
NT
4,2
CC,NC
B
(normal time, crash time)
4
8
4
5
4,2
9
2,1
D
0
4
11
50,30
9
4
2
9
4
0
11
5, 2
C
4
9
70,10
100,10
4
5
9
(crash cost, normal cost)
65,50
26
Solution Procedure
  • Crash the activity with smallest I (least cost)
  • Check if critical path changed at each step
  • Continue crashing until satisfied or not possible
  • Total Cost Indirect cost direct cost,
  • Minimum Cost schedule is the one that has minimum
    total cost

27
Advantages of PERT/CPM
  • Especially useful when scheduling and controlling
    large projects.
  • Straightforward concept and not mathematically
    complex.
  • Graphical networks aid perception of
    relationships among project activities.
  • Critical path slack time analyses help pinpoint
    activities that need to be closely watched.
  • Project documentation and graphics point out who
    is responsible for various activities.
  • Applicable to a wide variety of projects.
  • Useful in monitoring schedules and costs.

28
Limitations of PERT/CPM
  • Assumes clearly defined, independent, stable
    activities
  • Specified precedence relationships
  • Activity times (PERT) follow beta distribution
  • Subjective time estimates
  • Over-emphasis on critical path
Write a Comment
User Comments (0)
About PowerShow.com